IN THE HIGH COURT OF DELHI AT NEW DELHI
S. MURALIDHAR, J.
LANCO INFRATECH LTD. – Petitioner
Versus
HINDUSTAN CONSTRUCTION COMPANY LTD. – Respondent
ARB. A. (COMM.) 30 of 2016
Decided On : 23-09-2016
Arbitration and Conciliation Act, 1996 - Lanco Infratech Ltd. - Arbitration and Conciliation Act, 1996, Section 17
Fact of the Case:
Lanco appealed against an order directing them to furnish a bank guarantee to the Respondent. Disputes arose from contracts for civil works of a hydroelectric project. Lanco disputed the claims made by the Respondent and challenged the constitution of the Arbitral Tribunal.
Finding of the Court:
The Court found that the Arbitral Tribunal erred in directing Lanco to furnish a bank guarantee as the claims were speculative and not certified. The Tribunal also misinterpreted the contract clauses and failed to establish Lanco's financial distress.
Issues: The issues revolved around the scope of the Arbitral Tribunal's powers under Section 17 of the Act, the nature of the claims, and Lanco's financial status.
Ratio Decidendi: The Court clarified that the Tribunal's power to order interim measures is limited and should be based on non-speculative claims. It emphasized the need for certification of claims and the requirement to establish a prima facie case of financial distress before issuing interim orders.
Final Decision: The appeal was allowed, and the impugned order of the Arbitral Tribunal was set aside. The Tribunal was directed to pass the final Award independent of the set-aside order.
1. This appeal under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996 filed by Lanco Infratech Ltd. (‘Lanco’) is directed against an order dated 4th June, 2016 passed by the Arbitral Tribunal (‘AT’) allowing the application filed by the Respondent Hindustan Construction Company Ltd. (‘HCCL’) under Section 17 of the Act and directing Lanco to furnish a bank guarantee to the extent of 50% of the amount claimed by HCCL within 30 days in an approved RBI format for an initial period of 12 months and to be kept renewed from time to time upto 30 days from the date of pronouncing of the Arbitral Award.
2. The background to the present appeal is that Lanco is part of the Lanco conglomerate group known as the 'Lanco Group' which has various subsidiaries dealing with power infrastructure, construction, real estate etc. Lanco entered into two contracts for civil works of Power House, transformers and Butterfly Valve Caverns and switch yard of Teesta VI Hydroelectric Project, Sikkim and Contract No. LITC/Contract/Teesta-VI/4B i.e., LOT IV B and for civil works for various tunnels from RD 10370 upto junction with the bottom of Surge Tunnels including Adit Tunnels- IVA and IV near Subin Khore of Teesta-VI, Hydroelectric Project, LOT IV B on 25th June, 2008. Disputes that arose between the parties were unable to be resolved through mutual discussions. HCCL then invoked the arbitration clause and nominated its Arbitrator. The Institution of Engineers (India) appointed an Arbitrator on behalf of Lanco and in turn both the Arbitrators appointed the presiding Arbitrator and completed the AT.
3. The challenge to the constitution of the AT was disposed of by this Court by order dated 19th January, 2015 leaving it open to the Lanco to raise this challenge before the AT itself. Thereafter, a challenge was raised by Lanco in an application under Section 16 of the Act which was negatived by the AT by an order dated 4th April, 2015.
4. Lanco states that on 30th April, 2015 it received a copy of the Statement of Claim filed by HCCL which, for the LOT IVA, was for the sum of Rs. 32,64,31,545 and for LOT IV B in the sum of Rs.184,05,09,141. Lanco filed its Statement of Defence on 3rd December, 2015.
5. The admission/denial of documents took place on 6th January, 2016. According to Lanco, since no original document was filed by HCCL, it made a statement that the said documents could neither be admitted nor denied as they were only photocopies. Thereafter, HCCL filed an application under Section 17 of the Act seeking interim measures requiring Lanco to furnish a suitable security in the form of a bank guarantee, fixed deposit or in any other form which would be sufficient to satisfy the arbitral award that may be passed in favour of HCCL against the claims for LOT IV-A and LOT IV-B. Inter alia it was contended by HCCL that it had a good prima facie case on merits, and that on various occasions, Lanco itself had admitted its liability and had assured to pay a certain sum to HCCL and that Lanco was suffering from financial constraints as was evident from its balance sheet, profit and loss account and the fact that winding up petitions were pending against it in various courts. Further, Lanco was stated to be undergoing a Strategic Debt Re-structuring (‘SDR’).
6. Before the AT, it was contended by Lanco that it had already disputed the correctness of HCCL’s claims as well as the documents produced by it and that the claims were totally fictitious and arbitrary. It was stated that the claims which were essentially towards overhead costs, expenses towards retention of equipments, loss of earning capacity and profit etc. far from being admitted by Lanco were bogus, false and fabricated and without any basis and, therefore, the question of securing such claims did not arise. It was pointed out that the proceedings before the AT were on account of HCCL’s own failure to meet its contractual commitment and, therefore, it could not take advantage of its
Adhunik Steels Ltd. v. Orissa Manganese and Minerals (P) Ltd.
Gatix India Pvt. Ltd. v. Arshiya Rail Infrastructure Ltd.
H. M. Kamaluddin Ansari & Co. v. Union of India
Iron & Hardware (India) Co. v. Firm Shamlal & Bros.
Intertoll ICS Cecons v. National Highways Authority of India
Raman Tech. & Process Engg. Co. v. Solanki Traders
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.