COURT OF APPEAL PUTRAJAYA
ASIAPOOLS (M) SDN BHD – Appellant
Versus
IJM CONSTRUCTION SDN BHD – Respondent
| Table of Content |
|---|
| 1. facts of the case and parties involved. (Para 1 , 5 , 31) |
| 2. arguments regarding payment obligations. (Para 6 , 7 , 11 , 12) |
| 3. court's analysis of case law on contract clauses. (Para 8 , 9 , 10 , 13) |
| 4. precedents from other jurisdictions on payment clauses. (Para 19 , 20 , 21) |
| 5. final decision regarding payment liability. (Para 25 , 27 , 28) |
| 6. interpretation of contractual clauses. (Para 50 , 52) |
Appeal
[1] Parties are referred to in their capacities in the Sessions Court.
[2] The Kuala Lumpur Sessions Court had allowed the plaintiffs claim with costs against the defendant.
[3] The defendants appeal to the High Court was allowed with costs. The High Court made a further order that the judgment sum of RM271,458.29, paid by the defendant to the plaintiff, be returned to the defendant, together with interest at 8% p.a.
[4] The plaintiff has now appealed to this Court.
Finding Of Facts
[5] The facts at the trial are not in dispute. The plaintiff was the nominated sub-contractor to build, inter alia, a swimming pool for a 161-unit condominium in Seremban. The defendant had earlier entered into a main contract with the developer ("the employer"), Ng Chee Yew S
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.