Jharkhand Mandates Payment of Contractor Dues Following Admission
In a significant ruling, the of Jharkhand at Ranchi has affirmed that a state entity’s voluntary return of a acts as a of satisfactory work completion. Justice Ananda Sen, presiding over the case, directed the payment of totaling months of work performed by for the .
Unresolved Liabilities and Contractual Deadlines
The dispute originated from the "Harmu River Rejuvenation Project," initiated in . While the primary project concluded in , the contractor continued Operation and Maintenance (O&M) services until . Following the expiry of the agreement, the contractor alleged that JUIDCO failed to release its final billing (R.A. Bill No. 29), withheld O&M payments, and continued to demand the maintenance of a bank guarantee despite the contract's closure. The petitioner contended that they were forced to remain on-site because the project site was never formally handed back to the authorities.
The Tug-of-War Over Admitted Dues
The petitioner argued that official communications served as proof of work completion and that the withholding of funds was arbitrary. Conversely, JUIDCO defense counsel asserted that the matter involved complex questions of fact—such as project quality and technical scrutiny—that should be relegated to arbitration, noting that the petitioner's ongoing site presence lacked a formal extension agreement. However, JUIDCO’s counsel eventually admitted during the proceedings that the had been released to the contractor just days prior.
Legal Reasoning: Conduct as Evidence
Justice Ananda Sen emphasized that is appropriate for money claims when the dispute does not require complex or elaborate evidence. Citing established jurisprudence, the Court noted that there is no absolute bar against settling under . Importantly, the Court held that the respondents cannot claim that work was unsatisfactory while simultaneously releasing the very performance guarantee meant to secure that same work. This "" effectively nullified the respondents' attempt to create a "feigned" dispute regarding work quality.
Key Observations
-
"This voluntary release of the Bank Guarantee in favour of the petitioner now will have a great ramification in this case."
-
"The work has been completed by the petitioner is not disputed."
-
"The question of viability of the project cannot be raised after the contract has been awarded to complete the project."
-
"This act of release of Bank Guarantee is an admission of the respondent by conduct in support of the fact of unblemished completion of the work."
Final Directions
In light of these findings, the ordered the respondents to settle all outstanding payments, including the R.A. Bill No. 29 and the sixteen months of post-contract maintenance work, within sixty days. Furthermore, the Court mandated that these payments include interest at a rate of 10% per annum from the date they became due. This decision reinforces that state projects cannot unilaterally withhold payments for services accepted through conduct, shielding contractors from long-term, expensive litigation in for clearly admitted dues.