: Exercise of Against Arbitral Orders Only in Exceptional Cases
The has firmly reiterated that its under should be exercised with when it comes to passed by an arbitrator during ongoing proceedings. The single bench of Justice Sanjay Parihar dismissed a petition filed by challenging an arbitrator's decision to constitute a Technical Committee for inspection of solar power project sites.
The Dispute at Core
The dispute arises from a contract awarded to Tata Power by the for the supply, installation, testing, and commissioning of Off-Grid Solar PV Power Plants across 1,013 project sites in 20 districts of the Union Territory. The company claimed it completed all installations, which were verified and certified by the . According to Tata Power, outstanding dues of approximately Rs. 38.66 crore remained unpaid, leading it to terminate the contract on .
When the matter was referred to arbitration, SPSA filed an application under , seeking appointment of an expert committee for physical verification of the sites. The arbitrator initially rejected this request on , while expressly preserving the power to appoint an expert later if necessary.
The Renewed Application and Challenge
In March 2026, SPSA filed a renewed application, relying on fresh field-verification material from four districts and a communication from Junior Assistant Fayaz Ahmad Bhat, who allegedly disassociated himself from the earlier verification exercise in Kashmir. The arbitrator allowed the application and constituted the committee on .
Tata Power challenged this order before the High Court, arguing that it violated the earlier order, introduced a new factual defence after the closure of evidence, and that an inspection conducted in 2026 could not fairly determine the condition of installations that existed during 2021-2023. The company also contended that SPSA's own communication dated , acknowledged completion of the project, making the renewed request an instance of .
The Legal Framework: Minimal Intervention
Justice Parihar examined the settled legal position on judicial interference with arbitral proceedings, citing key precedents including , , and . The court observed that while under Articles 226 and 227 survives, its exercise against is governed by .
"The Court is therefore not required, at an intermediate stage of arbitration, to examine the correctness of the arbitrator's as though exercising ."
The court noted that the arbitrator's earlier order expressly preserved the power to appoint an expert upon a renewed request if circumstances warranted it. The respondents' reliance on fresh material, including the communication from Mr. Bhat and field reports, provided a basis for the arbitrator to reconsider the matter. Whether that material was credible or admissible were questions for the arbitrator to decide, not for the High Court under .
Addressing Key Concerns
On the question of temporal relevance, the court acknowledged the evidentiary difficulty but clarified that it did not undermine the arbitrator's jurisdiction.
"A physical condition found in 2026 cannot automatically be treated as proof of the condition prevailing in 2023. The , if any, between the Committee's observations and the petitioner's contractual performance would have to be independently established and evaluated by the Arbitrator after hearing both sides."
The court further held that constituting the committee did not amount to an adjudication that the installations were defective. The eventual report would remain material before the arbitrator and would not itself determine rights and liabilities. Tata Power would have a full opportunity to challenge the report's methodology, relevance, and conclusions.
Decision and Directions
Finding no or , the High Court dismissed the writ petition. However, it issued important directions to safeguard the petitioner's interests:
- The expert committee's report shall not be acted upon adversely without affording the affected party a reasonable opportunity to object to its contents and lead .
- The physical condition found in 2026 shall not, by itself, be treated as determinative of the condition at the time of installation or termination of the contract.
- The arbitrator is requested to conclude proceedings expeditiously while ensuring adequate hearing to both sides.
The judgment reinforces the legislative policy of in arbitration and clarifies that procedural orders of arbitrators, even if debatable, will not be interfered with at an interlocutory stage unless they suffer from a fundamental .