KPTCL Cannot Unilaterally Hike Supervision Fees: Karnataka High Court

In a significant ruling for private infrastructure developers, the High Court of Karnataka has ruled that the Karnataka Power Transmission Corporation Limited (KPTCL) lacks the legal competence to unilaterally revise supervision charges for self-execution electrical works. Delivering the order, Justice Ravi V Hosmai emphasized that such financial revisions require formal authorization from the regulatory commission, reinforcing the principle that power utilities cannot bypass statutory mandates in pursuit of cost recovery.

The Conflict: A Hefty Demand The dispute arose when M/s Anushka Realty Inc., which was developing a multi-storied residential project in Bengaluru, challenged a staggering demand notice of ₹1.2 crore issued by KPTCL. The company, which had opted for the 'self-execution' mode of electrical infrastructure development, was initially promised that charges would be capped at ₹15 lakh per established regulatory standards. However, citing a 2018 internal order, KPTCL demanded significantly higher charges, claiming the earlier limit was insufficient to cover modern technical and administrative supervision costs.

Arguments from the Bench The petitioner contended that KPTCL, as a State Transmission Utility, is bound by the frameworks set under the Electricity Act, 2003. They argued that Sections 39 to 41 of the Act define the utility's role strictly in terms of transmission and coordination, and do not include the power to fix or modify consumer charges.

Conversely, KPTCL argued that the existing ceilings, fixed years prior, were no longer viable for high-complexity modern projects. The utility maintained that its order was a mere "administrative measure" to ensure cost recovery for the technical oversight required to integrate consumer-created assets into the state grid, asserting that this function was inherent to their statutory responsibility ensuring grid safety.

Legal Analysis and Precedents The Court meticulously examined the regulatory hierarchy. It found that while KPTCL performs crucial grid-related functions, it does not possess the legislative authority to replace the Karnataka Electricity Regulatory Commission (KERC). Relying on the Supreme Court’s judgment in Joint Action Committee of Air Line Pilots’ Association of India v. Director General of Civil Aviation , the High Court reiterated that a statutory power must be exercised only by the authority upon whom the statute confers it.

Furthermore, the Court addressed the KPTCL’s attempt to justify the hike by citing a lack of rejection from the KERC. Justice Hosmai observed that an observational communication from the regulator stating KPTCL could "take suitable action" did not equate to a grant of fresh regulatory power, nor could it substitute for a formal notification or regulation under Section 181 of the Electricity Act.

Key Observations The judgment clarifies that financial impositions on consumers cannot be treated as discretionary administrative acts. Key highlights from the ruling include:

  • "Indeed, there is no express conferment of power (on KPTCL) to determine or revise charges payable by consumers for supervision of self-execution works."
  • "In view of conclusion above that observation in Annexure-R2 cannot be termed as delegation of power to KPTCL to restructure supervision charges, there would be no need for invocation of maxim ' delegatus non potest delegare '."
  • "It is now well settled that there cannot be imposition of tax, fee or charge etc., without statutory authorization."

The Final Verdict: Implications for Future Projects The Court allowed the writ petition, quashing both the 2018 order prescribing slab-wise charges and the consequential demand notice against Anushka Realty. The respondents have been directed to permit the continuation of work under the existing, regulator-approved tariff structure.

This ruling serves as a vital reminder to state undertakings that they cannot exercise "regulatory-style" powers absent an express mandate. For developers and industry stakeholders, the judgment protects against arbitrary cost escalations, ensuring that fees for public utility services remain strictly within the confines of established law. Should KPTCL wish to raise these charges in the future, the burden remains on them to approach the KERC for a formal, legal determination.