Kupwara Consumer Commission holds contractors, cement dealer, manufacturer liable for , awards ₹6.35 lakh
The , has ruled in favor of a homeowner whose newly built house developed cracks in its slab, holding two local contractors, a cement dealer, and a cement manufacturer jointly responsible for the defective construction. The Commission ordered the opposite parties to pay a total of ₹6,34,943, including the cost of repairs assessed by the government's technical department.
A Dream Home Turns Sour
Ghulam Mohidin Wani, a resident of Laderwan, Trehgam, Kupwara, set out to build a residential house on his land after obtaining the requisite permission. He engaged contractors Ghulam Mohd Shah and Mohd Rafi Pir (OPs 1 and 2) to execute the construction. The contractors provided a list of materials and specifically demanded cement of the 'Arco' brand. Wani purchased the cement from Manzoor Ahmad Najar, proprietor of (OP3), which was manufactured by (OP4).
The slab was laid, but almost immediately, cracks appeared, rendering the structure unsafe and insecure. Wani approached the opposite parties for redress, but they allegedly adopted delaying tactics, forcing him to file a consumer complaint alleging and .
The Legal Battle and the Technical Report
During the proceedings, OPs 1 to 3 failed to file their responses and were proceeded against . OP4, Dawar Cements, filed written objections denying the allegations but did not appear to contest the matter. Wani presented evidence through affidavits of four witnesses, including himself, corroborating his version of events.
Crucially, the Commission directed the , to inspect the site. The department submitted a detailed report assessing the loss caused to the house at ₹4,04,943. The Commission placed significant evidentiary weight on this independent technical assessment.
Joint Liability and the Standard of Care
The Commission observed that the contractors (OPs 1 and 2), having undertaken the construction work, were responsible not only for its execution but also for ensuring that the materials and workmanship met the requisite standards.
"OP Nos. 1 and 2 were not only responsible for executing the construction work but were also responsible for ensuring that the material and workmanship employed in the construction were of the requisite standard,"
the Commission noted.
The absence of any rebuttal evidence from the opposite parties further strengthened the complainant's case. The Commission found that the construction was deficient and that the damage was directly attributable to the use of or .
"The evidence on record, therefore, establishes that the construction work undertaken by the OPs was deficient, which caused extensive damage to the complainant's house,"
the Commission concluded.
The Final Order
The complaint was allowed with the following directions:
- OP Nos. 3 () and 4 () are directed to pay ₹4,04,943 towards the loss caused due to the use of alleged sub-standard cement.
- OP Nos. 1 to 4 are directed to pay ₹2,00,000 as for the inconvenience and agony suffered by the complainant.
- All OPs are directed to pay ₹30,000 towards .
The entire amount of ₹6,34,943 must be paid within 30 days from the date of the order, failing which it will carry interest at the rate of 5% per annum from the date of the order till realization.
This judgment reinforces the principle that all parties in a construction chain—from contractors to material suppliers—can be held jointly liable for deficient work, even when some choose not to defend themselves.