The has permitted the to proceed with the felling of trees required for an underground station project, while simultaneously issuing a series of stringent, mandatory directives to mitigate the environmental impact on local bird populations. The ruling concludes a initiated by petitioner Priyanshu Jain, who had sought to halt the removal of over 150 trees at the Rani Sarai land premises, citing the destruction of vital roosting habitats for thousands of birds, including parakeets protected under the .
While the bench comprising Justice Subodh Abhyankar and Justice Jai Kumar Pillai ultimately dismissed the petition, the decision was predicated on the doctrine of stare decisis . The court noted that a previous division bench had already adjudicated upon the metro alignment in the case of in . Finding that the route for the metro project had attained finality through that earlier judgment, the court held that it could not entertain a to the alignment in the guise of a tree-protection plea.
However, recognizing the ecological importance of the site, the court conducted a personal inspection of the Rani Sarai premises along with legal counsel and stakeholders to assess the site’s status as a critical roosting ground. During this visit, the judges observed large numbers of birds congregating in the trees. Although the court determined that the metro project was a sanctioned public infrastructure endeavor that could not be redirected, it exercised its to ensure that the process of deforestation caused the least possible disturbance to the avian species inhabiting the area.
Implementing Protective Protocols
To address the immediate threat to the birds, the court issued comprehensive operational directives that the Metro Rail Corporation must strictly follow. The judges emphasized that the felling of trees must not occur in a haphazard fashion. Instead, the process must be slow, systematic, and professionally monitored.
"The respondents are not to cut all the trees at once or in any random manner, but they should do so only under the supervision and consultation with at least two ornithologist/bird experts,"
the order stated. These experts are tasked with advising the authorities on how to prune branches and clear vegetation in a phased manner. This approach is intended to provide the birds with necessary "breathing time" to locate alternative roosting sites in the vicinity, which proponents of the project argued were already available in adjacent areas.
In addition to phased felling, the court mandated that a wildlife rescue team equipped with nets and medical supplies must remain present at the construction site during the entire clearing process. This team is explicitly charged with safeguarding baby birds and eggs, as well as providing immediate aid to any wildlife injured during the operation. To further facilitate this, the court directed the to pay a remuneration of ₹10,000 to each of the designated bird experts for their professional services.
Ensuring Long-Term Environmental Accountability
The judicial order extends beyond the immediate clearing process, imposing long-term obligations on the metro authorities to ensure compensatory environmental gains. The corporation has been directed to uphold its commitment to replace the lost vegetation by planting 2,500 trees in the area.
"The respondents are also directed to comply with the undertaking given by them of planting 2500 trees. A report in this regard may also be submitted with the Registry of this court, within one year from today,"
the court specified. Furthermore, the authorities are required to file annual reports with the court registry every April for the coming years, accompanied by photographic evidence from satellite mapping services to ensure the survival and maintenance of the newly planted saplings.
The court suggested that the process of selecting experts should involve experts like Bhalchandra Mondhe, a renowned environmentalist and Padma Shri awardee who appeared as an intervener. His expertise is expected to ensure that the pruning and clearing stages are managed with the highest possible sensitivity toward the avian population.
Addressing the Scope of
The dismissal of the petition highlights the court’s reluctance to act as an expert planning body. In its discussion, the court reiterated its position from the 2024 Raj Lakshmi Foundation order, asserting that is not the appropriate mechanism to substitute the views of technical experts regarding civil engineering and urban planning. The bench noted that the metro route was designed by experts after exhaustive deliberation on traffic flow, infrastructure needs, and the optimization of public land.
"Indeed, it would be a painful process for all the parties concerned, especially the bird lovers, but this is the best that we can think of under the circumstances,"
the court remarked. Despite the loss of the petition, the court expressed its satisfaction that its intervention has secured a more humane, expert-driven approach to the inevitable removal of the trees. By balancing the urgent requirements of urban transit development with the preservation of local biodiversity, the High Court has established a framework for future developmental projects where environmental impact and infrastructure growth intersect.
The is now tasked with initiating the phased clearance under the watchful eyes of the appointed ornithologists, ensuring that every effort is made to allow the birds to migrate safely to neighboring habitats while the essential transit infrastructure progresses. Compliance with these directives will be closely monitored by the court through the mandated annual reporting schedule.
bird habitat conservation - metro project infrastructure