The Madras High Court has initiated a formal inquiry into the Tamil Nadu government’s sudden decision to discontinue the ambitious Parandur Greenfield Airport project. During a high-stakes hearing on November 20, 2026 , the Division Bench of Chief Justice SA Dharmadhikari and Justice G. Arul Murugan expressed deep skepticism regarding the state's rationale for abandoning a major infrastructure project that had already undergone significant land acquisition and expenditure. The court’s intervention follows a public interest litigation (PIL) filed by a concerned citizen challenging the state’s decision as arbitrary and unconstitutional .

The bench raised pointed concerns about how a government could authorize a project of such magnitude, undertake extensive feasibility studies , and proceed with land acquisition , only to reverse course citing lack of feasibility. The judges observed that the abandonment of the project, which was intended to serve as a critical second airport for Chennai, appeared to be driven by the " whims and fancies " of the state leadership rather than sound administrative or technical grounds. The Court issued formal notices to the Tamil Nadu government, the Tamil Nadu Industrial Development Corporation Limited (TIDCO) , the Union Ministry of Civil Aviation , and the Airports Authority of India , seeking comprehensive responses regarding the basis of the cancellation.

Scrutinizing the Sudden Pivot on Infrastructure

The Parandur project was envisioned as a ₹27,400-crore greenfield aviation hub in the Kanchipuram district, designed specifically to address the severe capacity constraints at the existing Meenambakkam airport, which handles nearly 30 million passengers annually. According to the petition, the state had already spent approximately ₹680 crore of public funds and had successfully consolidated over 1,700 acres of land—covering nearly half of the required area—across multiple villages. The sudden announcement by Chief Minister C. Joseph Vijay in the Legislative Assembly on August 24, 2026 , to scrap the project sent shockwaves through the aviation and industrial sectors, prompting immediate legal scrutiny.

The Court’s primary concern during the hearing centered on the consistency of the government’s planning process. Chief Justice SA Dharmadhikari questioned the administration on why technical and environmental red flags, which the government now cites as the primary reason for cancellation, were not identified during the initial feasibility phase. The bench noted that such massive projects are not formulated in a vacuum and that the government is obligated to conduct thorough inspections and environmental impact assessments before declaring a site suitable for an international airport. "A feasibility study has to be conducted, land has to be acquired, etc. After all this, you cannot now come and say that no, no, this is not feasible," the bench remarked during the proceedings.

Environmental Hurdles Versus Public Expenditure

Advocate General Vijay Narayan , appearing for the state, defended the government’s position by explaining that a detailed review revealed that a significant portion of the acquired land comprised water bodies and agricultural zones. He argued that these geographical realities would make obtaining necessary environmental clearances extremely difficult, effectively rendering the site non-viable. He noted that the government had determined that correcting the course, even at this advanced stage, was preferable to persisting with a project that faced insurmountable environmental legal challenges.

The Advocate General further informed the court that the move was a policy decision and that a formal government order detailing the precise rationale would be released shortly. He emphasized that the government was acting to protect the livelihoods of local farmers and preserve essential wetlands, an argument the petitioner and the Court are now weighing against the financial losses incurred by the exchequer. The court, however, remained unsatisfied with the lack of documentation presented at the time of the announcement, questioning why a more robust vetting process did not occur before financial resources were committed.

Assessing the Constitutional Validity of the Cancellation

The petition, filed by G. Gouthaman, a software consultant and book publisher, argues that the decision lacks a reasoned assessment and fails to provide any technical data or expert committee report to support the claim of non-feasibility. The petitioner highlighted that the decision was announced under Rule 110 of the Tamil Nadu Legislative Assembly Rules, a mechanism that precludes immediate legislative debate, thereby shielding the policy shift from necessary public and political scrutiny. The legal challenge maintains that reversing a project that had already secured multi-agency appraisals and conditional approvals from central authorities without providing supporting data is an arbitrary exercise of power that violates Article 14 of the Constitution .

The PIL seeks to compel the government to produce all internal administrative files, hydrogeological reports, and financial ledger notes that formed the basis for the reversal. Furthermore, the petitioner has asked the court to impose an interim stay on the reclassification or alienation of the lands already acquired, fearing that if the government proceeds with dissolving the acquisition, the site may be permanently lost for future aviation expansion. The court’s decision to issue notices to the Union government and the Airports Authority of India indicates that the litigation will likely delve into the broader implications of federal and state cooperation in large-scale infrastructure projects.

The case has now set the stage for a critical review of the state’s decision-making process. As the government prepares its formal response and a government order detailing the cancellation, the High Court will continue to assess whether the abandonment constitutes a reasonable exercise of administrative discretion or an arbitrary waste of public resources. With the matter currently pending, the Court has not yet issued a stay on the government’s policy, but the scrutiny ensures that the state must provide a transparent, evidence-based justification for its sudden reversal on one of the region's most significant planned investments. The next phase of the hearing is expected to focus on the technical evidence, if any, that was available to the government at the time the decision was made in the Legislative Assembly .