NCLT Chennai Cancels Sale Deed of Homebuyer Who Failed to Submit Claim During CIRP

The National Company Law Tribunal (NCLT), Chennai, has delivered a significant ruling for the insolvency and homebuyer landscape, cancelling a registered sale deed and construction agreement of a homebuyer who failed to file a claim during the corporate insolvency resolution process (CIRP) of P Dot G Constructions Private Limited. The order reinforces the binding nature of approved resolution plans and serves as a stark reminder that stakeholders cannot remain silent during the process and later assert rights outside the plan.

The two-member bench comprising Judicial Member Sanjiv Jain and Technical Member Venkataraman Subramaniam observed that the homebuyer had received two clear opportunities—first during the CIRP and then during a 60-day window after the resolution plan was approved—but chose not to come forward. Consequently, the Tribunal held that the homebuyer could not “stand outside the resolution plan” which had attained finality.

The Homebuyer’s Claims and the Corporate Debtor’s Defense

The dispute arose out of a construction agreement dated February 11, 2016, followed by a registered sale deed dated February 12, 2016, between the homebuyer and P Dot G Constructions. The homebuyer claimed to have paid the entire consideration and obtained possession of the flat. According to the petitioner, ₹22 lakh had been paid by cheque in September 2014, and an additional ₹1,37,508 in cash in February 2016.

However, the corporate debtor contended that no claim had been filed by the homebuyer during the CIRP, nor during the subsequent 60-day window provided under Clause 4.4(xv) of the approved resolution plan. This clause specifically allowed homebuyers whose claims were not filed or were rejected to approach the successful resolution applicant within that period.

The NCLT scrutinised the sale deed and found it acknowledged only ₹2.88 lakh towards the undivided share of land. The deed did not admit receipt of the remaining ₹18,15,588 for the property described in Schedule B. Furthermore, there was no acknowledgement from the corporate debtor for the alleged cash payment of ₹1,37,508. The bench concluded that the homebuyer had failed to substantiate the claim that the entire sale consideration had been paid.

The Missed Opportunities

The Tribunal recorded, “the Respondent had not filed any claim form before the IRP during the CIR Period.” This failure deprived the homebuyer of the right to be considered in the resolution plan. Even after the plan was approved by the Committee of Creditors (CoC), the respondent did not avail the extra 60-day window. The bench noted that the resolution plan had become final and binding on all stakeholders, including those who failed to file claims.

The judges emphasised that a resolution applicant who successfully implements a plan cannot later be confronted with undecided claims. This principle, drawn from the Supreme Court’s decision in Committee of Creditors of Essar Steel India Ltd. v. Satish Kumar Gupta , protects the finality and sanctity of the resolution process.

Reliance on Supreme Court Precedents

The NCLT placed heavy reliance on the Supreme Court’s ruling in Jaypee Kensington Boulevard Apartments Welfare Association v. NBCC (India) Ltd. , which established that homebuyers who do not file claims during the CIRP cannot later challenge or stand outside the approved resolution plan. The bench also referred to the Essar Steel case, where the apex court underscored that a successful resolution applicant must not be burdened with unknown or belated claims after the plan has been approved.

These judgments form the backbone of the current insolvency framework, ensuring that resolution plans are comprehensive and all stakeholders participate within the designated timelines. The NCLT noted that the homebuyer had ample opportunity to assert his claim but chose to remain silent, and therefore could not be allowed to disrupt the finality of the plan.

Implications for Homebuyers and Corporate Insolvency Practice

This decision sends a clear signal to homebuyers involved in insolvent real estate projects: passive ownership of a property—even with a registered sale deed and possession—does not exempt one from the mandatory claim filing process under the Insolvency and Bankruptcy Code. The IBC prioritises collective resolution over individual rights, and all creditors, including homebuyers, must actively participate in the CIRP to have their claims recognised.

For resolution professionals and successful resolution applicants, the ruling provides comfort that once a plan is approved, it is binding on all stakeholders. The 60-day cure window is a reasonable grace period, but those who fail to act even then cannot later seek to undo the plan.

Legal experts view this as a necessary check against potential abuse by homebuyers who may attempt to use possession or registered documents to circumvent the insolvency process. The order also aligns with the legislative intent of the IBC to ensure time-bound resolution and finality.

Conclusion

The NCLT Chennai has ordered the cancellation of the sale deed and construction agreement, directed the homebuyer to surrender the original documents within 30 days, and declared that all claims arising from those documents stand extinguished. The case is a textbook example of the consequences of failing to adhere to procedural requirements in insolvency matters.

Homebuyers must remain vigilant and file their claims promptly during the CIRP, or at least within the additional window provided by the resolution plan. The NCLT’s ruling reaffirms that the IBC does not permit a stakeholder to pick and choose when to participate. For the legal community, this judgment is a valuable reference on the binding nature of resolution plans and the strict enforcement of claim-filing timelines.