NCLT Indore Dismisses Oswal Woollen Mills Insolvency Plea Against EKI Energy Services
The has dismissed an filed by against , ruling that a over contractual terms barred the proceedings.
Blocks Insolvency Route
The dispute arose from an Emission Reduction Purchase Agreement (ERPA) dated , under which Oswal agreed to supply Certified Emission Reductions (CERs) to EKI Energy. Oswal claimed it delivered 70,085 CERs on , triggering a payment obligation within 15 days. When EKI failed to pay the principal sum of ₹1.28 crore plus interest, Oswal issued a under on .
Carbon Credit Controversy Not a
EKI opposed the petition, arguing that the parties had been locked in a contractual dispute well before the . The company had invoked Clause 2.14(m) of the ERPA on , seeking to revise the CER purchase price from the agreed USD 1.0/2.5 per CER to USD 0.40/1.35 per CER, citing a collapse in the global carbon-credit market. Oswal rejected the proposal on , and correspondence continued through , with Oswal even threatening "legal litigations."
The tribunal found that this correspondence demonstrated opposing positions on the contractual price, payment mechanism, and quantity of CERs—amounting to a that existed before the . Referring to the 's test in , the bench noted that a dispute need only be to defeat a petition.
Invoicing and Quantity Issues Reinforce Dispute
EKI also pointed out that Oswal had not issued any invoice, as required under Clause 2.14(f) of the ERPA, and that the claimed quantity of 70,085 CERs exceeded the 68,544.14 CERs actually issued according to the . The tribunal observed that these disagreements were part of the broader contractual controversy and could not be resolved in summary proceedings.
Court Refuses to Adjudicate Contractual Merits
The bench clarified that it was not determining the validity of the price revision, the applicable rate, or the interest claim.
"The fact that each party consistently maintained its own position does not make the dispute
; rather, it demonstrates that the disagreement remained unresolved and was carried forward into the period preceding the
,"
the tribunal stated.
Key Observations
"The defence raised by the cannot be characterised as a or a . It is founded upon Clause 2.14(m) of the very ERPA on which the 's claim is based, and is supported by ."
"Whether the was ultimately entitled to invoke the said clause and whether the circumstances pleaded by it fell within the scope of the clause are matters which we are not required to finally determine at this stage. The relevant question is whether the contention is genuine and requires adjudication."
"This Tribunal, while exercising under , cannot undertake a final adjudication of such contractual questions."
Final Decision and Implications
The NCLT dismissed Company Petition IB (IBC)/56(MP)2025 with no order as to costs, holding that the under (5)(ii)(d) of the IBC was attracted due to the . The rejection is confined to the maintainability of the and does not preclude Oswal from pursuing through arbitration or civil suit.
The judgment reinforces the principle that the IBC is not a substitute for and that a genuine contractual dispute, even if not yet adjudicated, can shield a from .