Analysis and Conclusion:
The Bright Power Project (India) Private Limited case is a landmark judgment that clarifies the enforceability of contractual clauses related to claims, variations, and interest payments in construction contracts. It underscores that tribunals and courts must operate within the bounds of contractual stipulations, and any relief granted beyond these terms is generally inadmissible. This case serves as a guiding precedent for disputes involving contractual restrictions on claims and arbitration proceedings in India.

Search Results for "Bright Power Project"

Punjab National Bank VS Prime Engineers Consultants

2018 0 Supreme(Del) 3002 India - Delhi

S.RAVINDRA BHAT, A.K.CHAWLA

Bright Power Project (India) Private Limited, (2015) 9 SCC 695 - 5.46, 5.41, J.G. Engineers Pvt. Ltd v. ... Bright Power Project (India) Private Limited, (2015) 9 SCC 695 - The court discussed the arbitrability of claims, the price variation ... Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. The court then held that the Tribunal’s #HL_START....

Union of India, Acting through Chief Electrical Engineer (Construction) VS Bright Power Project (I) Pvt.  Ltd.

2015 0 Supreme(Bom) 497 India - Bombay

R.D.DHANUKA

contract between the parties whereunder the contractor has undertaken not to make any claim for delay in performance of the contract occasioned by an act of the employer, still a claim would be entertainable in one of the following situations: (i) if the contractor repudiates the contract exercising his right

UNION OF INDIA Vs BRIGHT POWER PROJECT (I) PVT.LTD.

India - Bombay High Court

union of india chief electrical enginer(CONTRUCTION) vs M/S BRIGHT POWER PROJECT INDIA (PVT) LTD

India - Bombay High Court - Original Side,Bombay

M/s.Bright Power Project India clause does not contain the prohibition on the power held that that clause does not contain the prohibition on the power ... which imposes prohibition on the power of the arbitrator to award interest on the sums found submits that clause 13(3) can not clearly impose prohibition on the power

PUNJAB NATIONAL BANK vs PRIME ENGINEERS CONSULTANTS

India - Delhi High Court

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. ... Power Project (India) Private Limited (supra) is equally forthright. ... This court is bound by the reasoning in Bright Power Project (supra), the interest to the extent it was granted in excess of the stipulated and agreed amount is therefore inadmissible and clearly amounts ... FAO (OS) No.....

PUNJAB NATIONAL BANK vs PRIME ENGINEERS AND CONSULTANTS

India - Delhi High Court

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. ... Power Project (India) Private Limited (supra) is equally forthright. ... This court is bound by the reasoning in Bright Power Project (supra), the interest to the extent it was granted in excess of the stipulated and agreed amount is therefore inadmissible and clearly amounts ... FAO (OS) No.....

PUNJAB NATIONAL BANK vs PRIME ENGINEERS CONSULTANTS

India - Delhi High Court

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. ... Power Project (India) Private Limited (supra) is equally forthright. ... This court is bound by the reasoning in Bright Power Project (supra), the interest to the extent it was granted in excess of the stipulated and agreed amount is therefore inadmissible and clearly amounts ... FAO (OS) No.....

PUNJAB NATIONAL BANK vs PRIME ENGINEERS AND CONSULTANTS

India - Delhi High Court

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. ... Power Project (India) Private Limited (supra) is equally forthright. ... This court is bound by the reasoning in Bright Power Project (supra), the interest to the extent it was granted in excess of the stipulated and agreed amount is therefore inadmissible and clearly amounts ... FAO (OS) No.....

Punjab National Bank vs Prime Engineers Consultants

India - Delhi High Court

S.RAVINDRA BHAT, A.K.CHAWLA

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. The court then held that the Tribunal's power to grant relief is circumscribed by such condition. ... With respect to the price variation clause and with respect to the interest on delay, stipulated beyond a particular period, this court notices that the judgment in Bright Power Project (India) Private Limited (supra) is equally....

PUNJAB NATIONAL BANK Vs PRIME ENGINEERS CONSULTANTS

2018 Supreme(Online)(DEL) 3481 India - High Court of Delhi

Bright Power Project (India) Private Limited, (2015) 9 SCC 695, in which the Supreme Court had occasioned to deal with the identical clause. The court then held that the Tribunal’s power to grant relief is circumscribed by such condition. ... With respect to the price variation clause and with respect to the interest on delay, stipulated beyond a particular period, this court notices that the judgment in Bright Power Project (India) Private Limited (supra) is equally....

SupremeToday Landscape Ad

Filter by Legal Phrase

SupremeToday Portrait Ad

Legal Issues on Supreme Today AI

logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top