The has established a definitive stance on the for appeals under the , declaring the 120-day window for filing such challenges to be mandatory and inflexible. In a judgment delivered by Justice Dipankar Datta and Justice Sheel Nagu, the Court ruled that lack the authority to condone delays beyond the by invoking . This decision effectively closes the door on belated appeals, emphasizing that the legislative intent behind the 2013 Act leaves no room for in extending these timeframes.
The matter arose from a challenge brought by the against an order of the . The Board had sought to overturn two directives from the in Jaipur, which favored The had previously dismissed the Board’s , ruling that the provided under was the appropriate path, but that the Board had already forfeited this right by failing to file within the maximum permissible period of 120 days.
Strict Adherence to Statutory Timelines
The Supreme Court’s examination of the case centered on whether the precedent set in —which suggested that the 60-day in the proviso of Section 74 was not mandatory—remained valid law. Upon review, the bench expressed significant reservations regarding the logic used in that earlier judgment. The Court observed that numerous other statutes, including the and the , contain similar in-built limitations that have been consistently upheld as absolute commands.
Justice Datta, writing for the bench, underscored that
"a parliamentary prescription stands altered by a judicial interpretation, giving impetus to belated appeals under
being filed and to the plea that any delay, howsoever inordinate, be condoned."
The Court maintained that the legislature’s intent to impose a strict outer limit is manifest, noting that if an extension had been intended, the statute would have provided the necessary linguistic framework for such leniency.
The bench explicitly rejected the argument that the 2013 Act, as beneficial legislation, implicitly permits the use of the Limitation Act to extend filing deadlines. By examining the scheme of the Act, the judges concluded that the period of 120 days is a rigid ceiling. Any attempt to interpret this as flexible would, according to the Court, effectively render the statutory proviso "
." The Court further remarked on the principle of judicial restraint, stating,
"If the legislature wilfully omits to incorporate something of an analogous law in a subsequent statute, or even if there is a
in a statute, the language of which is otherwise plain and unambiguous, the Court is not competent to supply the omission."
Addressing Judicial Consistency and Precedent
During the proceedings, counsel for the had argued that the S.V. Global Mill Limited decision represented a significant shift in judicial thinking and requested that the matter be referred to a larger bench for reconsideration. However, the Supreme Court declined this request, citing the doctrine of and the existence of a long line of decisions by larger benches that have consistently enforced strict limitations in similar statutory contexts.
The Court pointed out that the S.V. Global Mill Limited ruling had failed to account for such as , which clarified that even when a special law does not explicitly exclude the Limitation Act, courts must examine whether the nature of the scheme and the subject matter necessitate such an exclusion by implication. The current bench emphasized that the 2013 Act’s structure does not support the application of Section 5 of the Limitation Act, as it would create " " where acquiring bodies could file inordinately delayed challenges, further disadvantaging landowners.
Finality of the Appellate Process
Beyond the specific legal debate over limitation, the Court noted that the ’s attempt to bypass the appellate procedure by filing a under was fundamentally flawed. The High Court had been correct in its assessment that the Board could not circumvent the statutory remedy simply by choosing a different constitutional route. The Supreme Court affirmed that the Board’s failure to act within the prescribed window resulted in the total foreclosure of its right to appeal.
The judgment clarifies that the "120 days" mentioned in Section 74 is an absolute cap. Even in the exercise of the Supreme Court's under , the Court indicated it would not condone delays that disregard this legislative command. By dismissing the , the Court has reinforced a high standard of procedural compliance for government bodies and private entities alike.
For future proceedings, the ruling serves as a warning that statutory deadlines for land acquisition disputes are not suggestions but binding constraints. The Court ordered that all pending appeals before under Section 74 should be decided in accordance with these findings, signaling an end to the period of uncertainty regarding the maintainability of time-barred applications. The litigation concerning the has reached its conclusion with the dismissal of the petition, leaving the initial orders of the in full force.
Statutory Limitation - Appellate Jurisdiction