Upholds NEEPCO's , Precludes 's Award
In a significant ruling on arbitration law, the has held that a contractual clause barring claims for interest on delayed payments effectively prohibits an from awarding . The decision clarifies the distinction between clauses that bar interest only on disputed amounts and those that separately target delayed payments.
A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe allowed an appeal by against , setting aside a judgment that had restored awarded by an .
A Tale of Two Clauses: The Crucial Distinction
The dispute arose from a contract for civil works of a gas turbine power project in Tripura, valued at approximately ₹17.09 crore. The project faced delays, leading to arbitration. The attributed the delay to NEEPCO and awarded ₹3.30 crore on four claims, along with 12% and 9% pendente lite and .
NEEPCO challenged the award under . The held that of the General Conditions of Contract (GCC) barred the grant of interest, both pre-reference and pendente lite, and modified the award accordingly. However, the High Court restored the interest, relying on the 's decision in State of U.P. v. Harish Chandra and Co. ().
The core issue was whether was identical to the clause in Harish Chandra —which only barred interest on money held due to a dispute—or to clauses in Sayeed Ahmed & Company v. State of U.P. () and Jaiprakash Associates Limited v. Tehri Hydro Development Corporation (India) Limited (), which were held to be complete bars.
The Evolution of Interest Law Under Arbitration
The traced the law on interest under the and the 1996 Act. Under the 1940 Act, arbitrators could imply a power to award interest, and contractual bars were strictly construed. However, changed this: it expressly allows the tribunal to award interest
"
"
—meaning an is sufficient to exclude the power.
The Court noted that stands on a different footing from . While is procedural, is substantive and cannot be sourced solely from Section 31(7)(a) but must have a basis in an agreement, statute, or mercantile usage.
"" as a Separate Ground: The Decisive Difference
The Court compared the wording of with the clauses in
Harish Chandra
and
Sayeed Ahmed
. In
Harish Chandra
, the clause barred claims for interest
"with respect to any moneys or balances which may be lying with the Government owing to any dispute, difference or misunderstanding."
It did not separately address delay in making payments.
, however, reads: "No claims for interest or damages will be entertained by the Corporation with respect to any money or balance which may be lying with the Corporation owing to any dispute, difference or misunderstanding... or with respect to any delay on the part of the Engineer-in-Charge making periodical or final payments or in any other respect whatsoever."
The Court held that by naming as a separate, independent ground, does what the clause in Harish Chandra never did: it expressly shuts out a claim for interest arising from delayed payment, whether or not there was any dispute about it.
High Court's Error: Equating Apples and Oranges
The faulted the High Court for treating as identical to the clause in Harish Chandra . The Court noted that the very same structure—a general prohibition on interest for disputed amounts followed by a separate prohibition on delayed payments—appears in the clauses examined in Sayeed Ahmed and THDC-II , which were held to be complete bars.
"It is the line of decisions in Sayeed Ahmed and thereafter, not Harish Chandra , that governs this case," the Court observed.
Key Observations from the Judgment
The Court made the following pivotal observations:
"By naming as a separate ground, standing on its own and not tied to any dispute, does what the clause in Harish Chandra never did: it expressly shuts out a claim for interest arising from delayed payment, whether or not there was any dispute about it at all."
"The two clauses are worded differently, and that ."
The Court also rejected the argument that NEEPCO had waived its right to invoke , noting that the plea was specifically taken in the Statement of Defence before the .
Final Verdict: Prevails
The allowed the appeal, setting aside the High Court's judgment to the extent it restored . The Court held that the exceeded its jurisdiction under Section 31(7)(a) by awarding such interest despite the .
"
of the GCC bars the grant of interest for the pre-reference period, and that the
, in awarding such interest,
under
,"
the Court concluded.
The award stands modified accordingly, with no order as to costs. The decision reinforces the principle that under the 1996 Act allows express contractual terms to override the 's default power to award interest.