Susajja JV Anand LLP Wins Right to Arbitrate Against Bhopal Municipal Corporation

The Madhya Pradesh High Court has ruled that a waste management contract does not constitute a "works contract" under the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, merely because it involves incidental civil construction. Justice Deepak Khot allowed an application by Susajja JV Anand LLP under Section 11(6) of the Arbitration and Conciliation Act, 1996, and appointed former Calcutta High Court Chief Justice Sujoy Paul as the sole arbitrator to resolve the dispute with the Bhopal Municipal Corporation.

The Dispute Over Waste Remediation

In 2024, the Bhopal Municipal Corporation issued a Request for Proposal for the remediation of old waste through bioremediation and biomining, along with the processing and disposal of fresh waste at Adampur Chawni. Susajja JV Anand LLP was declared the successful bidder and executed a contract with the corporation.

After taking over the project site, Susajja alleged persistent infrastructure deficiencies — including a damaged tipping floor, lack of a windrow platform, inadequate sheds, drainage problems, and damaged boundary walls. A dispute also erupted over the quantity of legacy waste: the RFP estimated 2,50,000 MT, but a survey by MANIT assessed approximately 10,63,000 MT. The corporation cancelled MANIT’s appointment without explanation.

Susajja issued an intent-to-terminate letter on July 7, 2025, claiming ₹4.34 crore remained unpaid for fresh waste processing. When the corporation failed to cure the breaches, Susajja terminated the contract on July 22 and handed over the site two days later. The corporation responded with its own termination letter on August 11, disputing Susajja’s claims and alleging breaches.

Failed Dispute Resolution Mechanism

The contract contained a multi-tier dispute resolution clause requiring disputes to be first raised before the Competent Authority, then appealed to the Appellate Authority, and finally referred to the Madhya Pradesh Arbitration Tribunal under the 1983 Act. Susajja submitted its claims to the Competent Authority on August 20, 2025, but no decision was rendered within 45 days. The Appellate Authority refused to entertain the appeal, stating it lacked jurisdiction over matters related to the Swachh Bharat Mission.

Susajja then invoked arbitration under the Arbitration and Conciliation Act, 1996, on February 12, 2026, but the corporation did not respond. This led to the Section 11(6) application before the High Court.

The Core Legal Question

The Bhopal Municipal Corporation opposed the application, arguing that the contract involved excavation, remediation, construction of sheds and platforms, landfill and drainage works — activities that brought it within the definition of a "works contract" under Section 2(i) of the 1983 Act. Therefore, the dispute must be resolved by the Madhya Pradesh Arbitration Tribunal, not by an arbitrator appointed under the 1996 Act.

Susajja countered by relying on the Supreme Court’s decision in Ecogreen Energy Gwalior Pvt. Ltd. v. Municipal Corporation Gwalior (decided on April 21, 2026), which held that a solid waste management contract’s dominant purpose is waste management, not civil construction. Incidental civil works do not transform it into a works contract.

High Court’s Analysis

Justice Deepak Khot examined the nature and scope of the contract. He noted that the agreement’s primary objective was waste management — remediation, processing, and disposal. The civil construction aspects were ancillary and incidental to that main purpose.

Citing the Supreme Court’s Ecogreen Energy ruling, the judge observed: “From a reading of the aforesaid principle laid down by the Honorable Apex Court, it is demystified that the Court has to consider the nature and scope of the work which is agreed between the parties under the agreement and on consideration of nature of work, which is under the scope of the agreement, if the Court comes to the conclusion that it is not a work contract, the dispute can be referred by appointment of an Arbitrator under the Act of 1996.”

The court also relied on its own decision in M/s PKH M.P. Convention Center Pvt. Ltd. v. Madhya Pradesh State Tourism Development Corporation Limited , which held that even if parties agree to statutory arbitration under the 1983 Act, a contract that does not fall within the definition of a works contract is not amenable to the Tribunal’s jurisdiction. In such cases, the court can appoint an arbitrator under the 1996 Act if the parties intended to arbitrate.

Key Observations

The judgment emphasized the need to look beyond labels: “This Court is also of the considered opinion that the contract in question is not a work contract, as it deals dominantly for the purpose of waste management and the civil work which is incidental to the said management cannot be said to be a works contract.”

On the applicability of the 1983 Act, the court clarified: “Even if the parties have agreed to resolve their dispute through statutory arbitration under the Act of 1983, but if the contract is not a works contract then it is not amenable to the jurisdiction of the Tribunal under the Act of 1983. In such case, if the intention of the parties is to resolve the dispute through arbitration then it can be referred to the Arbitrator under the Act of 1996.”

The Decision

Justice Deepak Khot allowed Susajja JV Anand LLP’s application and, with the consent of both parties, appointed former Calcutta High Court Chief Justice Sujoy Paul as the sole arbitrator. The arbitration will be conducted at Jabalpur, and the parties must deposit fees as per the Madhya Pradesh Arbitration Centre (Domestic and International) Rules, 2019.

The ruling reinforces the principle that the dominant purpose of a contract determines its classification, not the incidental activities it may require. For municipal waste management contracts, this decision provides clarity: disputes will be resolved through the Arbitration and Conciliation Act, 1996, unless the contract is genuinely a works contract under the 1983 Act.