Tenaga Nasional awarded RM391,787.25 as Selayang Court holds registered user liable for meter tampering
has ordered to pay (TNB) RM391,787.25 for losses arising from meter tampering at a rented premises in Rawang, Selangor, affirming that registered consumers bear the responsibility for their electricity accounts even when a property is leased to third parties.
In a judgment delivered on 10 July 2026, Sessions Court Judge Norazlin binti Othman found that TNB had proven its claim on a balance of probabilities. The court also dismissed the defendant’s third-party claim against the tenant and property agents for indemnity, ruling that Quantum Image had failed to discharge its burden of proof.
Meter tampering discovered during routine inspection
The case stems from an inspection conducted by TNB on 23 December 2020 at the defendant’s premises located at 15-2 Jalan MR ¼, Taman M Residensi, Rawang. TNB technicians discovered that the electricity meter had been tampered with through direct wiring from the incoming TNB supply to the consumer’s distribution board, bypassing the meter entirely. This prevented the meter from recording actual electricity consumption across all three phases.
The tampering was found to have occurred over a period stretching back to the initial supply date of 16 May 2016. TNB calculated the loss of revenue using the Maximum Demand Load method, arriving at RM291,787.25 in unpaid charges, plus RM200 in operational costs and other applicable charges, totaling RM391,787.25.
Legal arguments: statutory claim vs. tenancy defence
TNB brought its claim under , which allows licensees to recover undercharged amounts through civil action. The utility company presented four witnesses, including the inspection team and the back-billing specialist who explained the calculation methodology.
Quantum Image contended that it should not be held liable because the premises had been leased to under a tenancy agreement dated 15 November 2017, prior to the inspection. The defendant argued that any tampering must have been carried out by the tenant or an unknown third party, and therefore the responsibility should shift to the occupier.
Court clarifies registered user’s enduring liability
Justice Norazlin rejected the defendant’s arguments, relying on a line of appellate authorities including *
The court emphasised that for claims under Section 38, TNB is not required to prove the identity of the person who tampered with the meter. What matters is whether the meter has been tampered with and whether the registered account holder has suffered a loss. As the court noted:
> "For the purposes of a claim under S.38(3) to (5), we take the view that it is not necessary for TNB to prove the identity of the person who damaged or tampered with the meter."
The judgment further observed that the defendant remained the registered consumer throughout the period, and the doctrine of privity of contract meant that TNB, not being a party to the tenancy agreement, could not be bound by any allocation of responsibility between landlord and tenant.
Limitation period and calculation methodology upheld
The defendant raised a limitation defence, arguing that the claim was time-barred. The court, however, applied the settled principle that the cause of action under Section 38 accrues on the date the tampering is discovered, not when it first occurred. Since the tampering was discovered on 23 December 2020 and the suit was filed on 17 October 2024, the claim fell well within the six-year limitation period under
On quantum, the court accepted TNB’s calculation using the Maximum Demand Load method. The defendant did not adduce any expert or technical evidence to challenge the computation. As the confirmed in Tenaga Nasional Bhd v Evergrowth Aquaculture Sdn Bhd [2021], the legislature has left the methodology of loss calculation to TNB because of the inherent difficulty in ascertaining actual usage when meters have been interfered with.
Third-party indemnity claim fails
The court also dismissed Quantum Image’s third-party proceeding against the tenant, Lai Yau Fatt (trading as ), and two property agents. The defendant sought full indemnity for any liability imposed in the main action.
Justice Norazlin found that the defendant had not established any legal basis for the indemnity claim. The tenancy agreement did not contain an express indemnity clause, and no statutory provision or equitable ground justified shifting the loss. The court observed that the defendant had focused its efforts on defending the main claim and neglected to provide a substantive legal justification for its third-party claim.
Final orders and costs
The court entered judgment in favour of TNB as follows:
- RM391,787.25 for loss of revenue and operational costs
- Interest at 5% per annum from the date of judgment until full settlement
- Costs of RM8,000 to be paid by Quantum Image to TNB
All other relief sought by TNB, including general and exemplary damages, were refused. The defendant’s third-party claim was dismissed with no order as to costs.
The judgment serves as a reminder to registered electricity consumers that leasing a property does not extinguish their contractual and statutory responsibility to the utility provider. Any rights of recourse against a tenant must be expressly secured through the tenancy agreement.
meter tampering - registered user liability - electricity theft - back billing - loss of revenue - consumer responsibility - privity of contract