YTL Construction Found Negligent for Flooding at Surau Ar Rahman; High Court Awards RM180,000
In a significant ruling, the has found liable for negligence and continuing private nuisance after its construction works caused repeated flooding at Surau Ar Rahman, a community surau in Larkin Jaya, Johor Bahru. Judicial Commissioner Noradura Binti Hamzah awarded a total of RM180,000 in damages to the plaintiffs, comprising special damages for repair costs and agricultural losses, general damages for the prolonged interference with the surau's use, and aggravated damages for the distress caused to the worshipping community.
The Flooding Saga
Surau Ar Rahman, serving the local Muslim community since 1978, sits adjacent to Sungai Sebulong. For decades, three square box culverts efficiently channeled the river's flow without causing major flooding. In late 2019, YTL Construction, as the local contractor for the Electrified Double Track Project (EDTP) from Gemas to Johor Bahru, began earthworks and landfilling, replacing the original culverts with temporary pipe culverts.
The plaintiffs—Dato' Dr Ghazali Bin Ismail, chairman of the surau's management committee, and the —alleged that the temporary culvert was grossly inadequate. The contractor initially installed a single pipe, then added a second and third in what witnesses described as a "trial and error" approach. From November 2020 onward, the surau and adjacent agricultural land suffered repeated flooding—including four major events—with floodwaters entering the prayer hall waist-deep, destroying doors, furniture, carpets, Quran cabinets, and agricultural produce. The flooding only ceased in April 2022 when a permanent culvert became operational.
Defendant’s Own Evidence Tells the Tale
The court placed heavy reliance on YTL Construction's own documents. The insurer-commissioned Adjuster’s Final Report from concluded unequivocally that "the drainage system did alter the natural flow of the water course" and that the damage was "indeed caused by the construction works carried out by the Insured," with no intervening factor. The adjuster assessed initial losses at RM47,688 gross.
Even more damaging was the testimony of the defendant’s own consultant engineer, SD3, who admitted he had never visited the site, that no hydraulic analysis for the temporary culvert was ever conducted, that the contractor ignored his instruction to install three culverts from the start, and that the works altered the natural flow of the river. The court found that no construction drawing for the temporary culvert was ever submitted to the relevant authority, and that no Request for Inspection was made—meaning the culvert was never formally approved.
A Stop Work Order Ignored
The (MBJB) issued a Stop Work Order on 29 November 2020 under the Street, Drainage and Building Act 1974 , directing the immediate cessation of earthworks and ordering the replacement of the temporary culvert with a structure that did not obstruct water flow. Despite this, the defendant took seventeen months to make the permanent culvert fully operational, leaving the surau vulnerable to further flooding.
Negligence and Nuisance Established
The court found that YTL Construction owed a duty of care to neighbouring landowners. Multiple breaches were proven: no hydraulic analysis, failure to follow the consultant’s instructions, lack of inspection, un-compacted soil causing river sedimentation, and raising the construction site level above the surau. The interference with the surau’s use—disrupting five daily prayers and community religious activities for over seventeen months—constituted a substantial and unreasonable private nuisance.
The court rejected the defendant’s arguments that flooding pre-existed the project or that river pollution was the cause. It noted that before 2020, only minor water overflow occurred at the river reserve without structural damage. The original culverts had functioned for decades without major flooding.
Damages and Costs
Judgment was entered for the plaintiffs with the following awards:
- Special damages to the 1st plaintiff (surau repairs): RM95,000
- Special damages to the 2nd plaintiff (agricultural losses): RM20,000
- General damages for continuing nuisance: RM40,000
- Aggravated damages: RM25,000
- Interest at 5% per annum and costs fixed at RM120,000
The court declined injunctive relief as the permanent culvert had already resolved the flooding. The award of aggravated damages reflected the defendant’s conduct: concealing the Stop Work Order from its own engineer, leaving the permanent culvert unopened for over a year, and subjecting a place of worship to repeated inundation.
Key Observations
> "The Defendant’s own Adjuster’s Final Report... unequivocally attributes the flooding to the Defendant’s construction works and expressly states there was no other intervening factor."
> "The inadequacy of the temporary works lay not in cross-sectional area alone... the associated earthworks reduced the retention area upstream of the culvert while raising the level of the construction site above that of the surau."
> "The repeated flooding of a place of worship over a period of some seventeen months... constitutes a substantial and unreasonable interference with the Plaintiffs’ use and enjoyment of the surau premises."
> "The Defendant’s approach to the temporary culvert was described... as a matter of ’trial and error’, installing pipes incrementally rather than designing an adequate solution."
This judgment underscores the responsibility of contractors to design and maintain adequate temporary works, especially when operating near watercourses and occupied premises, and confirms that negligence and nuisance claims can succeed even against major infrastructure projects.
flooding - inadequate culvert - stop work order - continuing nuisance - place of worship - duty of care - aggravated damages