SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1993 Supreme(SC) 973

SUPREME COURT OF INDIA
S. R. PANDIAN, R. M. SAHAI AND Dr. A. S. ANAND, JJ.
State of W.B., Appellant
Versus
M/s. National Builders, Respondent.
Civil Appeal No. 1138 of 1991,
D/- 13-10-1993.

Advocates:
A.PRABHAVATHY, GOBINDA MUKHOTY, H.K.PURI, P.S.POTI, S.K.BANDHOPADHYAY, S.K.NANDY, SARVA M.MITTER

Headnote:

Constitution of India,1950 - Article 227 - Arbitration Act - Section 8(l)(b) and 12(2) - Construction of 250 bed hospital - Settlement of claim - Arbitration - Dispute about settlement of claim in respect of construction of 250 bed hospital at Basudevpura having arisen between respondent (contractor) and appellant (Public Works Department of the State of West Bengal) Chief Engineer nominated a Superintending Engineer as arbitrator in accordance with clause 25 of agreement, relevant part of which runs - Except where otherwise provided in contract all questions and disputes shall be referred to sole arbitration of Chief Engineer of department. Should Chief Engineer be for any reason unwilling or unable to act as such arbitrator, such questions and disputes shall be referred to an arbitrator to be appointed by Chief Engineer - Respondent approached Chief Engineer and sought for appointment of a retired Additional Chief Engineer named in application as the sole arbitrator - Request was not accepted as according to Chief Engineer arbitrator appointed was still continuing - Respondent was however permitted to approach Court for extension of time, respondent, instead of filing application for extension of time, approached Court of Asstt. District Judge under Section 12(2) of Act for revoking authority of sole arbitrator and filling vacancy by appointing another arbitrator –Held, Court had no power to supply vacancy under S. 8(l)(b) only if arbitration agreement did not show that parties did not intend to supply vacancy - If no such intention could be culled from the arbitration clause, Court could supply vacancy - Where agreement provides for appointment of a specific person either by name or by designation and that person refuses to act then question of appointing him again cannot arise - Refusal by such a person results in agreement clause ceasing to operate - When two parties agree for appointment of A or B by name or designation and the person so named refuses to act then agreement shall be deemed to have exhausted itself - Person so named having refused to act he cannot be asked again to arbitrate - That would be contrary to very basis of arbitration that no one can be forced to act against his free will - It would also be contrary to agreement and if there is no agreement to appoint another person, only remedy is to approach Court to exercise its statutory power and appoint another arbitrator - In court opinion submission is not well founded in law - A person nominated by sole arbitrator stands substituted in his place - He does not have any independent personality - Power and authority exercised by him is same as authority which nominated him - Therefore, once nominee refuses to act it shall be deemed that arbitrator mentioned in arbitration clause has refused to act and therefore clause would cease to operate in same manner as Chief Engineer himself has refused to act - Appeal dismissed.

Judgment

R. M. SAHAI, J.:- The two questions of law that arise for consideration in this appeal are if the refusal of an arbitrator to resign while not accepting the joint request of the parties to extend time for arbitration and leave it to them to decide their future course of action amounts to refusal to act by the arbitrator within the meaning of S. 8(l)(b) of the Arbitration Act (in brief the Act) and if it be so whether the power to appoint next arbitrator vests in the Court or it has once again to be in accordance with the procedure provided in the Agreement.

2. Dispute about settlement of claim in respect of construction of 250 bed hospital at Basudevpura having arisen between the respondent (contractor) and the appellant (Public Works Department of the State of West Bengal) the Chief Engineer nominated a Superintending Engineer as arbitrator in accordance with clause 25 of the agreement, relevant part of which runs as under :-

"Except where otherwise provided in the contract all questions and disputes shall be referred to the sole arbitration of the Chief Engineer of the department. Should the Chief Engineer be for any reason unwilling or unable to act as such arbitrator, such questions and disputes shall be referred to an arbitrator to be appointed by the Chief Engineer".

When despite 59 sittings the proceedings did not come to an end and the arbitrator entertained certain applications of the appellant at a belated stage the respondent sought his resignation for legal misconduct. The application was decided by the arbitrator by a detailed order with following observations:-

"I have given my opinion that there has been no misconduct on any of the grounds before me by the learned claimant yet I am of the opinion justice delayed is justice denied and hence in this case there has been delay and the process in which the learned advocate of both the parties are leading and pleading the case delay is inevitable. If the claimant suffers from loss of confidence and apprehends miscarriage of justice from the arbitrator whose award is vital to him I shall not intend to interfere in his way of pursuit for justice.

I, therefore, direct that further extension of time on consent of both the parties will not be allowed by me and the extended date of arbitration is being allowed to expire.

As regards claimants humble prayer to me that I would be pleased to resign from the office. I am restraining myself in issuing any order as it concerns interest of both the parties and I leave it to both the parties to decide."

With this order the respondent approached the Chief Engineer and sought for appointment of a retired Additional Chief Engineer named in the application as the sole arbitrator. The request was not accepted as according to the Chief Engineer the arbitrator appointed was still continuing. The respondent was however permitted to approach the Court for extension of time, the respondent, instead of filing application for extension of time, approached the Court of Asstt. District Judge under Section 12(2) of the Act for revoking authority of the sole arbitrator and filling the vacancy by appointing another arbitrator. The application was allowed as in the opinion of the Court the arbitrator in the circumstances of the case had refused to act. The order was challenged by way of application under Art. 227 of the Constitution. The application was dismissed as the inference drawn by the trial Court that the arbitrator refused to act was a plausible one. It is against this order that this appeal has been filed. It is not clear if during pendency of the application under Art. 227 in the High Court the appellant had applied for any interim order for stay of further proceedings before the arbitrator. However even if it was prayed for then it presumably was not granted as, admittedly, during pendency of the application the arbitrator appointed by the Asstt. Distt. Judge started the proceedings in which the Executive Engineer appeared but expressed












Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top