SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

1994 Supreme(SC) 864

SUPREME COURT OF INDIA
Faizan Uddin, P B Sawant
NAV BHARAT CONSTRUCTION CO., APPELLANT
VERSUS
STATE OF RAJASTHAN AND OTHERS, RESPONDENTS.
Civil Appeals Nos. 4643-53 of 1985 with Nos. 4261-62 of 1983, 2177-2180 of 1993, decided on September 7, 1994.

Important Points

A contractual clause stating that a specific official's decision shall be final and binding does not necessarily constitute an arbitration agreement under the Arbitration Act. However, the official remains duty-bound to decide the claims as per the contract terms, and such decisions are binding on the parties.

Subject

Arbitration Law - Arbitration Agreement

Act Referred

Headnote

Arbitration Act - Section 20 - Contract - Completion or abandonment - Except where otherwise specified in contract decision of Chief Engineer of Rajasthan for tie being shall be final conclusive and binding on all parties to contract upon all questions relating to meaning of specifications designs drawings instructions hereinbefore mentioned and as quality of workmanship or material used on work or as to any other question claim right matter or things whatever in any way arising out of or relating to contract design drawings specifications or estimates instructions orders or these conditions or otherwise concerning works or execution or failure to execute same whether arising during progress of works or after completion or abandonment thereof or contract by contractor shall be finally conclusive and binding on contractor – Held, Having said this court are view that Chief Engineer in present case ought to have decision matter as terms of clause agreement - He may not decide it as an arbitrator Arbitration Act since he has not been appointed as such clause - But he was duty-bound to decide firms claims after hearing it - As provided for in clause whatever decision he gives is binding on parties - While dismissing these appeals court therefore direct Chief Engineer of State to decide claims made by appellant as early as possible provided claims are made within four months from today - In circumstances of case there will be no order as to costs - Penalty proceedings which are adopted by State shall be subject to final outcome of decision Chief Engineer in claims that appellants will make before Chief Engineer - Stay granted by this Court in civil appeals shall stand vacated – Appeal dismissed

Legal Category Hierarchy

  • civil law
    • contract law
      • arbitration
        • arbitration agreement (Para 1, 2, 3, 4)
  • administrative law
    • government contracts (Para 1, 5, 6)

Table of Contents

1. Dispute regarding whether a contract clause granting final decision-making power to a government official constitutes an arbitration agreement under the Arbitration Act. (Para 1 )

2. Whether clauses granting final and binding decision-making power to a Chief Engineer amount to an agreement to refer disputes to arbitration under the Arbitration Act. (Para 1 )

3. A clause granting final decision-making power to an official is not an arbitration agreement if a larger bench has held an identical clause lacks such character. (Para 2 , 3 , 4 )

4. A contract clause granting final and binding decision-making power to a government official does not constitute an arbitration agreement under the Arbitration Act. (Para 2 , 3 )

5. Appeals dismissed; Chief Engineer directed to decide claims as per contract terms, with penalty proceedings subject to the outcome. (Para 6 )

6. Does a clause granting final and binding decision-making power to a government official constitute an arbitration agreement?

No. A clause stating that the decision of a government official shall be final, conclusive, and binding on all parties does not spell out an agreement to refer disputes to arbitration under the Arbitration Act. (Para 2 , 3 )

7. How is a conflict between a larger bench and a smaller bench of the same court resolved regarding the interpretation of contract clauses?

The decision of a larger bench is binding and cannot be disregarded in favor of a judgment delivered by a smaller bench. (Para 3 )

8. If a clause is not an arbitration agreement, is the designated official still required to decide the dispute?

Yes. Even if the official is not acting as an arbitrator under the Arbitration Act, they remain duty-bound to decide the claims as per the terms of the agreement. (Para 5 )

ORDER

1. We have heard Shri Mool Chand Loharia who is a partner of the appellant-firm. He has brought to our notice various decisions of this Court as well as of the various High Courts. The firm had entered into in all 17 written agreements with the State Government in respect of various works in three irrigation projects. The language of all the agreements was the same. The relevant clauses of the agreement which have given rise to the present controversy between the firm and the State Government are clauses 22 and 23 which read as follows :

"22. All work to be executed under the contract shall be executed under the direction and subject to the approval in all respect of the Chief Engineer of the Government of Rajasthan for the time being, who shall be entitled to direct at what point or points and what manner they are to be commenced, and from time to time carried on.

Decision of the Chief Engineer to be final

23. Except where otherwise specified in the contract the decision of the Chief Engineer of Rajasthan for the time being shall be final, conclusive and binding on all parties to the contract upon all questions, relating to the meaning of the specifications, designs, drawings, and instructions hereinbefore mentioned and as to the quality of workmanship, or material used on the work or as to any other question, claim, right, matter, or things whatever in any way arising out of or relating to the contract, designs, drawings, specifications or estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same, whether arising during the progress of works or after the completion or abandonment thereof or the contract by the contractor shall be finally conclusive and binding on the contractor."

His contention is that these clauses spell out an agreement to refer the dispute to the arbitration of the Chief Engineer, and the Chief Engineer, as an arbitrator, is supposed to follow the provisions of the Arbitration Act and give an award under the said Act. For that purpose, the firm had made an application to the Chief Engineer. Since the Chief Engineer did not accept that the provisions of the said clauses spelt out an agreement for arbitration, he did not respond to the said application. Therefore, the firm filed a suit in the District Court for requiring the Court to refer the matter to arbitration under Section 20 of the Arbitration Act. The District Judge by his decision of 20-9-1982 dismissed the application relying upon the decision of this Court in State of U.P. v. Tipper Chand [(1980) 2 SCC 341 : AIR 1980 SC 1522] wherein a clause identical to the present clause 23 was the subject-matter of a similar controversy between the parties and this Court has held that it did not spell out an agreement to refer the dispute to arbitration. The firms revision before the learned Single Judge was rejected on the same ground and it is against the said decision of the learned Single Judge dated 19-1-1983 that the present appeals, viz., CAs Nos. 4261-62 of 1983 have been preferred.

2. The three learned Judges of this Court in Tipper Chand case [(1980) 2 SCC 341 : AIR 1980 SC 1522] after taking note of the clause which is identical in language to the present clause 23 on which reliance is placed on behalf of the appellant for spelling out an arbitration agreement, have held that the clause does not spell out an agreement for arbitration of the disputes. No doubt there is a subsequent decision of this Court of two learned Judges in Rukmanibai Gupta v. Collector [(1980) 4 SCC 556 : AIR 1981 SC 479] which has constructed a clause which fell for consideration there as a provision for referring the disputes to arbitration. That clause reads as follows :

"15. Whenever any doubt, difference or dispute shall hereafter arise touching the construction of these presents or anything herein contained or any matter or things connected with the said lands or the working or non-working




1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top