Supreme Court Of India
A.K. Mathur and Markandey Katju, JJ.
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION - Appellant
Versus
RELIANCE ENERGY LTD - Respondent
With Civil Appeal 3551 Of 2006
Decided On : 08/14/2007
Advocates Appeared :
A.S.BHASME, ABHISHEK RAO, ALTAF AHMAD, ANAND K.GANESAN, J.J.BHAT, JAYASREE SINGH, K.V.BALAKRISHNAN, K.V.MOHAN, M.G.Ramachandran, M.V.KINI, NITESH JAIN, PRASHANT BHUSHAN, RAJESH KUMAR, Rajiv Shakdhar, Ramji Srinivasan, RAVI KINI, RUKHSANA CHAUDHARY, SHEFALI JAIN, Shyam Divan, SMIEETAA INNA, SUNITA CHANDURKAR, SWATI SINHA, SYED NAQVI, U.A.RANA, V.B.Joshi, VARUN THAKUR
( 1 ) THIS appeal under Section 125 of the of the Electricity Act, 2003 (hereinafter for short "the Act") is directed against the judgment and order dated 29th March, 2006 passed by the appellate Tribunal for Electricity whereby the appellate Tribunal has allowed the appeals filed by the distribution companies and set aside the orders passed by the Maharashtra electricity Regulatory Commission (hereinafter for short "the Commission") dated 23. 2. 2005. The Commission on 3. 8. 2004 addressed a notice to all its licensees/distribution companies in Maharashtra and made an inquiry from them with regard to raising of the bills by the said licensees/distribution companies on the basis other than the actual meter reading for the relevant period, when large variations in consumption were noticed, or for other reasons. The notice dated 3. 8. 2004 sent by the Commission to all its licensees/distribution companies reads as under :-
"several instances have come to the commission's notice of so-called "amendment", "supplementary" or other such bills being raised by some licensees to consumers, often several years later, on a basis other than the actual meter reading for the relevant period, when large variations in consumption are noticed, or for other reasons. Computerised systems have sometimes been put in place which generate such bills automatically. Wide variations observed in recorded consumption and other such apparent anomalies may be useful for monitoring, checking/testing of meters and for taking corrective action. However, billing on a basis other than recorded consumption, and raising amended bills accordingly (often after several years later, and without giving reasons), is not mandated by law. The electricity statutes (in the past, and at present) provide inter alia that, in case of metered consumers, energy consumption charges have to be billed on the basis of meter readings. Moreover, the licensee, and not the consumer, is responsible for maintaining, rectifying, or having such meters replaced where necessary. Thus, no "amendment" bills of the kind referred to above can be raised, and any additional billing has to follow due process and the provision of law. In the context of such "amendment" bills, I am directed to ask that the billing practices followed be immediately reviewed and brought into conformity with the statutory provisions. An affidavit stating the corrective action taken (including withdrawal of all such pending bills, and refund, though adjustment in energy bills or otherwise, of amounts received from consumers on or after 10/6/2003) may be furnished by 3rd september, 2004. "
( 2 ) IN response to the said notice all the licensees/distribution companies in maharashtra made their respective submissions before the Commission explaining under what circumstances the supplementary/ amended bills were sent to the consumers. They tried to justify raising of such bills and stated that the these bills were rightly sent as they found that some time the meters were not registering proper consumption and on that basis they tried to justify their action.
( 3 ) THE Commission examined the matter in detail and vide its order dated 23/2/2005 in para 46 directed as under:-
"46. After considering all these factors and the submissions made, the Commission directs that the supplementary/amendment bills issued in the circumstances set out at para 42 and 43 above from 10th June, 2003 (the date of coming into force of EA, 2003) and upto notification of the Supply code. a. should be withdrawn, if due meter testing has not been done with the results intimated to the consumer. b. any amounts collected should be refunded to the concerned consumers (without interest considering the earlier lack of clarity on this meter on the part of the licensees); c. where meters have been found to be defective upon subsequent due testing (and the results intimated to the consumer), the bills may be adjusted for upto 3 months prior to the date of testi
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.