SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(SC) 749

SUPREME COURT OF INDIA
T.S. THAKUR & GYAN SUDHA MISRA, JJ.
RATNAGIRI GAS & POWER PVT. LTD. Appellants.
VERSUS
RDS PROJECTS LTD. & ORS. – Respondent
Civil Appeal No. 7593 of 2012 (Arising out of S.L.P. (C) No.3571 of 2012) with Civil Appeal No. 7594 of 2012 (Arising out of S.L.P. (C) No.5554 of 2012) and Civil Appeal No. 7595 of 2012 (Arising out of S.L.P. (C) No.6180 of 2012)
Decided On : 18-10-2012.

Headnote:

Constitution Of India,1950 – appointment Engineers – Inquiry - Appeals arise out of common judgment and order passed by High Court of Delhi whereby Writ Petition filed by respondent has been allowed and rejection of tender submitted by it quashed with mandamus to appellant company to take fresh decision on subject in light of observations made by High Court factual matrix leading to filing writ petition by Project hereinafter referred to as for short has been set out at considerable length in order passed by High Court - Court do not therefore consider it necessary to re count same all over again except to extent same is absolutely necessary for disposal of these appeals - Suffice it to say that Government of India has entrusted task of reviving and restructuring of Dabhol Project to Gas Authority of India and National Thermal Power Corporation for short both Government India undertakings who have in turn formed joint venture company in name and style of Power –Held, Counsel for appellants - Concession even if made by one of parties could not prevent other parties from arguing that it did not bind them or that same was contrary to facts - High Court ought to have examined the issue on merits rather than taking short cut - High Court has incidentally taken support from certificate and clarification issued on to hold that had indeed executed qualifying project at Car Nicobar - Court had in course of hearing asked counsel for Central Government to disclose us basis on which certificate and clarification had been issued by the officers concerned - Court got no satisfactory answer to query - Court even asked parties to produce relevant record including government files so that court could ourselves answer question regarding eligibility but in absence of any conclusive evidence and in absence of specific finding from High Court on question court remained handicapped - Court comes to conclusion that is not eligible in terms of Clause first tender notice as it had not executed breakwater of requisite length Writ Petition filed by respondent shall stand dismissed - Resultantly appellant shall be free to carry forward and finalize process of allotment works started by it in terms of second tender notice - case however High Court comes to conclusion that was eligible to compete for works in question on basis of first tender notice subject to that finding attaining finality in any further appeal filed by aggrieved party appellant shall be free to issue fresh tender notice without altering conditions of eligibility as stipulated –Order accordingly

JUDGMENT

T.S. Thakur, J.-Leave granted.

2. These appeals arise out of a common judgment and order dated 17th October, 2011 passed by the High Court of Delhi whereby Writ Petition (C) No.534 of 2011 filed by the respondent has been allowed and the rejection of the tender submitted by it quashed with a mandamus to the appellant- company to take a fresh decision on the subject in the light of the observations made by the High Court.

3. The factual matrix leading to the filing of the writ petition by RDS Project Ltd. (hereinafter referred to as ‘RDS’ for short) has been set out at considerable length in the order passed by the High Court. We do not, therefore, consider it necessary to re-count the same all over again except to the extent the same is absolutely necessary for the disposal of these appeals. Suffice it to say that Government of India has entrusted the task of reviving and restructuring of the Dabhol Project to Gas Authority of India Ltd. (GAIL) and National Thermal Power Corporation (‘NTPC’ for short) both Government of India undertakings who have in turn formed a joint venture company in the name and style of Ratnagiri Gas & Power Pvt. Ltd., the appellant in this appeal, for short referred to as ‘RGPPL’. The appellant-RGPPL is charged with the duty of completing the balance work at LNG Terminal of the Dabhol Power project and of commissioning and operating the same. The appellant has, for that purpose, engaged GAIL as its Engineer who has in turn appointed Engineers India Limited (EIL) as their Primary Project Management Consultant. Scott Wilson a U.K. based entity was also kept in the loop as a backup consultant for marine works.

4. In terms of an international competitive bidding notice, issued by it on 26th June, 2009, EIL invited tenders from eligible parties for completion of, what is called “Breakwater” at LNG Terminal at RGPPL site, Dabhol, Maharashtra. The construction of the breakwater was left incomplete by a previously employed contractor appointed for the purpose on account of the stoppage of the work by the Dabhol Power Company. The earlier contractor had, according to the appellant, constructed only 500 meters of breakwater length leaving the balance of nearly 1800 meters incomplete and a certain length thereof untouched.

5. Apart from stipulating other terms and conditions, Clause 8.1.1.1 of the tender required that Single Bidders responding to the invitation should have experience of successfully completing as a single bidder or “as a lead of a Consortium/Joint Venture”, at least one project of a breakwater in an offshore location with a minimum length of 400 meters. Clause 8.1.1.1 of the Tender document was in the following words: “The bidder shall have experience of having successfully completed, as a single bidder or as a lead of a Consortium/Joint Venture, at least one project of a breakwater in an offshore location (as defined at Clause No.8.1.2.5 below) of minimum length of 400m during the last 20 (twenty) years to be reckoned from the last date of submission of bids. The scope of work of the proposed qualifying project work should comprise of the design, engineering, project management and construction of the breakwater.”

6. In response to the notice inviting tenders, EIL received five tenders from five different entities viz. RDS the respondent in this appeal, M/s ESSAR Construction Ltd., M/s Afcons Infrastructure Ltd., joint venture of M/s Higgard Punj Lloyd Ltd. and joint venture of M/s Hung- Hua/Ranjit Buildcon Ltd.

7. With the tender submitted by it RDS enclosed the requisite documents such as Form-B in which details of specific work experience, on the basis whereof it claimed to be satisfying the Bid Qualification Criteria (‘BQC’ for short), were also given. It also enclosed along with its tender, completion certificate dated 5th April, 2008 issued by Deputy Chief Engineer-IV, Andaman Harbour Works under the Ministry of Shipping, Road Transport and Highway, Government of India certifying

















































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top