SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2015 Supreme(SC) 333

SUPREME COURT OF INDIA
Dipak Misra, Uday Umesh Lalit, JJ.
National Highways Authority of India – Appellant
Vs.
M/s ITD Cementation India Limited – Respondents
CIVIL APPEAL NO. 9799 OF 2010 WITH Civil Appeal No.9908/2011, Civil Appeal No. 9909/2011, Civil Appeal No.2488/2012, Civil Appeal No. 7066/2011, Civil Appeal No.3150/2012, Civil Appeal No. 686/2013, Civil Appeal No.4069/2013, Civil Appeal No. 5162/2012, Civil Appeal No.5661/2014, Civil Appeal No. 10586/2014, Civil Appeal No. 3913/15(@S.L.P. (C) No. 10014/2013), Civil Appeal No.3914/15(@S.L.P. (C) No. 10701/2013), Civil Appeal No.7373/2012 AND Civil Appeal No.6158/2013
Decided on: 24-04-2015

IMPORTANT POINT
Interpretation of contract by Arbitral Tribunal would be final and binding unless patently illegal.
Deciding legality of levy existing on relevant date is beyond jurisdiction of Tribunal.

Headnote:(a) Government Contract – Interpretation – Interpretation of contract by Arbitral Tribunal – Final and binding – Court does not sit in appeal over the findings and decisions of arbitrator – Can be interfered only if unreasonable – Arbitration and Conciliation Act, 1996 – Section 28(1)(a). (Para 19, 20)

       (2012) 5 SCC 306; (2010) 11 SCC 296; (2015) 3 SCC 49; (2014) 9 SCC 263 – Relied upon

       (2006) 11 SCC 181; (2003) 5 SCC 705 – Referred

       (b) Government contract – Clause 70.1 to 70.7 and 70.8 – Cost due to price escalation and WPI changes on the one hand and additional cost due to increase in royalty due to legislative action – Both stand on different footing – Price escalation covered by clauses 70.1 to 70.7 – Additional cost due to increase in royalty covered by clause 70.8 – Respondent entitled for compensation – No infirmity in Arbitral award. (Para 21)

       (c) Government contract – Clause 32.1 – Rate of royalty enhanced by a legislation subsequent to conclusion of contract – Appellant relying upon clause 45.1 requiring respondent to include anticipated increase in taxes in contract price – Arbitral tribunal accepting that increase in royalty could be covered under the expression ‘future events’ in clause 32.1 – Hence holding respondent entitled to the same – A plausible view – While quoting the initial rates and prices, respondent could not have contemplated any revision in rates of royalty at a future date – No interference warranted. (Para 29)

       (d) Arbitration and Conciliation Act, 1996 – Section 31 – Royalty on ordinary earth already being levied on the relevant date – Must be deemed to have been part of the rates or prices quoted – No change due to any subsequent legislation – Clause 70.8 of COPA not applicable – Tribunal holding existing law to be without any authority in law – Legality of levy existing on relevant date beyond jurisdiction of Tribunal. (Para 36, 37)

       Facts of the case:

       A contact was awarded to the respondent by the appellant on 17.10.2001 for execution of work of widening of lanes and rehabilitation of the existing two lane carriageway of Vaniyambadi-Pallikonda section of NH-6 (from Km.49.00 to Km.100.00). The total value of the contract was appropriately Rs.183.71 crores. The parties adopted FIDIC form of Conditions of Contract with some changes made which are called Conditions of Particular Application (COPA).

       The Government of Tamilnadu by issuing a notification under Section 15 of the Mines and Minerals (Regulation & Development) Act, 1957, increased the seigniorage fee (synonymous with Royalty charges) on stone, sand and earth to the tune of nearly 30% with effect from 1st November, 2002, i.e. after about one year from commencement of the Work.

       The respondent requested for Price Adjustment consequent to the increase in rates of Royalty under Sub-Clause 70.8 of COPA. The request was rejected on the ground that the increase in royalty charge cannot be paid separately as the same was already considered under the Price Adjustment formula being paid for general materials under Sub-Clause 70.3 of COPA.

       In the aforesaid circumstances the dispute between the parties stood referred to Arbitral Tribunal.

       The Arbitral Tribunal unanimously found that the respondent had incurred additional cost because of the change in rates of Seigniorage fee pursuant to change in legislation and that the said increase in the rates had not been taken into account in the indexing of any inputs to the price adjustment formula in general materials and therefore the respondent would be entitled to be paid the additional cost incurred by it.

       The appellant being aggrieved by the Arbitral award filed OMP in the High Court of Delhi which was dismissed by a Single Judge of the High Court.

       The Division Bench however agreed with the appellant on the second submission and remitted the matter to the Arbitral Tribunal on the limited issue of quantification of the amount.

       The Arbitral Tribunal, on remand by Supreme Court, by its award dated 07.05.2010 quantified the sum that the respondent was entitled to on account of increase in the rates at Rs.43,06,810/- and awarded interest @ 12% p.a. from the date of publication till realization.

       

       Finding of the Court:

       Levy of royalty or taxes subsequent to contract would be additional cost.

       Result: All Civil Appeals except Civil Appeal No.6158 of 2013 dismissed.

       

Judgment

Uday Umesh Lalit, J.

1. Leave granted in S.L.P (C) Nos. 10014 of 2013 and 10701 of 2013.

A. Civil Appeal Nos. 9799 of 2010, 9908/2011, 9909/2011, 2488/2012, 7066/2011, 3150/2012, 686/2013, 4069/2013, 5162/2012 and 5661/2014, 10586/14, Civil Appeal @ from SLP © 10014/2013 and Civil Appeal @ from SLP © 10701 of 2013:

2. All these appeals by special leave raise identical questions and as such are being dealt with and considered by this common judgment. The learned counsel for the parties agreed that Civil Appeal No.9799 of 2010 be taken and was accordingly dealt with as the lead case.

CIVIL APPEAL NO. 9799 OF 2010

3. Civil Appeal No. 9799 of 2010, by Special Leave seeks to challenge the judgment and order dated 30.11.2007 passed by the Division Bench of the High Court of Delhi at New Delhi in FAO (OS) No.216 of 2007.

4. The dispute in question relates to the consequences of an additional amount of royalty payable by the respondent as a result of the notification for upward revision of royalty (Seignorage Fee as named in Tamil Nadu) on minor minerals. This additional royalty was imposed by the State of Tamil Nadu w.e.f. 01.11.2002. It is the plea of the appellant that the additional amount of fee was not liable to be paid to the respondent in view of certain clauses in the contract which provided for a formula of escalation, while according to the respondent the full amount had to be compensated.

5. A contact was awarded to the respondent by the appellant on 17.10.2001 for execution of work of widening of lanes and rehabilitation of the existing two lane carriageway of Vaniyambadi-Pallikonda section of NH-6 (from Km.49.00 to Km.100.00). The total value of the contract was appropriately Rs.183.71 crores. The parties adopted FIDIC form of Conditions of Contract with some changes made which are called Conditions of Particular Application (COPA, for short). In the invitation to tender forming part of the contact under Clause 13.4 it was agreed between the parties as under:

13.4. All duties, taxes and other levies payable by the Contractor under the Contract, or for any other cause, as of the date 28 days prior to the deadline for submission of bids, shall be included in the rates and prices and the total bid price submitted by the bidder, and the evaluation and comparison of bids by the Employer shall be made accordingly.

6. The aforesaid stipulation dealt with the impact and inclusion of duties, taxes and other levies, as of the date 28 days prior to the deadline for submission of bids and clarified that the same shall stand included in the rates and prices and the total bid price submitted by the Contractor. Any subsequent variation in Prices on account of variety of reasons or factors after such date was dealt with in Clauses 70 to 70.8 of the COPA and the relevant parts thereof are quoted hereunder:-

Clause 70: Changes in Cost and Legislation

Delete the text of Clause 70 in its entirety and substitute, therefore the following clauses 70.1 to 70.8.

Sub-Clause 70.1 : Price Adjustment

The amount payable to the Contractor and valued at base rates and prices pursuant to Sub-Clause 60.1 hereof shall be adjusted in respect of the rise or fall in the indexed cost of labour, Contractor’s equipment, Plant materials and other inputs to the Work, by the addition or subtraction of the amounts determined by the formulae prescribed in this Clause.

Sub-Clause 70.2: Other Changes in Cost

To the extent that full compensation for any rise or fall in the costs to the Contractor is not covered by the provisions of this or other Clauses in the Contract, the unit rates and, prices included in the Contract shall be deemed to include amounts to cover the contingency of such other rise or fall in cost.

Sub-Clause 70.3 :Adjustment Formulae

Contact price shall be adjusted for increase or decrease in rates and price of labour, materials, Plant, machinery, equipment, spares, fuels and lubricants in accordance with the following principles and procedures as per formulae




































































































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top