(b) Government contract – Tender – Decision making process not reaching finality – Bid of respondent no. 1 not yet accepted – No right accruing to respondent no. 1 – Not entitled to any notice or hearing before inviting fresh bids. (Para 14)
(c) Government contract – Tender – RFQ issued in 2010 – Bids not decided in six years – Fresh tendering justified. (Para 15)
Facts of the case:
The Nagar Nigam, Meerut, published a Notice dated May 26, 2010 inviting tenders of Request for Qualification (RFQ) for establishment of a new modern slaughter house at village Ghosipur, Meerut on Build-Operate and Transfer (BOT) basis. Subsequently, the Nagar Nigam issued RFP for construction, operation and maintenance of modern slaughter house at Ghosipur, Meerut on July 29, 2010. Pursuant to the aforesaid RFP, tenders were submitted by only three firms.
Out of the above three bids only two bids were found eligible for consideration. As respondent No.1 had offered minimum concession period, it was selected by the BEC for recommendation as a Developer.
In view of only two tenders instead of minimum three required by rules, the Nagar Nigam, Meerut issued fresh advertisement inviting applications for RFQ.
Being aggrieved, respondent No.1 herein preferred Civil Misc. Writ Petition before the High Court. The High Court, by means of the impugned judgment, has allowed the same by quashing the decision of BEC dated November 22, 2010.
Finding of the Court:
Impugned judgment is erroneous.
Result: Appeal allowed.
JUDGMENT :
A.K. Sikri, J.
Leave granted.
2) This appeal is directed against the final judgment and order dated July 26, 2011 passed by the High Court of Judicature at Allahabad in Civil Misc. Writ Petition No. 71568 of 2010. The High Court, vide the impugned judgment, was pleased to allow the writ petition preferred by respondent No.1 herein by quashing the decision dated November 22, 2010 of the Bid Evaluation Committee (for short, 'BEC') and directed that the bid of the appellant, as accepted by it on September 08, 2010, be dealt with in accordance with law from the stage of such acceptance.
3) The dispute pertains to the construction, maintenance and operation of a slaughter house in Meerut, Uttar Pradesh. The appellants are intending to construct a slaughter house with ultra modern technology. Origin of this plan of the Government can be traced to the directions which were given by this Court vide judgment dated December 07, 2006 in the case of Nagar Nigam, Meerut v. Al Faheem Meat Exports Pvt. Ltd. & Ors., (2006) 13 SCC 382 emphasizing the need for modernising the slaughter houses according to the prescribed standards. Pursuant to the aforesaid directions of this Court, the State Government vide its G.O. dated August 06, 2008, laid down Policy Guidelines for operation of animal slaughter houses owned by urban local bodies in the State on the basis of Private Public Participation (PPP) Model. It was provided that slaughter houses owned by urban local bodies can be given on PPP Model to private persons by public auction/tender process on the condition that the private participants will have to modernise slaughter houses according to the prescribed standards. Accordingly, the State Government vide its G.O. dated September 29, 2009 constituted BEC with regard to the operation of animal slaughter houses owned by urban local bodies in the State on the basis of PPP Model in accordance with G.O. dated August 06, 2008 and June 26, 2009. The BEC was required to follow the Guidelines as laid down vide G.O. dated June 29, 2007 for selection, contracting and monitoring of Consultants and Private Developers for PPP Projects in the State. As per the Guidelines, the selection of the Developer was to be made through two stage bidding process, i.e.: Stage I – Shortlisting of Developer through EOIs in the form of Request for Qualification (RFQs) Stage II – Selection of Developer from shortlisted, developer on the basis of Request for Proposal (RFPs) submitted by them containing two stage bids i.e. Technical and financial bids.
4) The Guidelines provide for a PPP. The BEC was empowered to examine all aspects and stages of developer selection, i.e. issuance of EOI, evaluation of EOI, shortlisting of Developers, deciding terms of reference, issuance of Request for Proposal (RFP), evaluation of technical and financial proposals, negotiations and final selection of Developer. After the requisite evaluations, the BEC was to recommend the name of a Bidder/Developer to the Competent Authority for award of contract and the final approval of the Developer for the PPP project was to be granted by the Competent Authority. As per the Guidelines, the Competent Authority was the Cabinet of Ministers of the Government of Uttar Pradesh.
5) The Nagar Nigam, Meerut, published a Notice dated May 26, 2010 inviting tenders of Request for Qualification (RFQ) for establishment of a new modern slaughter house at village Ghosipur, Meerut on Build-Operate and Transfer (BOT) basis. In the Notice, the estimated cost of the project was shown to be Rs.101.76 crores and the project was to be implemented within 24 months. Pursuant to the aforesaid Notice, financial and technical bids were received from three firms and the consultant had found all the three bids to be deficient and recommended for invitation of fresh bids. Accordingly, the Nagar Nigam again published a Notice dated June 29, 2010 inviting tenders of RFQ. Pursuant to the aforesaid Notice, five financial and technic
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.