SUPREME COURT OF INDIA
T. S. Thakur, CJI., R. Banumathi, Uday Umesh Lalit , JJ.
M/s Electrotherm (India) Ltd. – Appellant
Versus
Patel Vipulkumar Ramjibhai & Ors. – Respondents
CIVIL APPEAL NO. 7222 of 2016 (Arising out of SLP (Civil) No.16860 of 2012)
Decided On : 02-08-2016
(b) Environmental law – EIA Notification of 2006 – Public consultation/public hearing – Mandatory for granting Environmental Clearance – Committee approving Clearance on the ground of no additional requirement of land and withdrawal of ground water – Increased water requirement and entailing additional pollution load not considered – Appellant’s request for exemption from public hearing for grant of Environmental Clearance for expansion plan should not have been accepted. (Para 16, 17)
(2011) 7 SCC 338 – Relied upon
(c) Environmental law – Environmental Clearance granted by exempting the appellant from public consultation/ public hearing – Project already undertaken on basis of such clearance and most of the recommendations made by CPCB are complied with – Decision exempting public consultation/public hearing set aside and matter is relegated back to concerned Authorities to effectuate public consultation/public hearing – Directed that in the event of negative mandate at the public hearing, entire plant will not be closed down but the production shall be scaled down to the level of Environmental clearance dated 20.02.2008. (Para 20)
Facts of the case:
The Notification dated 14.09.2006 issued by the Central Government in exercise of powers conferred by sub-section(1) and Clause V of sub-section(2) of Section 3 of the Environment (Protection) Act, 1986 read with Clause(d) of sub-rule(2) of Rule 5 of the Environment (Protection) Rules, 1986 directed that the required construction of new projects or activities or the expansion or modernization of existing projects or activities listed in the Schedule to the Notification entailing capacity addition with change in process and or technology would be undertaken only after prior Environmental Clearance from the Central Government or as the case may be by the State Level Environment Impact Assessment Authority.
The Appellant set up a Steel Plant at Village Samakhiyali, for manufacturing various products after having received No Objection Certificate from Gujarat Pollution Control Board on 25.02.2005, which thereafter granted consent for manufacture of Pig Iron, Steel Billets/Slabs, Steel Bars and Rods, etc.
The Appellant later by its letter dated 30.11.2007 applied for Environmental Clearance. On 20.02.2008 the Government of India, Ministry of Environment and Forests granted Environmental Clearance for manufacture of Pig Iron, Steel Billets/Slabs, Steel Bars and Rods, etc.
The Appellant thereafter, applied for expansion of Steel Plant.
Environmental Clearance for the expansion was granted by Government of India, Ministry of Environment and Forests.
On or about 10.05.2010 Respondent No.1 herein filed Special Civil Application in the High Court of Gujarat, in public interest, seeking revocation of Environment Clearance granted to the Appellant for expansion of its plant.
The High Court allowed the Special Civil Application principally on the ground that the Environmental Clearance dated 27.1.2010 was granted without there being public consultation or public hearing which was a mandatory requirement under 2006 Notification.
Finding of the Court:
The decision making process in doing away with or in granting exemption from public consultation/public hearing, was not based on correct principles and as such the decision was invalid and improper.
Result: Appeal disposed of.
JUDGMENT
Uday Umesh Lalit, J.
1. Leave granted.
2. This appeal challenges the judgment and order dated 11.05.2012 passed by the High Court of Gujarat allowing Special Civil Application No.5986/2010 setting aside the Environmental Clearance dated 27.01.2010 and directing that the operations of the entire plant of the Appellant be stopped and that the operations could be continued only after fresh Environmental Clearance was accorded in its favour by the Ministry of Environment and Forests and Union of India.
3. The Environment Impact Assessment Notification dated 27.01.1994 issued by the Central Government in exercise of powers conferred by sub-section(1) and Clause V of sub-section(2) of Section 3 of the Environment (Protection) Act, 1986 read with Clause(d) of sub-rule(2) of Rule 5 of the Environment (Protection) Rules, 1986 stipulated inter alia that in case of expansion or modernization of any activity, if pollution load exceeded the existing one or the new project was listed in Schedule I to the said Notification, such activity would not be undertaken unless the Environmental Clearance was accorded by the Central Government. Same thought was carried and finds expressly stipulated in the Notification dated 14.09.2006 issued by the Central Government in supersession of the Notification dated 27.01.1994. The Notification dated 14.09.2006 directed that the required construction of new projects or activities or the expansion or modernization of existing projects or activities listed in the Schedule to the Notification entailing capacity addition with change in process and or technology would be undertaken only after prior Environmental Clearance from the Central Government or as the case may be by the State Level Environment Impact Assessment Authority. Clauses 2 and 4 of the Notification deal with requirements of prior Environmental Clearance and Categorization of Projects and Activities respectively. Under Clause 7 Environmental Clearance process comprises of four stages in sequential order, namely, (1)-Screening, (2) Scoping, (3) Public Consultation and (4) Appraisal.
4. The Appellant set up a Steel Plant at Village Samakhiyali, for manufacturing various products after having received No Objection Certificate from Gujarat Pollution Control Board (“GPCB”, for short) on 25.02.2005, which thereafter granted consent vide Authorization Order dated 10.11.2005 for manufacture of Pig Iron, Steel Billets/Slabs, Steel Bars and Rods, etc.
5. The Appellant had set up the Plant and begun manufacturing process and later by its letter dated 30.11.2007 applied for Environmental Clearance. On 20.02.2008 the Government of India, Ministry of Environment and Forests granted Environmental Clearance, the relevant portions of the Clearance being:-
“2.0 The Ministry of Environment and Forests has examined the application. It is noted M/s. Electrotherm (India) Ltd. have proposed expansion of Pig Iron Plant (150 to 350 TPD) with Captive Lignite/Coal char based Power Plant (24 MW) and WHRB (6MW) at Samakhiyali, Bhachhu, Kutch, Gujarat.
Total project area is 100.6276 ha. and expansion will be carried out in 20.79 ha. No National Park of Wildlife Sanctuary is located within 10 km ………………………............................... ……….. Total cost of project is Rs. 90.00 Crores……………...
3.0 Iron ore will be reduced in a Blast Furnace. ESP dust collectors, venture scrubbers, bag letters will be provided to control are emissions from WHRB, AFBSC, Boiler, Crusher House etc. Gas will be cleaned in GCP. Total water requirement of 650 M/day will be supplied by Gujarat water Supply and Sewage Board (GWSSB) Zero Discharge will be adopted. Fine particles of coke, iron ore and ETP sludge will be recycled and reused in the process. BF Slag will be sold to cement manufacturers of used for road construction. Fly ash will be used in the captive brick manufacturing plant. Cha
Lafarge Umiam Mining Private Limited -T.N. Godavarman Thirumulpad v. Union of India
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.