SUPREME COURT OF INDIA
T.S. Thakur, CJI., A.M. Khanwilkar, J.
Mahanadi Coalfields Ltd. & Ors. – Appellants
Vs.
M/s. Dhansar Engineering Co. Pvt. Ltd & Anr. – Respondents
Civil Appeal No. 9732 of 2016 (arising out of S.L.P.(Civil) No. 11876 of 2013)
Decided On : 27-09-2016
(b) Interpretation of contract – Clause 5 – A clause of the contract cannot be read in isolation – Other terms and conditions of the contract must be read as a whole. (Para 18)
(c) Interpretation of contract – Clause 5 – Authorising appellants to reduce or increase the tendered quantity by +/– 30% during subsistence of contract – Contract extended till 15th July 2004 – Order attaining finality – Appellants well within powers to allot extra 30% work on 11th June 2004. (Para 19)
(d) Interpretation of contract – Clause 5 – 45 clear days notice for extra quantity of work – Only if appellants required respondents to increase the machine capacity by upto 30% extra “daily” quantity – Instantly, appellants merely allotting extra 30% quantity without requiring the respondents to increase the daily quantity – Not unjustified. (Para 21, 23)
(e) Interpretation of contract – Penalty – Appellant not suffering any loss of production due to backing out of respondents – However, appellants had to get the work done at higher rate – Absence of notice to respondents before imposing penalty – Respondents could have invoked Clause 30.3 for reconsideration of penalty – Instead they approached High Court – High Court holding the demand to be impermissible – In view of setting aside of the impugned judgment, respondents given liberty to approach appellants – Question whether demand vitiated in absence of notice left open. (Para 24)
(1969) 2 SCC 554; (2014) 9 SCC 105; (1991) 1 SCC 212 – Referred
(f) Constitution of India – Article 226 – Availability of alternative remedy – Maintainability of writ petition – Not necessary to consider in present matter. (Para 25)
(2007) 9 SCC 593; (2003) 2 SCC 107; (2011)5 SCC 697; (2007) 10 SCC 88; (1998) 8 SCC 1 – Referred
Facts of the case:
The appellants issued notice inviting tenders for the work of extraction and transfer of Coal/Coal Measure Strata (CMS) by deploying “Surface Miners” on hiring basis at various Open Cast Projects, inter-alia, at Lakhanpur.
The respondents were declared the lowest bidder and work order was issued in favour of the respondents and a formal agreement was executed between the parties.
The respondents commenced the work of surface miners at Lakhanpur and completed around 70% of the awarded quantity by the end of February 2004. Due to financial problems faced by the respondents, they requested the appellants to allow them to close the contract by invoking power to reduce the quantity by 30% of awarded quantity, under clause 11 of the general terms and conditions of the NIT; and to issue fresh tender for the remaining work. The appellants did not accede to the said request. The respondents requested the appellants to extend the time frame for completion of the remaining contract upto 15th July 2004 as the contract period was only till 15th April, 2004.
Extension of three months time was granted while reserving the right to impose penalty.
As the contract period was subsisting till 15th July 2004, the appellants issued an approval order dated 11th June 2004 to increase of 30% extra quantity i.e. 14.8 Lakh cubic meter at the existing rate or next tender rate whichever is lower, amounting to Rs. 252.42 Lakh. The respondents however, reiterated that the contract be treated as closed -as they were on the verge of completing the quantity specified in the contract by 15th June 2004.
After a fresh tender process and a letter of intent was issued in favour of third party (Sainik Mining and Allied Services) but at a higher rate of Rs.31.50 per cubic meter.
The bills submitted by the respondents for the work executed under the contract dated 26th May 2003 were considered by the Board of the appellants
The Board of the appellants decided to impose penalty for non-execution of the balance contract work by the respondents and including the financial loss incurred by the appellants due to allocation of that work to third party at higher rate. Consequently an approval order for recovery of penalty was issued by the appellants on 3rd November 2005
The Division Bench of the High Court allowed the Writ Petition filed by the respondents.
Finding of the Court:
Impugned judgment cannot be sustained.
Result: Appeal allowed.
JUDGMENT :
A.M. Khanwilkar, J.
Leave granted.
2. This appeal challenges the judgment of the Division Bench of the High Court of Orissa at Cuttack dated 7th November 2012 in Writ Petition (Civil) No. 1093/2006.
3. Briefly stated, on 2nd December 2002 the appellants issued notice inviting tenders for the work of extraction and transfer of Coal/Coal Measure Strata (CMS) by deploying “Surface Miners” on hiring basis at various Open Cast Projects, inter-alia, at Lakhanpur.
The respondents were declared the lowest bidder having quoted Rs.17/-per cubic meter for the stated contract. A letter of intent was issued in favour of the respondents on 4th April, 2003 which was accepted by the respondents on 14th April, 2003. Work order was issued in favour of the respondents on 23rd April, 2003 and a formal agreement was executed between the parties on 26th May 2003. The relevant clauses of the agreement are clauses 2 to 5 which read as under:-
“2. Time shall be considered as one of the essence of the contract and the time for the completion of the contract shall be counted from 16.04.2003 of from the date of issue of L.O.I. to which terms the contractor agreed at the time when his tender was accepted and the contract shall be completed by 15.04.2004 provided, sufficient face is provided by the management.
3. The work order has already been issued for a period of one year for a quantity of 49,50,000 Cum. At the rate of Rs. 17.00/- Cum. for an amount of Rs. 8,41,50,000.00.
4. The contractor shall re-deploy the Surface Miner in other OCPs as per direction of the Company.
5. The tendered quantity may be reduced or increased by +/-30%. No claim shall lie on the company for such variation in quantity whether increase or decrease. The tenderer must be in a position to increase the machine capacity upon 30% extra daily quantity within 45 days notice.” (emphasis supplied)
4. As the agreement refers to the terms and conditions of the tender document, we may usefully refer to the relevant clauses therein.
“11.0 VARIATION IN SCHEDULED QUANTITY EXTENT AND RATE
The quantity given in the “Schedule of Quantity’s provisional and is meant to indicate the extent of the work and to provide a uniform basis for tendering and any variation either by addition or omission shall not vitiate the contract.
The tendered quantity may be reduced or increased by 30%. No claim shall be on the company for such variation in quantity whether increase or decrease. Tenderer must be in a position to increase the machine capacity within 45 days notice to achieve the extra increased quantity.
If the additional altered or substituted work includes any item of work for which no “rate is specified in the contract, “rate” for such item shall be determined by the Company Headquarters in the following manner:-
a. The rate shall be derived from the rate for similar or near similar item of work awarded in the Company, or
b. The rate shall be derived from contractor’s rate claimed for such item of work supported by analysis of the rate claimed by the contractor. The rate to be determined by the Company Headquarters as may be considered reasonable taking into account percentage of profit and overhead not exceeding ten percent or on the basis of market rate, if any prevailing at the time when work was done.
However, the Engineer-in-charge shall be at liberty to cancel the instruction by giving notice in writing and to arrange to carry out the work in such manner as he considers advisable under the circumstances. The contractor shall under no circumstances suspend the work in the plea of non-settlement of rates.
The time of completion of the originally contracted work shall be extended/reduced by the Company in the proportion that the additional/reduced work (in value) bears to the original contracted work (in value), as may be assessed and certified by the Engineer-in-charge.
The company through its Engine
Gorkha Security Services v. Government (NCT of Delhi)
Kumari Shrilekha Vidyarthi v. State of U.P.
Popcorn Enterainment v. City Development Corporation
Harbanslal Sahnia v. Indian Oil Corporation Ltd.
Union of India v. Tantia Construction Pvt. Ltd.
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.