SUPREME COURT OF INDIA
Ranjan Gogoi, CJI., Sanjay Kishan Kaul, K.M. Joseph, JJ.
DAMODAR VALLEY CORPORATION – Appellant
Versus
CENTRAL ELECTRICITY REGULATORY COMMISSION AND OTHERS – Respondent
Civil Appeal No. 4881 of 2010
Decided on : 03-12-2018
(b) Damodar Valley Corporation Act, 1948 – Section 38 – Capital – Not entirely equity – Means loan and equity and value of operating assets when first put to commercial use – Recovery under the Regulations – As return on equity in respect of the equity portion, and as interest on the loan component – No complaint raised about interest not being given in respect of interest which is ploughed back as capital. (Para 22, 23)
(2018) 8 SCC 281 – Relied upon
(2007) 3 SCC 33 – Referred
(c) Administration of justice – Appellant’s objection to calculating interest on loan by reducing the loan amount by the cumulative depreciation – Central Commission reiterating the procedure in the first round of litigation – Appellant not taking any exception to it in first round of litigation – Matter attaining finality – Not open to appellant to raise the same issue in the second round. (Para 27)
Facts of the case:
The appellant filed Petition No . 66/2005 seeking determination of its tariff for the period from 2004 to 2009. By order dated 3.10.2006, the Commission proceeded to determine the tariff.
Pursuant to the order of the Appellate Tribunal remanding the matter back for consideration, a revised tariff order came to be passed on 6.8.2009 by the Commission. The order dated 6.8.2009 came to be impugned by the appellant before the Appellate Tribunal and said appeal came to be dismissed.
Finding of the Court:
Appellant has not made out any case.
Result: Appeal dismissed.
JUDGMENT
K.M. Joseph, J.
By this appeal maintained under Section 125 of the Electricity Act 2003 (hereinafter referred to as the Act of 2003) , the appellant seeks to challenge the order passed by the Appellate Tribunal dismissing the appeal filed by the appellant against the order of the Central Electricity Regulatory Commission (hereinafter referred to as the Commission' ) .
BACKGROUND FACTS
2. The appellant is a statutory body constituted under the Damodar Valley Corporation Act, 1948 (hereinafter referred to as the DVC Act' ) . It was entrusted with multifarious functions. One of the functions it was entrusted was that it was duty bound to carry out generation, transmission and distribution of electrical energy both hydro electrical and thermal. It was also called upon to, operate schemes for irrigation, water supply and drainage besides flood control in the Damodar river and its tributaries. Acting under Section 20 of the DVC Act, the appellant was fixing the tariff for the electricity which it was generating and transmitting to its consumers. With the enactment of the Electricity Act in 2003, a suo motu proceeding was taken by the Commission with respect to the determination of the tariff of the appellant. Pursuant to the order dated 29. 03.2005 , the appellant filed Petition No . 66/2005 seeking determination of its tariff for the period from 2004 to 2009. By order dated 3.10.2006, the Commission proceeded to determine the tariff. The Commission proceeded to take note of the multifarious functions with which the appellant was entrusted. Its case that it was following a cost plus policy for fixation of its tariff as also the difficulties that would be posed by imposing the tariff under the Act of 2003 with effect from 1.4 .2004 was noticed. It was ordered that the tariff fixed by the Commission would apply from 2005-2006 and it was to operate from 1.4.2006. The Commission had also appointed one-man Commission. Besides the same it appreciated the scope of the Fourth proviso to Section 14 of the DVC Act and found that the provisions of the DVC Act which were not inconsistent with the 2003 Act would continue to hold good even after the enactment of the 2003 Act. Even if there was inconsistency between the DVC Act and the regulation made under the 2003 Act, the DVC Act would continue to operate. After settling the legal position, in this regard, the Commission proceeded to decide upon the various contentions relating to elements which were to constitute the tariff.
3. This order came to be challenged by the appellant before the Appellate Tribunal for Electricity. There were also appeals filed by the consumers. By order dated 23.11.2007 the Appellate Tribunal allowed the appeal filed by the appellant and ordered as follows:
"In view of the above the subject Appeal No.273 of 2006 against the impugned order of Central Commission passed on October 3, 2006 is allowed to the extent described in this judgment and we remand the matter to Central Commission for de novo consideration of the tariff order dated October 3, 2006 in terms of our findings and observations made hereinabove and according to the law. Appeal No. 271, 272 and 275 of 2006 and No. 08 of 2007 are also disposed of, accordingly."
4. Pursuant to the said order of the Appellate Tribunal remanding the matter back for consideration, a revised tariff order came to be passed on 6.8.2009 by the Commission. The order dated 6.8.2009 came to be impugned by the appellant before the Appellate Tribunal and said appeal came to be dismissed. It is said order by the Appellate Tribunal which is challenged in the present appeal. It may be noted at this juncture itself that the first order of the Appellate Tribunal dated 23.11.2007 came to be challenged before this Court by certain consumers of the appellant. Those appeals were taken up earlier and they came to be dismissed by this Court
Bhaskar Shrachi Alloys Limited v. Damodar Valley Corporation
Delhi Electricity Regulatory Commission v. BSES Yamuna Power Limited
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.