SUPREME COURT OF INDIA
R. BANUMATHI, INDIRA BANERJEE, JJ.
SP SINGLA CONSTRUCTIONS PVT. LTD. – Appellant
VERSUS
STATE OF HIMACHAL PRADESH AND ANOTHER – Respondents
CIVIL APPEAL NOS. 11824-11825 OF 2018 (Arising out of SLP(C) Nos.1274-75 of 2015)
Decided On : 04-12-2018
(2014) 11 SCC 560; (2018) 6 SCC 287 – Relied upon
(2017) SCC Online Del 7808 – Cited with approval
(b) Arbitration and conciliation Act, 1996 – Section 12(5) r/w Cl. (65) of General conditions of contract – Objection on appointment of an officer of the department as arbitrator on ground of bias – Rejected – Well settled that arbitration clauses in government contracts providing that an employee of the department will be the sole arbitrator are neither void nor unenforceable. (Para 11, 12)
(2009) 8 SCC 520; (2007) 5 SCC 304; (2004) 10 SCC 504; (2015) 2 SCC 52 – Relied upon
(c) Arbitration of Conciliation Act, 1996 – Section 11(6) and 12(5) – Appellant challenging appointment of arbitrator u/s 11(6) – Well settled that appointment of arbitrator has to be challenged before the arbitrator himself in the first instant. (Para 13) 21
(d) Arbitration and Conciliation (Amendment) Act, 2015 – Section 26 – Provisions of Act, 2015 – Cannot have retrospective operation in arbitral proceedings already commenced, unless the parties otherwise agree. (Para 16)
(2014) 11 SCC 560; (2018) 6 SCC 287 – Relied upon
(2017) SCC Online Del 7808 – Referred
(e) Arbitration – Appointment of arbitrator at the instance of the government – Arbitration agreement cannot be invoked for the second time. (Para 19)
(f) Arbitration and Conciliation Act, 1996 – Section 11 and 25 – Contractor not appearing before arbitral tribunal – Not filing any statement of claim – Instead, filing application u/s 11 – Arbitrator terminating arbitration u/s 25 – Application u/s 11 held impermissible. (Para 21)
Facts of the case:
The appellant was awarded construction work contract for a sum of Rs.14,29,81,500/-. An agreement was also entered into between the parties and clause (65) of the General Conditions of Contract contains arbitration clause. The period allowed for completion of work was on or before 04.01.2009. However, extension was granted to the appellant up to 30.06.2010. The work was completed by the appellant on 04.06.2011 and payment for the execution of work was made. The appellant raised a dispute and requested for the appointment of arbitrator. Pursuant to the request of the appellant, the Chief Engineer, HPPWD appointed the “Superintendent Engineer, Arbitration Circle, HPPWD, Solan” as the arbitrator in terms of clause (65) of the agreement. The arbitrator entered upon reference on 11.11.2013. The appellant after requesting for the appointment of arbitrator either remained absent from the proceedings or sought adjournments stating that he intends to challenge the appointment of arbitrator before the Chief Justice as per the provisions of Arbitration and Conciliation Act, 1996. Even after hearing, no statement of claim was filed by the appellant. Arbitration proceedings were terminated under Section 25(a) of the Arbitration and Conciliation Act, 1996.
The High Court held that the appointment of “Superintendent Engineer” as arbitrator being in terms of clause (65) of the agreement, Section 11(6) of the Act cannot be invoked. The appointment of arbitrator could not be challenged by way of an application under Section 11(6) of the 1996 Act.
Finding of the Court:
Application u/s 11 was impermissible.
Result: Appeals disposed of.
JUDGMENT
R. BANUMATHI, J.
Leave granted.
2. These appeals arise out of the judgments dated 10.03.2014 in Arbitration Case No.4049 of 2013 and dated 01.09.2014 in Review Petition No. RPST/20087/2014 passed by the High Court of Himachal Pradesh in and by which the High Court dismissed the Arbitration Petition and Review Petition filed by the appellant declining to appoint arbitrator holding that as per the terms of the agreement, arbitrator had already been appointed.
3. Brief facts which led to the filing of these appeals are as follows:-
The appellant was awarded construction work contract on 19.12.2006 relating to balance work of 214.00 mtrs. span C/C bearings on abutment bridge over river Beas at Harsipattan on Mandi Rewalsar Chandesh-Rakhota Maserah Sarkaghat Tihra Sandhole Alampur Jawalamukhi road for a sum of Rs.14,29,81,500/-. An agreement was also entered into between the parties and clause (65) of the General Conditions of Contract contains arbitration clause. The period allowed for completion of work was on or before 04.01.2009. However, extension was granted to the appellant up to 30.06.2010. The work was completed by the appellant on 04.06.2011 and payment for the execution of work was made. The appellant raised a dispute and requested for the appointment of arbitrator vide its letter dated 18.10.2013. Pursuant to the request of the appellant, the Chief Engineer, HPPWD appointed the “Superintendent Engineer, Arbitration Circle, HPPWD, Solan” as the arbitrator on 30.10.2013 and the said appointment had been made in terms of clause (65) of the agreement. The arbitrator entered upon reference on 11.11.2013. The appellant after requesting for the appointment of arbitrator either remained absent from the proceedings or sought adjournments stating that he intends to challenge the appointment of arbitrator before the Chief Justice as per the provisions of Arbitration and Conciliation Act, 1996. Even after hearing, no statement of claim was filed by the appellant. On 06.08.2014, arbitration proceedings were terminated under Section 25(a) of the Arbitration and Conciliation Act, 1996.
4. Being aggrieved by the appointment of “Superintendent Engineer, Arbitration Circle, Solan, HPPWD” as the arbitrator, the appellant filed petition before the High Court under Section 11(6) of the 1996 Act praying for appointment of independent arbitrator. The High Court placed reliance upon the judgment of this Court in Antrix Corporation Limited v. Devas Multimedia Private Limited (2014) 11 SCC 560 wherein it was held that in case, if any party is dissatisfied or aggrieved by the appointment of arbitrator in terms of the agreement by other party/parties, his remedy would be by way of petition under Section 13 of the 1996 Act, and, thereafter while challenging the award under Section 34 of the 1996 Act. The High Court held that the appointment of “Superintendent Engineer” as arbitrator being in terms of clause (65) of the agreement, Section 11(6) of the Act cannot be invoked. The appointment of arbitrator could not be challenged by way of an application under Section 11(6) of the 1996 Act. Being aggrieved by the dismissal of the arbitration petition, the appellant is before us.
5. On behalf of the appellant, learned senior counsel Mr. Maninder Singh submitted that the appointment by office after coming into operation of the 1996 Act, was no more permissible and any appointment could only be made in terms of Section 11 of 1996 Act. It was further submitted that since the arbitrator appointed by office had entered upon the reference, the appellant was compelled to file Arbitration Petition No.4049 of 2013 and the High Court erroneously rejected the prayer made on behalf of the appellant for appointment of an independent arbitrator by name. The learned senior counsel further submitted that the arbitrator appointed by office, is an employee in service of the HPPWD which the provision of Section 12(5) bars at the threshold. Learned senior counsel p
Antrix Corporation Limited v. Devas Multimedia Private Limited
Ratna Infrastructure Projects Pvt. Ltd. v. Meja Urja Nigam Private Limited
Board of Control for Cricket in India v. Kochi Cricket Private Limited
Indian Oil Corporation Limited v. Raja Transport Private Limited
Ace Pipeline Contracts (P) Ltd. v. Bharat Petroleum Corporation Limited
Union of India v. Uttar Pradesh State Bridge Corporation Limited
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.