SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2019 Supreme(SC) 1373

SUPREME COURT OF INDIA
R. BANUMATHI, A.S. BOPANNA, HRISHIKESH ROY, JJ.
Central Organisation For Railway Electrification – Appellant
Versus
M/S ECI-SPIC-SMO-MCML (JV) A Joint Venture Company – Respondent
Civil Appeal Nos. 9486-9487 of 2019 (Arising out of SLP(C) Nos.24173-74 of 2019)
Decided on : 17-12-2019

Advocates Appeared:
For the Petitioner(s):A.N.S. Nadkarni, Priyanka Das, Raj Bahadur Yadav, S.S. Rebello, Rashmi Malhotra, Sunil Upadhyay, Jitin Singhal, Advocates
For the Respondent(s):Sridhar Potaraju, Shiwani Tushir, Shwata Parihar, H. Usha Sri, Tulasi Vishnu Menon, Advocates

IMPORTANT POINTS
Appointment of arbitrator by High Court in contravention of terms of contract is not justified.
Merely because the arbitrators in panel are the retired employees who have worked in the Railways, it does not make them ineligible to act as the arbitrators in terms of section 12(5).
When power of General Manager to appoint arbitrator gets counter balanced by equal power to respondent to appoint arbitrator, the General Manager cannot be held incompetent to appoint arbitrators because he himself is ineligible to be appointed an arbitrator in terms of section 12(5).

Headnote:

(a) Arbitration and Conciliation Act, 1996 - Section 12(5) and Clause 64(3)(a)(i), General Conditions of Contract - Modified Clause 64(3)(a)(i) waiving off application of section 12(5) only cases where total disputed claim does not exceed Rs.1 crore - Instantly claims totaling Rs.165 crores - Said clause not applicable. (Para 16)

(b) Arbitration and Conciliation Act, 1996 - Section 11(6) and Clause 64(3)(b), General Conditions of Contract - Clause 64 modified after coming into force of the Arbitration and Conciliation (Amendment) Act, 2015 prescribing procedure for appointment of arbitral tribunal - Providing for appointment of three arbitrators - Even in application under section 11(6) respondent praying for appointment of a sole arbitrator in terms of clause 64 - Prayer for appointment of sole arbitrator and such appointment by High Court - Not justified. (Para 19, 21, 22)

(c) Arbitration and Conciliation Act, 1996 - Section 12(5) - Employees of Government department made ineligible to be appointed as arbitrator - Appellant keeping names of retired officers in panel of arbitrators - Merely because the arbitrators in panel are the retired employees who have worked in the Railways, it does not make them ineligible to act as the arbitrators. (Para 27)

(d) Arbitration and Conciliation Act, 1996 - Section 12(5) and 11(6); and Clause 64(3)(b), General Conditions of Contract - Appellant sending list of empanelled arbitrators to respondent for selecting two names in terms of clause 64(3)(b) - Respondent obliged to respond within thirty days which he did not do - Instead, filing application under section 11(6) - Contending that appellant extinguished his right to appoint arbitrator on foiling the application u/s 11(6) - Not sustainable. (Para 30)

(e) Arbitration and Conciliation Act, 1996 - Section 12(5) and Schedule VII r/w - Clause 64(3)(b), General Conditions of Contract - Contention that General manager of Railways being himself ineligible to be appointed as an arbitrator cannot nominate arbitrators - Contention negatived - Power of General Manager to appoint arbitrator gets counter balanced by equal power to respondent to appoint arbitrator. (Para 37, 38)

Facts of the case:

High Court rejected the contention of the appellant that the arbitrator is to be appointed as per General Conditions 64 (3)(a)(ii) and 64 (3)(b) of the Contract and appointed Shri Justice Rajesh Dayal Khare as the sole arbitrator for resolving the dispute between the parties.

Finding of the Court:

Appointment of arbitrator by High Court in contravention of terms of contract is not justified.

Merely because the arbitrators in panel are the retired employees who have worked in the Railways, it does not make them ineligible to act as the arbitrators in terms of section 12(5).

When power of General Manager to appoint arbitrator gets counter balanced by equal power to respondent to appoint arbitrator, the General Manager cannot be held incompetent to appoint arbitrators because he himself is ineligible to be appointed an arbitrator in terms of section 12(5).

Result: Appeals allowed.

JUDGMENT :

R. BANUMATHI, J.

Leave granted.

2. These appeals have been preferred against the impugned orders dated 03.01.2019 and 29.03.2019 passed by the High Court of Judicature at Allahabad in Arbitration Application No.151 of 2018 in and by which the High Court rejected the contention of the appellant that the arbitrator is to be appointed as per General Conditions 64 (3)(a)(ii) and 64 (3)(b) of the Contract and appointed Shri Justice Rajesh Dayal Khare as the sole arbitrator for resolving the dispute between the parties.

3. The appellant awarded work contract of Rs.165,67,98,570/-to the respondent-Company by an agreement dated 20.09.2010 which contains the arbitration clause. Subsequently, after coming into force of Arbitration and Conciliation (Amendment) Act, 2015 (w.e.f. 23.10.2015), the Government of India, Ministry of Railways made a modification to Clause 64 of the General Conditions of Contract and issued a notification dated 16.11.2016 for implementation of modification. The modified Clause 64(3)(a)(ii) (where applicability of Section 12(5) has been waived off) inter alia provided that in cases where the total value of all claims exceeds Rs. 1 crore, the Arbitral Tribunal shall consist of a panel of three gazetted Railway Officers not below JA (Junior Administrative) Grade or two Railway Gazetted Officers not below JA Grade and a retired Railway Officer, retired not below the rank of Senior Administrative (SA) Grade officer as arbitrators. The procedure for constitution of the Arbitral Tribunal is provided thereon. Clause 64(3)(b) deals with the appointment of arbitrator where applicability of Section 12(5) of the Arbitration and Conciliation Act has not been waived off. Clause 64(3)(b) stipulates that the Arbitral Tribunal shall consist of a panel of three retired railway officers not below the rank of Senior Administrative Officer as the arbitrators as per the procedure indicated thereon.

4. Since the respondent did not complete the work under the contract within the prescribed period, on 18.10.2017, the appellant issued “Seven days” notice under Clause 62 of the General Conditions of Contract to the respondent. Thereafter on 27.10.2017, the appellant issued a “48 hours’ notice” to the respondent calling upon the respondent to make good the progress of work, failing which the contract will stand terminated. Since the respondent did not make adequate progress in the work, on 01.11.2017, the contract was terminated as per Clause 62 of the General Conditions of the Contract. The respondent was also informed that their security deposit has been forfeited and the performance guarantee submitted by it shall also be encashed.

5. The respondent filed a Petition No.760 of 2017 before the High Court challenging the termination of the contract which came to be dismissed by the High Court vide order dated 28.11.2017 and the High Court directed the respondent to avail the alternative remedy by invoking arbitration clause. The respondent vide its letter dated 27.07.2018 requested the appellant for appointment of an Arbitral Tribunal for resolving the disputes between the parties and settle the claims value of Rs.73.35 crores. In reply dated 24.09.2018, the appellant sent a list of four serving Railway Electrification Officers of JA Grade to act as arbitrators. The respondent was asked to select any two and communicate to the appellant for formation of the arbitration tribunal panel. Vide letter dated 25.10.2018, the respondent was sent a list of another panel comprising four retired Railway officers. In terms of Clause 63(3)(b) of Railway’s General Conditions of Contract, the respondent was asked to select any two from this list and communicate them to the appellant within thirty days for constitution of the arbitration tribunal.

6. The respondent did not send a reply to the above letters of the appellant; but filed Arbitration Petition No. 151 of 2018 before High Court under Section 11(6) of the Arbitration and Conciliation Act seek


Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top