SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2022 Supreme(SC) 1184

SUPREME COURT OF INDIA
DHANANJAYA Y. CHANDRACHUD, CJI., A.S. BOPANNA, J.B. PARDIWALA, JJ.
The Tata Power Company Limited Transmission - Appellant
Versus
Maharashtra Electricity Regulatory Commission & Ors - Respondents
Civil Appeal No. 1933 of 2022
Decided On : 23-11-2022

Important Points

IMPORTANT POINT
Determination and regulation of tariff – Electricity Act 2003 provides States sufficient flexibility to regulate intra-state transmission systems, wherein Appropriate State Commissions possess power to determine and regulate tariff.

Subject

Energy Law - Electricity Transmission and Tariff Regulation

Act Referred

ELECTRICITY ACT: S.111, S.14, S.15, S.125, S.39, S.180, S.63, S.61, S.181
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (MULTI YEAR TARIFF) REGULATIONS: Reg.8

Headnote

Electricity Act, 2003 – Sections 62 and 63 – Determination and regulation of tariff – Electricity Act 2003 provides States sufficient flexibility to regulate intra-state transmission systems, wherein Appropriate State Commissions possess power to determine and regulate tariff – Electricity Act 2003 seeks to distance State Governments from determination and regulation of tariff, placing such power completely within ambit of Appropriate Commissions – Provisions of Electricity Act 2003 do not prescribe one dominant method to determine tariff – Section 63 operates after bidding process has been conducted – Where tariff has already been determined through bidding, Appropriate Commission has to adopt such tariff that has been determined – Appropriate Commission cannot negate such tariff determined through bidding by using its powers under Section 62 – Electricity Act 2003 or policy framework, particularly NTP 2016 read with GoM GR dated 4 January 2019, did not make it binding upon MERC to allot HVDC project only through TBCB route. (Paras 128 and 129)

Result : Appeal dismissed.

Legal Category Hierarchy

  • energy law
    • electricity act 2003
      • tariff determination
        • regulated tariff mechanism (Para 71)
        • tariff based competitive bidding (Para 72, 73)
      • transmission licensing (Para 54, 55)
  • administrative law
    • statutory bodies
      • regulatory commissions
        • powers and functions (Para 83, 86)
  • practice and procedure
    • appeals
      • statutory appeals (Para 106, 125)

Advocates appeared:
For the Appellant(s) : Mr. Shyam Divan, Sr. Adv. Mr. Shri Venkatesh, Adv. Ms. Kanika Chugh, Adv. Mr. Nitin Saluja, AOR Mr. Suhael Buttan, Adv. Mr. Siddharth Joshi, Adv. Mr. Vineet Kumar, Adv. Mr. Anant Singh, Adv. Ms. Shivani Luthra Lohiya, Adv.
For the Respondent(s): Mr. Vikas Singh, Sr. Adv. Mr. Mahesh Agarwal, Adv. Mr. Hemant Singh, Adv. Ms. Deepa Chawan, Adv. Mr. Arshit Anand, Adv. Ms. Geetika Sharma, Adv. Mr. Harshit Singh, Adv. Mr. Mridul Chakravarty, Adv. Mr. Biju Mattam, Adv. Mr. Lakshyajit Singh Bagdwal, Adv. Ms. Lavanya Panwar, Adv. Ms. Reshma Nathani, Adv. Ms. Deepeika Kalia, Adv. Mr. Aditya Kayla, Adv. Mr. E. C. Agrawala, AOR Ms. Amita Singh Kalkal, AOR Mr. Sudhanshu S. Choudhari, AOR Mr. Mahesh P. Shinde, Adv. Ms. Rucha A. Pande, Adv. Ms. Veeraragavan M., Adv. Mr. Sachin Patil, AOR Mr. Siddharth Dharmadhikari, Adv. Mr. Aaditya A. Pande, AOR Mr. Bharat Bagla, Adv. Ms. Kirti Dadheech, Adv.

Table of Contents

1. Grant of transmission licence for HVDC project — Dispute over tariff determination modality — Regulated Tariff Mechanism under Section 62 versus Tariff Based Competitive Bidding under Section 63, Electricity Act. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 )

2. Whether Tariff Based Competitive Bidding is the dominant route for transmission licences — Applicability of National Tariff Policy and State Government Resolutions to existing versus new projects. (Para 43 , 44 )

3. Sections 62 and 63 provide alternative modalities — National Tariff Policy is a material consideration but not binding — Concurrent findings on project status are not reopenable. (Para 69 , 70 , 71 , 72 , 73 , 74 , 75 , 76 , 77 , 78 , 79 , 80 , 81 , 82 , 83 , 84 , 85 , 86 , 87 , 88 , 89 , 90 , 91 , 92 , 93 , 94 , 95 , 96 , 97 , 98 , 99 , 100 , 101 , 102 , 103 , 104 , 105 , 106 , 107 , 108 , 109 , 110 , 111 , 112 , 113 , 114 , 115 , 116 , 117 , 118 , 119 , 120 , 121 , 122 , 123 , 124 , 125 , 126 , 127 )

4. Sections 62 and 63 are alternative routes — National Tariff Policy is a material consideration, not a binding mandate — Concurrent findings of fact are final under Section 125. (Para 74 , 94 , 99 , 106 )

5. Appeal dismissed — State Regulatory Commissions directed to frame regulations under Section 181 regarding tariff determination modalities within three months. (Para 128 , 129 , 131 , 132 )

6. Is the Tariff Based Competitive Bidding (TBCB) route under Section 63 the dominant method for determining transmission tariffs?

No. Sections 62 and 63 provide alternative modalities. Section 63 is invoked after a bidding process is conducted; it does not take precedence over Section 62 at the stage of choosing the modality of tariff determination. (Para 73 , 74 , 77 )

7. Is the National Tariff Policy (NTP) binding on State Regulatory Commissions when determining tariff modalities?

The NTP is a statutory policy and a material consideration that must guide the Commission, but it is not a binding mandate that overrides the Commission's general regulatory discretion to determine tariffs. (Para 88 , 94 , 99 )

8. Can the Supreme Court reopen concurrent findings of fact recorded by a Regulatory Commission and an Appellate Tribunal in an appeal under Section 125?

No. An appeal under Section 125 of the Electricity Act is maintainable only on substantial questions of law. Concurrent findings of fact recorded by the lower fora cannot be reopened. (Para 106 )

9. Does a State Government Resolution mandating TBCB for new projects bind the State Regulatory Commission?

Not unless issued as a direction in matters of policy involving public interest under Section 108. Tariff fixation falls within the independent statutory domain of the Regulatory Commission. (Para 110 , 111 , 112 )

JUDGMENT :

Dhananjaya Y. Chandrachud, CJI.

A glossary of defined terms used in the judgment has been provided below:

Glossary of Terms

Defined Term

Definition

Act

Electricity Act, 2003

AEMIL/second respondent

Adani Electricity Mumbai Infra Limited

AEML-T third respondent

Adani Electricity Mumbai Limited - Transmission

APTEL

Appellate Tribunal for Electricity

CEA

Central Electricity Authority Development Guidelines Guidelines for encouraging Competition in Development of Transmission Projects

DPR

Detailed Progress Report

EC/fifth respondent

Empowered Committee

FoR

Forum of Regulators

GoM’s GR

Government of Maharashtra’s, Government Resolution dated 04.01.2019

HVDC

High Voltage Direct Current

HVDC Project

1000 MW HVDC (VSC based) link between 400 kV MSETCL Kudus & 220 kV AEML Aarey EHV Station

MERC/first respondent

Maharashtra Electricity Regulatory Commission

MERC MYT Regulations

Maharashtra Electricity Regulatory Commission (Multi Year Tariff) Regulations 2019

MERC MYT Amendment Regulations

Maharashtra Electricity Regulatory Commission (Multi Year Tariff) (First Amendment) Regulations 2022

MoP

Ministry of Power

MSETCL/fourth respondent

Maharashtra State Electricity Regulatory Commission

NEP

National Electricity Policy

NTP 2006

National Tariff Policy 2006

NTP 2016

National Tariff Policy 2016

REL

Reliance Energy Ltd.

R-Infra

Reliance Infrastructure Limited

RTM

Regulated Tariff Mechanism

STU

State Transmission Utility

TBCB

Tariff Based Competitive Bidding

TBCB Guidelines

Tariff Based Competitive Bidding Guidelines for Transmission Service issued by the MoP dated 13.04.2006

TPC-T/appellant

Tata Power Company Limited Transmission

VSC

Voltage Source Converter

This judgment has been divided into the following sections to facilitate analysis:

A. The Facts

B. Proceedings before the MERC and APTEL

C. The Submissions

D. Regulatory Framework

D. 1 Electricity Act 2003

D.2 Policy framework

D. 2.1 Central

D. 2.2 State Policies

E. The Analysis

E. 1 Section 63 : The dominant route or the alternative route

E. 1.1. The value of TBCB Guidelines prescribed under Section 63

E. 2 General Regulatory Power of the Appropriate Commission

E.2.1 The nature of NTP- binding or a material consideration

E. 3 Value of GoM GR

E. 3. 1The New- Old Conundrum

E. 3. 2 Relevance of GoM GR for MERC’s Decision

E. 3. 3 Relevance of GoM GR vis-à-vis MSETCL’s decision

F Conclusion

1. APTEL, by its judgment dated 18 February 2022, dismissed an appeal under Section 111 of the Act instituted by the appellant against a decision of MERC dated 21 March 2021.

2. On 21 March 2021, MERC granted a transmission licence to AEMIL under Sections 14 and 15 of the Act for setting up a 1000 MW HVDC (VSC based) link between 400 kV MSETCL Kudus and 220 kV AEML Aarey EHV Station.

3. The appellant challenged MERC’s order before APTEL, inter alia, on the ground that the grant of the licence was not preceded by a TBCB process. TPC-T contended that the failure to adhere to a TBCB process pursuant to Section 63 was contrary to public interest and statutory mandate. APTEL dismissed the appeal. This has given rise to a statutory appeal under Section 125 of the Act.

A. The Facts

4. On 12 November 2007, MSETCL issued a communication to CEA stating, inter alia, that it was difficult to lay overhead AC lines to bring power from the new 400kV sub-station, which was required to meet Mumbai’s growing demand of power, to Mumbai’s load centres due to constraints. Hence, it was proposed that VSC based HVDC technology may be utilised to connect the new sub-station with major load centres in Mumbai through DC cab


1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top