SUPREME COURT OF INDIA
DHANANJAYA Y. CHANDRACHUD, CJI., A.S. BOPANNA, J.B. PARDIWALA, JJ.
The Tata Power Company Limited Transmission - Appellant
Versus
Maharashtra Electricity Regulatory Commission & Ors - Respondents
Civil Appeal No. 1933 of 2022
Decided On : 23-11-2022
Electricity Act, 2003 – Sections 62 and 63 – Determination and regulation of tariff – Electricity Act 2003 provides States sufficient flexibility to regulate intra-state transmission systems, wherein Appropriate State Commissions possess power to determine and regulate tariff – Electricity Act 2003 seeks to distance State Governments from determination and regulation of tariff, placing such power completely within ambit of Appropriate Commissions – Provisions of Electricity Act 2003 do not prescribe one dominant method to determine tariff – Section 63 operates after bidding process has been conducted – Where tariff has already been determined through bidding, Appropriate Commission has to adopt such tariff that has been determined – Appropriate Commission cannot negate such tariff determined through bidding by using its powers under Section 62 – Electricity Act 2003 or policy framework, particularly NTP 2016 read with GoM GR dated 4 January 2019, did not make it binding upon MERC to allot HVDC project only through TBCB route. (Paras 128 and 129)
Result : Appeal dismissed.
JUDGMENT :
Dhananjaya Y. Chandrachud, CJI.
A glossary of defined terms used in the judgment has been provided below:
| Glossary of Terms | |
| Defined Term | Definition |
| Act | Electricity Act, 2003 |
| AEMIL/second respondent | Adani Electricity Mumbai Infra Limited |
| AEML-T third respondent | Adani Electricity Mumbai Limited - Transmission |
| APTEL | Appellate Tribunal for Electricity |
| CEA | Central Electricity Authority Development Guidelines Guidelines for encouraging Competition in Development of Transmission Projects |
| DPR | Detailed Progress Report |
| EC/fifth respondent | Empowered Committee |
| FoR | Forum of Regulators |
| GoM’s GR | Government of Maharashtra’s, Government Resolution dated 04.01.2019 |
| HVDC | High Voltage Direct Current |
| HVDC Project | 1000 MW HVDC (VSC based) link between 400 kV MSETCL Kudus & 220 kV AEML Aarey EHV Station |
| MERC/first respondent | Maharashtra Electricity Regulatory Commission |
| MERC MYT Regulations | Maharashtra Electricity Regulatory Commission (Multi Year Tariff) Regulations 2019 |
| MERC MYT Amendment Regulations | Maharashtra Electricity Regulatory Commission (Multi Year Tariff) (First Amendment) Regulations 2022 |
| MoP | Ministry of Power |
| MSETCL/fourth respondent | Maharashtra State Electricity Regulatory Commission |
| NEP | National Electricity Policy |
| NTP 2006 | National Tariff Policy 2006 |
| NTP 2016 | National Tariff Policy 2016 |
| REL | Reliance Energy Ltd. |
| R-Infra | Reliance Infrastructure Limited |
| RTM | Regulated Tariff Mechanism |
| STU | State Transmission Utility |
| TBCB | Tariff Based Competitive Bidding |
| TBCB Guidelines | Tariff Based Competitive Bidding Guidelines for Transmission Service issued by the MoP dated 13.04.2006 |
| TPC-T/appellant | Tata Power Company Limited Transmission |
| VSC | Voltage Source Converter |
This judgment has been divided into the following sections to facilitate analysis:
| A. The Facts B. Proceedings before the MERC and APTEL C. The Submissions D. Regulatory Framework | |
| D. 1 Electricity Act 2003 D.2 Policy framework D. 2.1 Central D. 2.2 State Policies | |
| E. The Analysis | |
| E. 1 Section 63: The dominant route or the alternative route E. 1.1. The value of TBCB Guidelines prescribed under Section 63 E. 2 General Regulatory Power of the Appropriate Commission E.2.1 The nature of NTP- binding or a material consideration E. 3 Value of GoM GR E. 3. 1The New- Old Conundrum E. 3. 2 Relevance of GoM GR for MERC’s Decision E. 3. 3 Relevance of GoM GR vis-à-vis MSETCL’s decision | |
| F Conclusion | |
1. APTEL, by its judgment dated 18 February 2022, dismissed an appeal under Section 111 of the Act instituted by the appellant against a decision of MERC dated 21 March 2021.
2. On 21 March 2021, MERC granted a transmission licence to AEMIL under Sections 14 and 15 of the Act for setting up a 1000 MW HVDC (VSC based) link between 400 kV MSETCL Kudus and 220 kV AEML Aarey EHV Station.
3. The appellant challenged MERC’s order before APTEL, inter alia, on the ground that the grant of the licence was not preceded by a TBCB process. TPC-T contended that the failure to adhere to a TBCB process pursuant to Section 63 was contrary to public interest and statutory mandate. APTEL dismissed the appeal. This has given rise to a statutory appeal under Section 125 of the Act.
A. The Facts
4. On 12 November 2007, MSETCL issued a communication to CEA stating, inter alia, that it was difficult to lay overhead AC lines to bring power from the new 400kV sub-station, which was required to meet Mumbai’s growing demand of power, to Mumbai’s load centres due to constraints. Hence, it was proposed that
Energy Watchdog v. Central Electricity Regulatory Commission
PTC India Ltd. v. Central Electricity Regulatory Commission
Determination and regulation of tariff – Electricity Act 2003 provides States sufficient flexibility to regulate intra-state transmission systems, wherein Appropriate State Commissions possess power ....
The court clarified that Section 63 of the Electricity Act allows local authorities to apply for tariff adoption, rejecting the APTEL's restrictive interpretation.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.