SUPREME COURT OF INDIA
S. Ravindra Bhat, Pamidighantam Sri Narasimha, JJ.
The Chief Engineer, Water Resources Department & Ors. - Appellants
Versus
Rattan India Power Limited Through Its Director & Ors. - Respondents
Civil Appeal No. 8550 of 2022 Arising Out Of SLP (C) No. 28161 of 2016
Decided On : 13-01-2023
Government Contract – Diversion of Water for Industrial Use – Reduction of total liability towards irrigation restoration charges – Sustainability of – Respondent No.1 itself has willfully and deliberately entered into agreement knowing fully well legal and business consequences – There existed agreement between parties which stipulated a sum of Rs.1,00,000 as irrigation restoration charges and pursuant to this agreement, Respondent No.1 had even issued an undertaking – High Court committed error in entertaining a fresh writ petition which effectively claimed same reliefs as of previous one – High Court committed mistake in not only entertaining writ petition but also in supplanting its view over that of contract – Impugned final judgment and order passed by High Court set aside. (Paras 20 and 22)
Facts of the case:
Short question which arises for our consideration in present case relates to whether a party to a contract is entitled to question amount of consideration after signing contract.
Findings of Court:
Balance amount due and payable towards irrigation restoration charge shall be paid by Respondent No.1 on or before 30.06.2023. Further, interest @ 12% p.a. shall be payable from the date instalment/payment fell due till the date of the impugned order i.e., 05.05.2016.
Result : Civil Appeal allowed.
JUDGMENT :
PAMIDIGHANTAM SRI NARASIMHA, J.
1. The short question which arises for our consideration in the present case relates to whether a party to a contract is entitled to question the amount of consideration after signing the contract. By adverting to the facts of the case, we have held that Respondent No.1 is estopped from doing so because the Appellant, in all its communications, had sought for an amount of Rs.1,00,000 as irrigation restoration charges i.e., consideration for diversion of water for industrial use, which was earlier reserved for irrigational purposes. Even the contract entered into between the parties prescribed the same amount. In fact, Respondent No.1 agreed to the pay the consideration by issuing an undertaking on the date of signing of the contract. In any case, this contractual dispute concerning the reduction of irrigation restoration charges, was contested by the parties in an earlier Writ Petition before the High Court of Judicature at Bombay, and the High Court by its order dated 22.11.2012 had dismissed the challenge. This is the second round of litigation on the same issue.
2. This appeal by the State of Maharashtra is against the judgment of the Division Bench of the High Court of Judicature at Bombay at Nagpur1[In WP No. 4968 of 2015 dated 05.05.2016], whereby the High Court has reduced the ‘irrigation restoration charges’ which the Respondent herein has contracted to pay, from Rs.1,00,000 per hectare to Rs.50,000 per hectare. This has the effect of reducing the total liability of the Respondent towards irrigation restoration charges from Rs. 232.18 Crores to Rs.116.09 Crores.
3. The matter before us concerns the levy of ‘irrigation restoration charge’ by the Appellant as per Government Resolution dated 01.03.2009. The Respondent and other similarly placed companies use water for industrial purposes, which is otherwise reserved for irrigation of agricultural land. The usage of water for industrial purposes is seen as loss of water for irrigation, and in order to compensate for the same, the said charge is levied and collected by the Appellant. These charges are levied after taking into account the total number of hectares which will be deprived of irrigation due to the diversion of water for industrial use.
4. The other cost levied by the Appellant is the ‘capital expenditure charge’. This charge is used towards the construction and maintenance of dams. The payment of this charge is optional. Therefore, in the present case, we are not concerned with the levy and payment of the ‘capital expenditure charge’.
Facts:
5. On 21.02.2004, the Irrigation Department of the State of Maharashtra came up with a circular wherein it was prescribed that when water is diverted for non-irrigation purposes, then the entity using such water shall pay a sum of Rs.50,000 per hectare as irrigation restoration charges. The circular stated that no water shall be diverted unless an agreement is entered into between the concerned industry and the government.
6. Sophia Power Company Ltd.2[hereinafter referred to as ‘SPCL’], the predecessor of Respondent No.1 herein, intended to set up a 2640MW thermal power plant. For that purpose, a communication dated 12.12.2007 was sent by SPCL to the Maharashtra Industrial Development Corporation to confirm the availability of 240 million liters of water per day to facilitate the smooth running of the thermal power plant. Pursuant to the application made by SPCL, a high-powered committee constituted by the State of Maharashtra in its meeting held on 21.02.2008, granted in-principle approval for the usage of water by SPCL. This in-principle approval was subject to SPCL paying capital contribution and irrigation restoration charges. The high-powered committee named the Appellant herein as the implementing agency.
7. On 25.07.2008, the Vidarbha Irrigation Development Corporation granted f
A party to a contract is not entitled to question amount of consideration after signing contract.
The main legal point established in the judgment is the requirement for mutual consent to vary the terms of an existing agreement and the need for a clear modification or amendment to change the bill....
The court emphasized the principle of fairness in contractual agreements and the importance of upholding executed contracts.
(1) If Arbitrator construes term of contract in a reasonable manner, award cannot be set aside with reference to deduction drawn from construction.(2) Setting aside of arbitral award – Narrow scope o....
Water cess can only be imposed when water is drawn from irrigation works as defined by the Bihar Irrigation Act, 1997, and requires a prior notification to classify a part of a river as such; failure....
Unfairness of demanding arrears based on retrospective reassessment of water charges when a concluded contract and benefit passed on to consumers.
The court confirmed that arbitration awards can only be set aside on specific grounds under the Arbitration and Conciliation Act, typically requiring a demonstration of public policy conflict or pate....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.