SUPREME COURT OF INDIA
B.R. Gavai, Vikram Nath, JJ.
Developer Group India Pvt. Ltd. – Appellant(s)
Versus
Surinder Singh Marwah and Others – Respondent(s)
Civil Appeal No. 523 of 2023 (Arising out of SLP(C) No. 11779 of 2020)
Decided On : 25-01-2023
Civil Procedure Code, 1908 – Order XXXIX Rules 1 and 2 – Companies Act, 2013 – Sections 337 and 339 – Injunction – Restraint Order – Consortium of six land-owning companies injuncted from transferring, selling or alienating properties of company purchased by them – While passing an order of injunction, Courts are required to be guided by principles of prima facie case, balance of convenience and irreparable injury – Assuming that the respondent Nos. 1 and 2 along with other claimants have a claim of around Rs.31 Crores, entire project in an area of 115 acres cannot be stalled – If Division Bench of High Court found that, there was a prima facie case in favour of respondent Nos. 1 and 2, they could have passed an appropriate order to protect interests of respondents rather than stalling entire project – A blanket order directing maintenance of status quo in respect of all 11 properties admeasuring 115 acres is not justified – If such an order is allowed to continue, it will cause irreparable injury to appellant and respondent No.4 inasmuch as entire development would be stalled – Impugned judgment and order passed by Division Bench of High Court in Company Appeal set aside – Appellant and respondent No.4 directed to file an undertaking before Court that they shall not create any third party rights in respect of properties in question. (Paras 17, 19 and 20)
Facts of the case:
Present appeal arises from judgment and order dated 16th December 2019, passed by Division Bench of High Court of Delhi, thereby allowing a Company Appeal, being Company Appeal No. 10 of 2019, against an order dated 21st February 2019 passed by Single Judge of the High Court of Delhi, in Company Petition No. 482 of 2009, wherein earlier interim orders of Single Judge, dated 11th July 2018 and 16th August 2018, restraining the transfer, selling or alienating of 11 properties purchased by a consortium of six land-owning companies, had been vacated. In allowing appeal, Division Bench of High Court, vide the impugned judgment and order, once again restrained these six companies from alienating the properties.
Findings of Court:
After the final Audit Report is submitted by the Auditor/Chartered Accountants appointed by the learned Single Judge, the learned Single Judge of the High Court would pass final orders with regard to the properties in respect of which the undertaking is to be given by the appellant and the respondent No.4.
Result : Appeal Partly allowed.
JUDGMENT :
B.R. GAVAI, J.
1. Leave granted.
2. The present appeal arises from the judgment and order dated 16th December 2019, passed by the Division Bench of the High Court of Delhi, thereby allowing a Company Appeal, being Company Appeal No. 10 of 2019, against an order dated 21st February 2019 passed by the learned Single Judge of the High Court of Delhi, in Company Petition No. 482 of 2009, wherein earlier interim orders of the learned Single Judge, dated 11th July 2018 and 16th August 2018, restraining the transfer, selling or alienating of 11 properties purchased by a consortium of six land-owning companies, had been vacated. In allowing the appeal, the Division Bench of the High Court, vide the impugned judgment and order, once again restrained these six companies from alienating the aforesaid properties.
3. The facts, shorn of unnecessary details, are as follows:
3.1 It is the allegation of the respondent Nos. 1 and 2 that in the year 2008, on the representation of one Dr. Rajesh Aeren, the Managing Director (MD) of respondent No.3 Company, they decided to invest in a commercial project called Festival City Mall at G.T. Road (National Highway No. 1), Ludhiana, Punjab, being launched by respondent No. 3 Company. In furtherance of the project, a term loan of Rs. 100 Crore was also availed from a consortium of banks. The interest of the respondent Nos. 1 and 2 was limited to 46% of the project, which now stands at 30%. The respondent Nos. 1 and 2 were assured of returns with effect from 1st August 2008, failing which respondent No. 3 and its Directors were to be jointly and severally liable to pay interest @ 2.15% per annum on the amount remaining unpaid to respondent Nos. 1 and 2. Respondent Nos. 1 and 2 were collectively allocated 17 shops in the project.
3.2 The project, however, ran into trouble and the construction was stalled. Neither the possession was offered nor was the assured return or the interest thereon given to respondent Nos. 1 and 2.
3.3 The respondent Nos. 1 and 2, in the year 2009 filed a winding up petition, being Company Petition No. 482 of 2009, before the High Court of Delhi, against respondent No. 3 Company. During the course of the winding up proceedings, the learned Single Judge of the High Court, vide its order dated 19th December 2015, directed respondent No. 3 to deposit a sum of Rs. 1.5 crore with the Registrar of the High Court. However, the said direction was not complied with, and, therefore, vide order dated 18th March 2016 of the learned Single Judge of the High Court, respondent No. 3 Company went into liquidation.
3.4 It is pertinent to note that there were several other investors who too had invested in the project. Various complaints were filed against respondent no. 3 Company and its Directors which resulted in an FIR No. 6 of 2015 being registered on 7th January 2015. Subsequently, the investigation thereon resulted in a charge sheet dated 2nd December 2016, wherein it was alleged that huge sums of money were diverted, defalcated and siphoned off from the corpus of respondent No. 3 Company, which was meant to be utilized for the construction of the project.
3.5 The appellant herein is a 100% FDI company with investors based in Singapore and Japan. In the year 2014, a development and management agreement was entered into between the appellant herein and a consortium of six land-owning companies i.e. Aeren R. Mallz Pvt. Ltd., Aeren R Township Pvt. Ltd., Yashraj Buildcon Pvt. Ltd., Yashvardhan Infrastructure Developers Pvt. Ltd., Aeren R Buildcon Pvt. Ltd. and PMC Entertainment Pvt. Ltd. (now, Fortune R Buildco Developers Pvt. Ltd., i.e., respondent No.4 herein), for exclusive developmental rights over 11 properties extending to 115 acres of land in a real estate project launched by the consortium of six companies for a consideration of Rs. 43 crores.
3.6 Neither the appellant herein nor the cons
SupremeToday
Injunction – Restraint Order – Consortium of six land-owning companies injuncted from transferring, selling or alienating properties of company purchased by them – While passing an order of injunctio....
The court established that insolvency processes for real estate should be project-specific, protecting homebuyers and ensuring fair treatment of creditors.
The court ruled that a plaintiff’s limited interest in property, dictated by the will, cannot be construed as absolute ownership; undue influence invalidates share transfers.
The court established that adherence to statutory processes for property sale was observed, and petitioners failed to pursue available legal remedies, justifying dismissal.
The court modified the interim injunction to require fair market valuations and banking transactions, addressing concerns of potential asset undervaluation and unauthorized cash dealings, ensuring fa....
Fraud claims are not within the jurisdiction of the Debt Recovery Tribunal, allowing civil suits to proceed despite jurisdictional bars under the RDDBFI Act.
The court emphasized that insolvency proceedings should not be exploited to evade liabilities, confirming the necessity to protect homebuyers' interests and investigate corporate fraud.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.