M. R. SHAH, AHSANUDDIN AMANULLAH
Delhi Development Authority – Appellant
Versus
Shiv Raj – Respondent
JUDGMENT
M.R. Shah, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 8081 of 2015 by which the High Court has allowed the said writ petition and has declared that the acquisition with regard to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Delhi Development Authority has preferred the present appeal.
2. From the impugned judgment and order passed by the High Court, it appears that it was the specific case on behalf of the appellant before the High Court and even so stated in the counter filed before the High Court that the possession of the land in question was taken over on 21.04.2006. However, thereafter and relying upon the decision of this Court in the case of Pune Municipal Corporation and Anr. v. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183 , the High Court has allowed the said writ petition and has declared that the acquisition with respect to the land in question is deemed to have lapsed on
Lapse of land acquisition proceeding – Fact that possession of land in question was taken over on 21.04.2006, there shall not be any deemed lapse of acquisition.
Lapse of land acquisition proceeding – Fact that possession of land in question was taken over on 14.07.1987, there shall not be any deemed lapse of acquisition.
Lapse of land acquisition proceeding – In case a person has been tendered compensation as provided under Section 31(1) of 1894 Act, it is not open to him to claim that acquisition has lapsed under Se....
Non-payment or non-deposit of compensation does not lead to a lapse if possession has been taken or if compensation has been paid.
Once possession is taken, there shall be no deemed lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013.
Lapse of land acquisition proceeding – Landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that acquisition proceedings had lapsed under Se....
The interpretation of Section 24(2) requires both possession and compensation to be considered for deeming land acquisition proceedings as lapsed.
Possession of land and payment of compensation are crucial factors in determining whether there is a lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, ....
Non-deposit of compensation in court does not result in the lapse of land acquisition proceedings.
The interpretation and application of Section 24(2) of the Act, 2013 are crucial in determining whether there is a deemed lapse of land acquisition proceedings based on possession, compensation, and ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.