S. RAVINDRA BHAT, DIPANKAR DATTA
S. D. Shinde Tr. Partner – Appellant
Versus
Govt. of Maharashtra – Respondent
JUDGMENT :
S. Ravindra Bhat, J.
1. These appeals challenge a common judgment of the Aurangabad Bench of the Bombay High Court,1[Dated 13.08.2009, in AO 108/2005; the appeal to the Division Bench was rejected on the ground of maintainability.]. The appellant was aggrieved by the judgment of the trial court,2[Joint Civil Judge, Senior Division, Ahmednagar, in R.C.S. No.595/1997.]. The trial court had set aside an award made in the appellant’s favour, 3[Dated 14.12.1997.] awarding substantial amounts towards its claim, in the backdrop of a road construction contract.
2. The first respondent, the Government of Maharashtra Irrigation Department, through Executive Engineer (hereafter EE), issued a tender notice for the work “Construction of Earth Work, structure and lining in Km. No.91 to 110 Kukadi Left Bank Canal”. This tender was accepted, and a work order was issued on 23.07.1983; the estimated cost of the work was Rs. 4,01,77,153/-. The contract between the parties visualized the period for completion of work to be 18 (Eighteen) English calendar months. The due date for completion of work, thus, was 22.01.1985. It was, however, not completed; several extensions were given, on the under
Major (Retd.) Inder Singh Rekhi v Delhi Development Authority
J.C. Budhraja v. Chairman, Orissa Mining Corporation Ltd. and Another
Setting aside arbitral award – Courts, while adjudging whether an arbitration award calls for interference has to be conscious that Arbitrator is sole Judge of facts – Unless an error of law is shown....
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
Arbitration Agreement – Award -Scope of interference by the courts into the award is quite limited. A court considering an application under Section 30 of the Act neither sits in appeal over an award....
The Court's power while exercising jurisdiction under Section 37 of the Act is limited, and it cannot undertake an independent assessment on the merits of the Award.
The court established that the timeline for invoking arbitration under the General Condition of Contract is critical and that the arbitrator's jurisdiction is determined by the latest relevant decisi....
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.