SUPREME COURT OF INDIA
ABHAY S OKA, AUGUSTINE GEORGE MASIH, JJ.
M/s. Modern Builders – Appellant
Versus
State of Madhya Pradesh & Anr. – Respondents
Civil Appeal Nos. 8528-8529 of 2024
Decided on : 30-08-2024
Arbitration and Conciliation Act, 1996 – Section 37 – Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 – Section 7 – Constitution of India – Article 142 – Appeal against arbitral award – Dispute arsing from work contract – Before taking recourse to Arbitration Act, appellant had taken recourse to Section 7 of 1983 Act – Order of Arbitration Tribunal, holding that Arbitration Act will apply, led appellant to file petition under Section 11(6) of Arbitration Act which was not objected to on the grounds of applicability of 1983 Act – Objection of State Government was confined to merits of claim – Award is only in sum of Rs. 6,52,235/- with interest – Award was made on 25th April 2014 – It will be unjust to set aside award only on the ground of failure of appellant to take recourse to 1983 Act – Appellant had taken recourse to 1983 Act before seeking appointment of Arbitrator – This is a fit case to exercise jurisdiction under Article 142 of Constitution of India to ensure that complete justice is done – By setting aside impugned Judgment, appeal under Section 37 of Arbitration Act will have to be restored with request to High Court to decide the same on merits – All issues on merits of restored appeal under Section 37 of Arbitration Act are kept open – However, award should not be set aside on the grounds of applicability of 1983 Act. (Paras 7 and 8)
Facts of the case:
Respondents, aggrieved by arbitral award, preferred a petition under Section 34 of Arbitration Act before District Judge, Jabalpur. District Judge dismissed the petition. Respondents filed appeal under Section 37 of Arbitration Act before High Court for challenging order of District Court. By impugned Judgment, High Court proceeded to set aside the award only on the ground that provisions of 1983 Act were applicable.
Findings of Court:
If appellant has withdrawn amount paid as per award, same shall be deposited by appellant with High Court within two months from today. Amount shall be invested by High Court in a fixed deposit with any nationalised bank till disposal of restored appeal. High Court, while deciding appeal, shall pass appropriate directions regarding withdrawal of amount with interest accrued thereon.
Result : Appeals allowed.
JUDGMENT :
ABHAY S. OKA, J.
FACTUAL ASPECTS
1. The appellant was appointed as a contractor to construct a minor bridge. The contract was granted by the first respondent–State of Madhya Pradesh. The second respondent, Executive Engineer, National Highway Division Sagar, Madhya Pradesh, rescinded the contract by the letter dated 9th November 2001. Clause 29 in the work order incorporated an arbitration clause. The appellant requested for constitution of an Arbitral Board. The said request was rejected. Even the subsequent representation was rejected. Therefore, the appellant applied for a reference to the Madhya Pradesh Arbitration Tribunal, Bhopal (for short, ‘the Arbitration Tribunal’) in accordance with Section 7 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (for short, ‘the 1983 Act’). By the order dated 19th April 2010, the Arbitration Tribunal concluded that as there was an arbitration clause in the contract, the provisions of the Arbitration and Conciliation Act, 1996 (for short, ‘the Arbitration Act’) would apply. The Tribunal held that only when there is no arbitration clause, the provisions of the 1983 Act would apply. In view of this order, the appellant filed a petition under Section 11(6) of the Arbitration Act before the High Court of Madhya Pradesh at Jabalpur. The petition was allowed, and a retired District Judge was appointed as the Arbitrator. An award was made on 25th April 2014 by the learned Arbitrator.
2. The respondents, aggrieved by the said award, preferred a petition under Section 34 of the Arbitration Act before the District Judge, Jabalpur. The learned District Judge dismissed the said petition. The respondents filed an appeal under Section 37 of the Arbitration Act before the High Court for challenging the order of the District Court. By the impugned judgment, the High Court proceeded to set aside the award only on the ground that as held by this Court in the case of Madhya Pradesh Rural Road Development Authority & Anr. v. L. G. Chaudhary Engineers and Contractors, (2018) 10 SCC 826, the provisions of the 1983 Act were applicable.
SUBMISSIONS
3. The learned counsel appearing for the appellant invited our attention to the fact that the decision in the case of Madhya Pradesh Rural Road Development Authority was rendered nearly four years after the date of the award. However, in paragraph 17 of the said decision, this Court observed that if an award is already made by the Arbitrator and if the objection to the jurisdiction of the Arbitrator was not raised at an appropriate stage, the award may not be annulled only on that ground. The learned counsel submitted that the respondents did not challenge the order passed by the High Court under Section 11(6) of the Arbitration Act. The objection regarding the jurisdiction of the arbitration was raised only in the written submissions. He would, therefore, submit that the award could not have been set aside based on the decision of this Court.
4. The learned counsel appearing for the respondents submitted that, as seen from the award, a contention was raised in the written statement filed before the Arbitrator that the appellant should have taken recourse to Section 7 of the 1983 Act. Therefore, the dispute was raised at the appropriate stage, and hence, paragraph 17 of the decision in the case of Madhya Pradesh Rural Road Development Authority will have no application.
CONSIDERATION OF SUBMISSIONS
5. A few factual aspects will have to be noted. After the contract granted to the appellant was rescinded, the appellant invoked Section 7 of the 1983 Act by approaching the Arbitration Tribunal. By the order dated 19th April 2010, the Arbitration Tribunal held that in view of the arbitration clause in the contract, the 1983 Act will have no application and the appellant will have to take recourse to the Arbitration Act. In view of this order, the appellant invoked the jurisdiction of the High Court under Section 11(6) of the Arbitration Act by filing a petitio
Madhya Pradesh Rural Road Development Authority & Anr. v. L. G. Chaudhary Engineers and Contractors
Appeal against arbitral award – It will be unjust to set aside award only on the ground of failure of appellant to take recourse to another Act.
Advocates appeared :For the Appellant : Kunal Thakre For the Respondent : Siddharth Sharma
The main legal point established in the judgment is the jurisdiction of the arbitrator under the Act, 1996, and the applicability of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 to the di....
The High Court affirmed the exclusive jurisdiction of the Madhya Pradesh Arbitration Tribunal over disputes arising from a works contract, asserting arbitration clauses cannot override statutory mand....
Cause of action estoppel arises where in two different proceedings identical issues are raised, in which event, latter proceedings between same parties shall be dealt with similarly as was done in pr....
Arbitration applications must adhere to contract stipulations for lawful proceedings; premature filings are not maintainable.
Jurisdictional objections to arbitration awards must be raised during proceedings, not at execution; failure to do so leads to unenforceable awards.
Section 8 of the Arbitration and Conciliation Act, 1996 is mandatory and requires the Court to refer parties to arbitration if the agreement contains an arbitration clause. Finality of the order of t....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.