DIPANKAR DATTA, AUGUSTINE GEORGE MASIH
Rajnesh Sharma – Appellant
Versus
Business Park Town Planners Ltd. – Respondent
Key Points: - (!) The court emphasizes that actual loss must be proved before compensation is granted, and interest can be awarded beyond the contract rate when warranted by facts. - (!) There is no universal rule that builder-charged default interest cannot be awarded to the buyer; reasonable interest is permitted. - (!) The Supreme Court modified NCDRC’s 9% p.a. interest to 12% p.a. in Vidya v. Parsvnath, indicating that rate depends on case specifics. - (!) The Court held that the respondent’s conduct—long delay and high default interest—may justify not awarding nominal liability and adjusting interest to reflect fairness. - (!) , (!) - (!) Clause 7 and its interpretation show that layout changes may occur, but the seller’s obligations and possible refunds are impacted by such changes. - (!) - (!) The appellant argued for higher or parity-based interest when compared to the builder’s rate and other cases; the Court discusses parity and reasonableness. - (!) The Court’s decision to modify interest from 9% to a higher rate (12% in earlier case, 18% in other contexts) demonstrates variability based on conduct and circumstances. - (!) - (!) The Court analyzes whether changes in layout and location bound the purchaser and impact compensation/refund. - (!) - (!) Authority and law on awarding interest, including references to IREO Grace and Vidya decisions, guiding reasonableness of rates. - (!) The decision to modify the rate of interest to reflect fairness, while upholding refund of principal.
JUDGMENT :
Dipankar Datta, J.
THE APPEAL
1. This appeal assails an order dated 13th January, 2023, passed by the National Consumer Disputes Redressal Commission, New Delhi1[NCDRC] disposing of a consumer complaint lodged before it by the appellant.
FACTS
2. Facts in brief, necessary for the disposal of the present appeal, are as follows:
b. On 11th December, 2007, a plot buyer agreement3[AGREEMENT] was executed between the parties.
c. As per clause 22 of the AGREEMENT, the possession of the plot was to be handed over within 24 months of sanction of service plans of the entire colony. Furthermore, clause 12 provided that time is of the essence, and in case of default by the buyer, late payment charges at 18% p.a. on the due amount, compounded at the time of every succeeding instalment or three months, whichever is earlier, would be levied by the respondent.
d. By April,
Ghaziabad Development Authority v. Balbir Singh
Fortune Infrastructure v. Trevor D’Lima
Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan
Kolkata West International City Pvt. Ltd. v. Devasis Rudra
(1) Plot Buyer Agreement – Objective of granting compensation cannot be altered such that it amounts to a windfall gain to other party – Before compensation can be granted by NCDRC, actual loss must ....
The court found no basis for modifying the interest rate and additional costs due to insufficient grounds and lack of contractual entitlement for increased interest on delayed possession.
Housing – A home buyer cannot be compelled to take possession of flat after a long time – High rate of interest cannot be awarded on refund amount.
Flat Buyer Agreement – Delay in delivery of possession – Rate of interest on amount of refund cannot be less than that as provided in agreement.
Builder is bound to complete construction and hand over possession of flat to buyer within stipulated time. Burden would lie on developer to explain steps taken to comply with contractual stipulation....
Consumer service agreements may not curtail statutory jurisdiction of consumer forums, which can award compensation beyond stipulated contractual terms if deemed unfair.
(1) Justified Withholding of Payments – An allottee is not necessarily “at fault” for stopping installments if it is evident that the builder is nowhere near completing the project by the committed d....
Flat Buyers Agreement – Rate of interest must be same for both parties.
Written statement – Even when defendant’s/opposite party’s right to file a written statement is forfeited that by itself will not make it obligatory on part of NCDRC to pass an order in favour of a c....
Flat Buyer’s Agreement – Denial of timely possession despite substantial payment – Payment of interest on refund of principal amount is necessary.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.