SUPREME COURT OF INDIA
Dipankar Datta, Augustine George Masih, JJ.
Rajnesh Sharma – Appellant
Versus
M/S. Business Park Town Planners Ltd. – Respondent
Civil Appeal No. 3988 of 2023
Decided On : 24-09-2025
Consumer Protection Act, 1986 – Section 14 – Real estate – Plot Buyer Agreement – Offer to allot alternate plot – Before compensation can be granted by NCDRC, actual loss must be proved to have been suffered by consumer – Proof of actual loss would require evidence to be tendered, for, it is a guiding lamp for grant of compensation – There is no principle of law that interest in default charged by builder can never be granted to buyer – Amount of interest should be reasonable – What is reasonable varies from case to case – Same is to be granted considering facts and circumstances of each case – Keeping in mind overall conduct of respondent and delay caused by it in offering plot, this is an appropriate case where refund of principal amount with 9% interest as awarded by NCDRC, will not serve ends of justice – Respondent cannot be permitted to escape with nominal liability for its default, while it charged 18% interest on default committed by appellant – Although, rate of interest charged by builder cannot be granted to buyer as a rule of thumb, however, in present case, equity and fairness demands that respondent be put to same rigours for charging 18% interest and face consequences similar to those imposed on appellant for default committed by him – Rate of interest increased from 9% to 18% per annum. (Paras 11, 12, 18, 19, 20 and 21)
Facts of the case:
Present appeal assails an order dated 13th January, 2023, passed by National Consumer Disputes Redressal Commission, New Delhi, disposing of a consumer complaint lodged before it by appellant.
Findings of Court:
We substitute rate of interest awarded by the NCDRC and increase it from 9% to 18% per annum, while keeping other terms intact. Respondent shall refund requisite amount within a period of two months from date.
Result : Appeal partly allowed.
Key Points: - (!) The court emphasizes that actual loss must be proved before compensation is granted, and interest can be awarded beyond the contract rate when warranted by facts. - (!) There is no universal rule that builder-charged default interest cannot be awarded to the buyer; reasonable interest is permitted. - (!) The Supreme Court modified NCDRC’s 9% p.a. interest to 12% p.a. in Vidya v. Parsvnath, indicating that rate depends on case specifics. - (!) The Court held that the respondent’s conduct—long delay and high default interest—may justify not awarding nominal liability and adjusting interest to reflect fairness. - (!) , (!) - (!) Clause 7 and its interpretation show that layout changes may occur, but the seller’s obligations and possible refunds are impacted by such changes. - (!) - (!) The appellant argued for higher or parity-based interest when compared to the builder’s rate and other cases; the Court discusses parity and reasonableness. - (!) The Court’s decision to modify interest from 9% to a higher rate (12% in earlier case, 18% in other contexts) demonstrates variability based on conduct and circumstances. - (!) - (!) The Court analyzes whether changes in layout and location bound the purchaser and impact compensation/refund. - (!) - (!) Authority and law on awarding interest, including references to IREO Grace and Vidya decisions, guiding reasonableness of rates. - (!) The decision to modify the rate of interest to reflect fairness, while upholding refund of principal.
JUDGMENT :
Dipankar Datta, J.
THE APPEAL
1. This appeal assails an order dated 13th January, 2023, passed by the National Consumer Disputes Redressal Commission, New Delhi1[NCDRC] disposing of a consumer complaint lodged before it by the appellant.
FACTS
2. Facts in brief, necessary for the disposal of the present appeal, are as follows:
b. On 11th December, 2007, a plot buyer agreement3[AGREEMENT] was executed between the parties.
c. As per clause 22 of the AGREEMENT, the possession of the plot was to be handed over within 24 months of sanction of service plans of the entire colony. Furthermore, clause 12 provided that time is of the essence, and in case of default by the buyer, late payment charges at 18% p.a. on the due amount, compounded at the time of every succeeding instalment or three months, whichever is earlier, would be levied by the respondent.
d. By April, 2011, the appellant had paid a sum of Rs. 28,79,065/-. On 13th April, 2011, more than 5 (five) years after the first payment, the respondent informed the appellant that due to changes in the layout plan, it had decided to allot an alternative plot to the appellant. Since the new plot was 7 sq. yards larger than the original plot, the respondent further demanded a sum of Rs. 2,30,784/- as an additional amount. Accordingly, an addendum to the AGREEMENT was executed between the parties on 13th April, 2011. Clause 7 of the AGREEMENT (discussed in the latter part of the judgment) provided for allotment of an alternative plot if a change in layout plan was required by any statutory authority.
e. The appellant on 11th March, 2015, paid a sum of Rs. 83,377.67, out of which Rs. 83,300.76 was towards interest @ 18% p.a. charged by the respondent for the appellant’s default in making the payments.
f. As per the statement of accounts dated 23rd March, 2015 prepared by the respondent, the appellant had paid a sum total of Rs. 43,13,312.67/-.
g. Aggrieved by the respondent’s inaction in allotting the plot, the appellant terminated the AGREEMENT with the respondent vide letter dated 27th March, 2017.
h. Thereafter, on 27th March, 2017, the appellant issued a legal notice informing the respondent about such termination and seeking a refund of Rs. 43,13,212/- along with 24% interest p.a. and a sum of Rs. 72,30,000/- on account of loss of appreciation of property.
i. Ultimately, in April 2018, the appellant lodged the consumer complaint4[Consumer Case No. 885 of 2018] before the NCDRC referred to in the opening paragraph.
j. After the lodging of the complaint, the respondent offered the possession of the plot on 8th May, 2018, subject to payment of a further amount of Rs. 7,60,900.33/-.
k. Vide the impugned order, the consumer complaint was disposed of with directions to the respondent to refund the entire principal amount of Rs. 43,13,212/- along with simple interest @ 9% p.a. from the date of each payment till the date of refund. Additionally, Rs. 25,000/- was awarded towards litigation costs to the appellant.
l. The said order is under challenge before this Court in this appeal at the instance of the partly successful complainant.
IMPUGNED ORDER :
3. During the course of hearing before the NCDRC, learned counsel for the respondent offered to repay the principal amount with 9% simple interest per annum. This weighed with the NCDRC, and it ordered accordingly without going into the merits of the case. It is imperative to mention that the impugned order nowhere records that the appellant accepted such an offer. Rather, the NCDRC disposed of the matter merely based on the offer made by the counsel for the respondent.
SUBMISSIONS ON BEHALF OF THE APPELLANT
4. It was submitted by M
Ghaziabad Development Authority v. Balbir Singh
Fortune Infrastructure v. Trevor D’Lima
Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan
Kolkata West International City Pvt. Ltd. v. Devasis Rudra
(1) Plot Buyer Agreement – Objective of granting compensation cannot be altered such that it amounts to a windfall gain to other party – Before compensation can be granted by NCDRC, actual loss must ....
The court found no basis for modifying the interest rate and additional costs due to insufficient grounds and lack of contractual entitlement for increased interest on delayed possession.
Housing – A home buyer cannot be compelled to take possession of flat after a long time – High rate of interest cannot be awarded on refund amount.
Flat Buyer Agreement – Delay in delivery of possession – Rate of interest on amount of refund cannot be less than that as provided in agreement.
Builder is bound to complete construction and hand over possession of flat to buyer within stipulated time. Burden would lie on developer to explain steps taken to comply with contractual stipulation....
Consumer service agreements may not curtail statutory jurisdiction of consumer forums, which can award compensation beyond stipulated contractual terms if deemed unfair.
(1) Justified Withholding of Payments – An allottee is not necessarily “at fault” for stopping installments if it is evident that the builder is nowhere near completing the project by the committed d....
Flat Buyers Agreement – Rate of interest must be same for both parties.
Written statement – Even when defendant’s/opposite party’s right to file a written statement is forfeited that by itself will not make it obligatory on part of NCDRC to pass an order in favour of a c....
Flat Buyer’s Agreement – Denial of timely possession despite substantial payment – Payment of interest on refund of principal amount is necessary.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.