SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(SC) 337

SUPREME COURT OF INDIA
PAMIDIGHANTAM SRI NARASIMHA, ALOK ARADHE, JJ.
M/s A.K.G. Construction And Developers Pvt. Ltd – Appellants
Versus
State of Jharkhand & Ors. – Respondents
Civil Appeal No(s). 4152 of 2026 Arising out of SLP (C) No. 23858 of 2025 With Civil Appeal No(s). 4153 of 2026 Arising out of SLP (C) No. 22669 of 2025
Decided On : 02-04-2026

Advocates appeared:
For the Appellant(s) : Mr. R. Ayyam Perumal, AOR
For the Respondent(s): Mr. Kumar Anurag Singh, Adv. Mr. Jayant Mohan, AOR Mr. Zain A. Khan, Adv. Ms. Adya Shree Dutta, Adv. Ms. Dorjee Ongmu Lachungpa, Adv. Mr. Priyanshu Teotia, Adv. Mr. Dev Aaryan, Adv. Mr. Mohd. Abran Khan, Adv.

A blacklisting order requires a specific show-cause notice to uphold principles of natural justice; its absence renders the blacklisting illegal and arbitrary.

Headnote:(A) Judicial Review - Standards of Legality, Rationality, and Proportionality applicable to administrative actions regarding contracts, particularly in termination and blacklisting contexts - Blacklisting without proper notice is not justified (paras 2, 3, 12, 22).

(B) Termination - Upheld due to clear evidence of negligence in construction, as established in multi-level enquiries and reports from institutions (paras 3, 25).

(C) Blacklisting - Reversed due to failure to adhere to principles of natural justice, including lack of a proper show-cause notice (paras 4, 19, 24).

Facts of the case:
The appellant, a contractor, faced termination of contract and blacklisting arising from the collapse of an Elevated Service Reservoir, attributed to alleged negligence, despite offering to reconstruct at its own expense.

Findings of Court:
The termination was substantiated while the blacklisting order was quashed due to procedural infirmities and lack of proper notice.

Issues: Whether the blacklisting was legally justified given the lack of a proper show-cause notice and the nature of the consequences of blacklisting.

Ratio Decidendi: The court reaffirmed the necessity of issuing a specific show-cause notice before blacklisting due to its severe implications, setting aside the blacklisting based on this principle.

Result: The appeals against termination dismissed while the order of blacklisting set aside.

Table of Content
1. court emphasizes standards for administrative actions. (Para 2 , 3)
2. court affirms termination order, sets aside blacklisting. (Para 4 , 5)
3. factual background of the construction contract and collapse. (Para 6 , 7 , 8)
4. arguments regarding legality and procedure of termination and blacklisting. (Para 10 , 11)
5. independence of termination and blacklisting processes. (Para 17 , 18)
6. importance of notice and principles of natural justice in blacklisting. (Para 19 , 20 , 21)
7. requirement for proper reasoning and due process in blacklisting. (Para 22 , 23)
8. final conclusions on legality of termination and blacklisting. (Para 24 , 25)

JUDGMENT :

1. Leave granted.

2. While exercising judicial review over administrative actions of the State and its instrumentalities in relation to contracts provisioning clauses and rules relating to termination and/or blacklisting, Courts must apply distinct standards of legality, rationality and proportionately. Such an approach is compelling as conditions for imposing such measures, as also the consequences of such actions, have differing gravity.

3. Upon careful consideration of the impugned State action, which terminates the contract and blacklists the appellant without meaningful distinction, we hold that the termination order is substantiated and justified. However, the blacklisting order suffers from patent infirmities: it evinces no application of mind, disregards the mandatory precept of audi alteram partem, and fails to precede with a show-cause notice requiring the contractor to demonstrate why such drastic action should not be taken. Blacklisting, being stigmatic and exclusionary in nature, cannot be imposed mechanistically but must comport with principles of natural justice and reasonableness.

4. For the reasons detailed hereafter, we uphold the order of termination and the impugned judgement and review order affirming the same, but set aside the decision to blacklist the appellant.

5. Having upheld the order of termination, we were of the opinion that the assumed logical consequence of blacklisting is neither supported by application of mind nor followed by a clear notice proposing blacklisting. For the reasons to follow, we set aside the order of blacklisting. However, in the facts and circumstances of the case, due to passage of time, we have suitably moulded the relief and directed that the order of blacklisting shall not continue for five years as directed by the Department but will cease to operate from the date of our judgment.

Facts

6. The appellant, a registered contractor with the Water and Sanitation Department was contracted for construction of an Elevated Service Reservoir (ESR) by issuance of a Letter of Acceptance (LOA) on 06.03.2023. During the subsistence of the contract, on 01.06.2024, the top dome of the reservoir collapsed. Though it was justified as being a result of an unexpected cyclone, the appellant offered to reconstruct it at own expense. However, the Department issued a show cause notice dated 04.06.2024, seeking explanation as to why action should not be taken for the negligence and bad quality of work. The contents of the show cause notice are as follows -

“(PURPOTED SHOW CAUSE)

GOVERNMENT OF JHARKHAND

DRINKING WATER & SANITATION DEPARTMENT

Letter No. 4/A.V.-01-1019/2024- 1311

From,

Navneet Kumar

Under Secretary to the Government.

To,

M/s. A.K.G. Construction & Developers Pvt. Ltd. Ranchi.

Ranchi, Date- 4/6/24

Subject: Regarding submitting clarification.

Context: Letter No. 727 of Executive Engineer, Drinking Water and Sanitation Division, Jhumritilaiya, dated 01.06.2024.

Sir,

As per the directions, the department received information about collapse of the under-construction water tower in Neemadhi village under Koderma-Demchonch Jaynagar Mega Rural Water Supply Scheme through the relevant letter on the above subject.

The collaps

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top