SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(SC) 544

SUPREME COURT OF INDIA
DIPANKAR DATTA, SATISH CHANDRA SHARMA, JJ.
Petroleum And Natural Gas Regulatory Board – Appellant
Versus
M/S Jay Madhok Energy Pvt. Ltd. Led Consortium – Respondent
Civil Appeal Nos. 1880-1881 of 2024 With Civil Appeal Nos. 3649-3650 of 2024
Decided On : 12-05-2026

Advocates appeared:
For the Appellant(s) : Mrs. Aishwarya Bhati, A.S.G. Mr. Utkarsh Sharma, AOR Mr. Suyash Gaur, Adv. Ms. Sanskriti Bharadwaj, Adv.
For the Respondent(s): Mr. Parag P. Tripathi, Sr. Adv. Mr. Mahesh Agarwal, Adv. Mr. Saurav Agarwal, Adv. Mr. Arshit Anand, Adv. Mr. Shashwat Singh, Adv. Mr. Anshuman Choudhary, Adv. Ms. Aparajito Sen, Adv. Mr. E. C. Agrawala, AOR

Strict adherence to prescribed statutory procedure is mandatory for regulatory cancellation actions; non-compliance invalidates orders even if public interest is involved.

Headnote:(A) Petroleum and Natural Gas Regulatory Board Act, 2006 - Section 37 - City Gas Distribution Network Regulations, 2008 - Regulations 11(5) and 16 - Cancellation of authorization for laying pipelines - Forfeiture of performance bank guarantees and imposition of penalty - Procedure for consequences of default - Specific procedure under Regulation 16 must be followed strictly - Public interest considerations do not justify non-compliance with mandated steps - Any departure from prescribed manner invalidates the action. (Paras 9, 10 and 11)

(B) Appeal - Second appeal - Substantial question of law - Scope of interference limited to perversity, illegality or such vice - Mere possibility of another view insufficient for interference.

Facts of the case:
Regulatory authorization for laying gas pipelines was cancelled after inquiry into omissions, commissions, non-performance and submission of incorrect documents, along with forfeiture of guarantees and penalty. Tribunal had earlier set aside prior orders for procedural lapses and directed fresh orders in accordance with law. Regulator again failed to adhere to procedure.

Findings of Court:
Procedure prescribed by regulations was not followed despite opportunities and prior directions. Performance shortcomings affected public interest over a decade, with blame shared by both parties. However, statutory mandate takes precedence over expediency.

Issues: Whether regulator must strictly specify reasonable time for corrective action and follow procedural requirements before imposing penalties and cancellation despite admitted breaches; whether non-compliance precludes action even when detrimental to public interest.

Ratio Decidendi: When statute requires action in particular manner by authority, strict adherence is essential; departure is indefensible and invalidates the resulting order. Result : Appeals dismissed.

Table of Content
1. procedural history of appeals under section 37 (Para 1 , 2 , 3)
2. authorization grant, cancellation and penalty facts (Para 4)
3. appeal requires substantial question of law (Para 5)
4. pngrb contentions on breach and procedure (Para 6 , 7)
5. authority must strictly follow prescribed statutory procedure (Para 8 , 10)
6. prior aptel direction to follow regulation 16 (Para 9)
7. no substantial question of law, appeals dismissed (Para 11 , 12 , 13)

ORDER

1. Civil Appeal Nos. 1880 and 3649 of 2024 under Section 37 of the PETROLEUM AND NATURAL GAS REGULATORY BOARD ACT , 2006 [2006 Act] have been carried by the Petroleum and Natural Gas Regulatory Board [PNGRB] from the common judgment and order dated 28th September, 2022 passed by the Appellate Tribunal for Electricity [APTEL], New Delhi, allowing the appeals [Appeal Nos.161 and 162 of 2022] of the respondent.

2. Civil Appeal Nos. and 1881 and 3650/2024 too are preferred by the PNGRB under Section 37 of the 2006 Act. The common judgment and order dated 13th September, 2023 of the APTEL rejecting applications for review [DFR Nos. 28 and 29/2023] of the PNGRB is under challenge therein.

3. The appeals before the APTEL, at the instance of the respondent, were directed against an order dated 3rd December, 2020 passed by the PNGRB. For the diverse reasons assigned in the common impugned order dated 28th September, 2022, the orders dated 3rd December, 2020 were set aside and the appeals preferred by the respondent allowed.

4. Respondent was granted authorization in respect of Geographical Areas of Ludhiana and Kutch (East) for laying gas pipelines. Such authorisation was cancelled by the PNGRB under Section 23 of the 2006 Act together with forfeiture of Performance Bank Guarantees and imposition of penalty of an amount equivalent to 50% of the Performance Bank Guarantees on account of certain omissions and commissions, as per the conclusions reached during an inquiry.

5. In terms of Section 37 of the 2006 Act, an appeal against an order of the APTEL shall lie to this Court on one or more of the grounds specified in Section 100 , Code of CIVIL PROCEDURE CODE [CPC]. Having regard to the fact that the main appeals are in essence second appeals of the nature contemplated by the CPC, the same can be entertained only upon involvement of a substantial question of law.

6. According to the PNGRB [page B of the paper book], “the question of law of general importance which arises for consideration in the present case is that when there is an admitted case of breach of Regulations by the authorized entity, coupled with concealment of information and submission of doctored documents to the statutory regulator, and the non-performance on the part of the entity is writ large on the face of the record, despite several opportunities to take corrective action having been given to the authorized entity by the statutory regulator, even then the statutory regulator is required to strictly specify and indicate the reasonable time given to the authorized entity to take corrective action and fulfil its obligation and in case of failure to do so, the statutory regulator is precluded from taking any action against the authorized entity, even though the actions of the authorized entity are clearly detrimental to public interest”.

7. Though, the APTEL assigned diverse reasons for upholding the challenge of the respondent to the impugned order dated 3rd December, 2020, not all the reasons assigned were questioned before us in course of hearing on behalf of the PNGRB. The only point argued is in relation to default committed by the respondent to abide by the terms and conditions of and the action initiated authorizations: due show cause notice dated 26th March, 2019 was issued under Section 23 of the 2006 Act as well as under Regulation 16 of the PNGRB (Authorizing Entities to Lay, Build, Operate or Expand City or Local Natural Gas Distribution Network) Regulations, 2008 [2008 Regulations] “on why th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top