IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
DHIRAJ SINGH THAKUR, CJ., R. RAGHUNANDAN RAO, J.
Vanacharla Venkata Krishna Rao, S/o. Satyanarayana Murthy & Others - Appellants
Versus
Union of India, Rep. by its Secretary to Government of India, Ministry of Road Transport and Highways and Others - Respondents
W.A. Nos.1001 of 2023 & 135 of 2024
Decided On : 22-08-2024
Acquisition - Land Acquisition - National Highways Act, 1956 - Sections 3A, 3D, 3G - The court interpreted the provisions regarding land acquisition, emphasizing that once land vests with the government, it cannot be reduced or withdrawn without following due process.
Fact of the Case:
The case involved a challenge to land acquisition notifications under the National Highways Act, where the extent of land intended for acquisition was reduced after initial notifications, leading to disputes over compensation and the legality of the acquisition process.
Finding of the Court:
The court found that the learned single Judge's direction to issue a fresh notification under Section 3G was unsustainable, as the land had already vested with the government under Section 3D, and compensation should be based on that notification.
Issues: The main issues were whether the reduction of land acquisition was lawful and whether compensation should be determined based on the initial or the revised notifications.
Ratio Decidendi: The court held that once land is vested with the government under Section 3D, it cannot be reduced or withdrawn without following the proper legal process, and compensation must be determined based on the land actually acquired.
Result: The court modified the learned single Judge's order to direct compensation based on Section 3D of the Act.
JUDGMENT :
(Dhiraj Singh Thakur, CJ.) :
The present writ appeals have been preferred against the judgment and order, dated 21.09.2023, passed in W.P. No.34565 of 2022.
Briefly stated, the matter facts are as under:
2. A notification, dated 18.04.2018, came to be issued by the Ministry of Road, Transport and Highways in purported exercise of powers conferred under sub-section 1 of Section 3A of the National Highways Act, 1956 (hereinafter referred to as “the Act”) declaring its intention to acquire the parcels of land mentioned in the said notification for public purpose inter alia for construction of flyovers, vehicular underpasses, Four Laning/Six Laning etc., of National Highway No.16/216A in Gundugolanu – Rajamahendravaram Section in the West Godavari District of the State of Andhra Pradesh. The total land that was identified and was intended to be used for the aforesaid public purpose was reflected as 3.5954 Hectares.
3. Since objections were called by virtue of notification, dated 18.04.2018, objections filed by the petitioners were considered but rejected. Thereafter, notification under Section 3D of the Act came to be issued on 07.12.2018 by the Central Government after having considered the report of the competent authority holding that the lands specified in the schedule be acquired for the purpose as was notified in terms of notification, dated 18.04.2018.
What is important, however, is that as against 3.5954 Hectares earlier envisaged to be utilized for the public purpose in terms of the notification issued under 3A of the Act, land to an extent of only 2.1395 Hectares was sought to be utilized for the said public purpose in terms of the notification issued under Section 3D of the Act.
4. Initially, a notification, dated 18.01.2019, was issued under Section 3G(3) of the Act. However, subsequently, another notification, dated 11.10.2022, was issued under Section 3G(3) of the Act pursuant to the communication received from the Project Director, Rajamahendravaram, on account of the reduced requirement of land in view of the reduction of the width of the National Highway from 60 meters to 46 meters.
5. Section 3G of the Act envisages payment of an amount determined by the order of a competent authority where any land is acquired under the Act. If the amount so determined by the competent authority is not acceptable to either of the parties, the said Section envisages determination of that issue by an Arbitrator to be appointed by the Central Government to which proceedings the Arbitration and Conciliation Act, 1996, would be applicable.
6. Being aggrieved of the acquisition proceedings under the Act, the petitioners preferred W.P. No.34565 of 2022 before the learned single Judge, which was primarily aimed at challenging notification, dated 11.10.2022, issued under Section 3G of the Act, urging that the same was unsustainable, as it notified parcels of land different from the land that were notified in its earlier notification, dated 18.01.2019, issued under Section 3G of the Act.
It was also the case of the petitioners before the learned single Judge that the reduction in the extent of land sought to be acquired from the petitioners would not in any way benefit them, as the remaining extents after reduction would not serve any purpose and would become useless.
7. Learned single Judge, vide judgment and order impugned, dated 21.09.2023, partly allowed the writ petition and directed the authorities to take necessary action for issuing fresh notification under Section 3G of the Act in consonance with notification issued under Section 3A of the Act and to determine the compensation payable to the petitioners in accordance with law. This direction had its basis in the finding recorded by the learned single Judge that there was no specific provision under the Act, which would allow the Government/authorities to withdraw or reduce the extent of land sought to be acquired especially after the said land vested with the Central Gov
The court established that land once vested with the government under the National Highways Act cannot be reduced without following due legal process.
The court established that land once vested in the government under the National Highways Act cannot be reduced without following the statutory process.
The court upheld the validity of land acquisition proceedings under the National Highways Act, confirming the necessity of adherence to statutory requirements while emphasizing the priority of public....
The procedure under Sections 3G and 3E of the National Highways Act was duly followed in passing the awards.
Public interest in land acquisition for national highway construction can outweigh individual objections related to procedural inadequacies when substantial work has progressed.
Land plans and other details of the land covered under the notification are available and can be inspected by the interested persons at the aforesaid office of the competent authority” there is suffi....
The main legal point established in the judgment is that land acquisition proceedings can be challenged after the passing of the award and receipt of compensation in exceptional cases falling within ....
Notifications must meet the statutory requirements and furnish all the details in the notification issued at the first instance. Vague notifications may not be quashed, and the court may direct the r....
The scope of judicial review in acquisition matters is very limited and the courts can nullify the acquisition of land and in rarest of rare case, the particular project, if it is found to be ex-faci....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.