IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
Gannamaneni Ramakrishna Prasad, J.
Jasti Venkateswara Rao, S/O. Anjaneyulu – Petitioner
Versus
The Government of Andhra Pradesh Rep By Its, Principal Secretary, Finance And Planning Department And Ors.- Respondents
Writ Petition No: 24237/2010
Decided On : 30-07-2024
Cess - Labour Cess - Building and Other Construction Workers Cess Act, 1996 - The court interpreted the provisions of the Act, emphasizing that deductions for Labour Cess can only occur if the amount is included in the contract estimates, influencing the decision to allow the writ petition.
Fact of the Case:
The writ petitioner, a registered contractor, challenged the government's action of not including 1% Labour Cess in payments for ongoing works, arguing that the estimates did not provide for such deductions and that the government acted arbitrarily.
Finding of the Court:
The court found that the government's unilateral decision to deduct Labour Cess without including it in the estimates was arbitrary and violated the principles established in a previous judgment, which required that deductions could only occur if the cess was included in the estimates.
Issues: Whether the government could deduct Labour Cess from payments made to the contractor without including it in the contract estimates.
Ratio Decidendi: The court held that deductions for Labour Cess are only permissible if the corresponding amount is included in the contract estimates, reinforcing the legal obligation under the Building and Other Construction Workers Cess Act, 1996.
Result: The writ petition is allowed, directing the inclusion of 1% Labour Cess in estimates and prohibiting deductions without such inclusion.
ORDER :
Gannamaneni Ramakrishna Prasad, J.
Heard Ms. Mahathi Saaveri, learned Counsel for the Writ Petitioner and Sri K. Arjun Chowdary, learned Assistant Government Pleader for Finance and Planning.
2. Prayer made in the Writ Petition is as under:-
3. The Writ Petitioner is a registered contractor carrying out Infrastructure Projects and construction works in various Government Departments. The Writ Petitioner is presently doing works which are under the control of the Government of Andhra Pradesh (Respondent No.3) with regard to improvements to Elwinpeta – Ramannaguda Road to Eguvu Tadikonda from k.3/0 to 6/180 in Vizianagaram District. The Government of Andhra Pradesh has issued Memo dated 28.02.2008 bearing U.O.Note No.4763/PFS. F8 (A1)08-4 (Ex.P.3), (Impugned Memo). Vide the Impugned Memo dated 28.02.2008, the following demands are made :
ii. In respect of agreements which provide that the Contractor shall pay Cess at the rate not exceeding 2% of the cost of Construction under the Building and other Construction Workers Cess Act, 1996, the Contractor has no option but to pay Cess by way of deduction at source effect from 26.06.2007.
4. It is the contention of the Writ Petitioner herein that in respect of present contract, there is no provision made-out in the estimates of the tender notice and the agreement executed do not cover the Labour Cess. It is further submitted that the Irrigation Department unilaterally cannot authorise to recover the Labour Cess from the Contractors bills, without consent of the contractor or entering into supplemental agreement by including suitable provision of 1% Labour Cess in the revised estimate. It is, therefore, submitted that the direction issued by the Finance and Planning Department is wholly without jurisdiction, and it is therefore arbitrary and violative of Article 14 of the Constitution of India.
5. Learned Counsel for the Writ Petitioner has furnished a copy of the Order passed by the Learned Single Judge of this Court in CH.V.V. Subba Rao Vs. Government of Andhra Pradesh, represented by its Principal Secretary and Others (W.P.No.11269 of 2009 & batch dated 22.10.2009) and submitted that this issue is no more res integra and the law, as settled by this Court in the above judgment, has become final.
6. This Court has perused the Order passed by the Learned Single Judge in CH.V.V. Subba Rao Vs. Government of Andhra Pradesh, represented by its Principal Secretary and Others (W.P.No.11269 of 2009 & batch dated 22.10.2009). The relevant portion of the Judgment is usefully extracted hereunder:
Deductions for Labour Cess are valid only if the cess is included in the contract estimates, as per the Building and Other Construction Workers Cess Act, 1996.
Deductions for Labour Cess are only valid if included in the contract estimates, reaffirming the principle that contractors cannot be penalized for omissions not reflected in their agreements.
The main legal point established in the judgment is that the labour cess is not leviable on the supply of materials and consultancy charges under the Building and Other Construction Workers' Welfare ....
Taxes not to be imposed save by authority of law - Article 265 of Constitution is the source of power for the Union and States to impose taxes in accordance with law. Article 265 of the Constitution ....
The Labour Cess cannot be retrospectively applied to tenders initiated before the cut-off date specified in the Circular dated 09.07.2010.
The court held that deductions for the cess on construction payments are valid under the relevant welfare legislation, affirming that activities like laying pipelines constitute construction work.
Cess under the Cess Act read with BOCW Act is leviable in respect of building and other construction works.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.