SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Kar) 222

IN THE HIGH COURT OF KARNATAKA AT BENGALURU
SURAJ GOVINDARAJ, J.
J.M. Swamy – Appellant
Versus
Government Of India Central Public Work Department Rep By Its – Respondent
Civil Misc. Petition No. 168 of 2021
Decided on : 11-08-2022

Advocates:
Advocate Appeared:
For the Appellant :Sri. P. Harischandra Reddy, Advocate
For the Respondent: Sri Kumar. M.N, adv

Point of Law: Requirement of A&C Act is for an independent Arbitrator to be appointed, so that he/she would be in a position to decide matter impartially and as such, reducing possibility of a challenge to an arbitral award being passed by such an Arbitrator.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 11 (6) (a) & (c), 11 , 9, 12(1)(b) , 12(5) , 13 - Sole Arbitrator - Challenge procedure - Grounds for challenge - Seeking interim protection - there are any justifiable doubts as to independence or impartiality of Arbitrator appointed or not in light of grievance raised by petitioner and petitioner not being acceptable to said Arbitrator arbitrating disputes between parties - bar under Section 12(5) of A&C Act would apply to a former employee or not - In interest of speedy arbitration it is required of this court to appoint an Arbitrator acceptable to one and all so as avoid any delay in such challenge proceedings. (Para 29).

Finding of the Court: Court is of considered opinion that there are justifiable grounds about Arbitrator being independent or impartial and therefore, would come within mischief of Section 12(5) of A&C Act. Therefore, appointment is made prior to amendment or post amendment, Court is of considered opinion that disqualification on account of possible conflict of interest and justifiable grounds of impartiality and independence would apply to Arbitrator appointed by respondent. When such a disqualification is exfacie evident, Court is of considered opinion that there would be no purpose served by this Court permitting petitioner to raise issue by filing necessary challenge before Arbitrator in terms of Section 13 of A&C Act.

Result: Ordered accordingly.

ORDER :

1. The petitioner is before this Court seeking for the following reliefs:

    a. To pass an appropriate order by terminating the existing arbitral tribunal for appointment of independent and impartial Sole Arbitrator in the place of 3rd respondent as per the petitioner requests under the provisions of section 11 (6) sub-section (a) & (c) of the Arbitration and Conciliation Act, 1996 Amended Act 2015 (3 of 2016) to adjudicate the disputes/claims between the parties for the work of "SITC of Combined Effluent Treatment Plant in STC, BSF campus, Yelahanka, Bangalore SH: Construction of Sewage Treatment Plant of MBBR (Movable Bed Bioreactor) of 350 KLD capacity including electromechanical components", Contract Agreement No.16/SE/BCD111/2016-17 date 15-2-2017.

b. To pass an appropriate order as per the clause 25 of GCC and also amended act 2015 (3 of 2016) by appointing independent and impartial sole arbitrator under section 11 (8) of the act for settlement of disputes/claims between the parties as per the conditions of contract.

c. Pass such other orders as the Hon'ble Court deems fit in the interest of justice and equity.

d. MAKE any further scheme for dealing with the matter as contemplated under sub-section (10) of section 11 of the Arbitration and Conciliation Act, 1996 Amended Act 2015 (3 of 2016).

2. The petitioner having participated in a tender, had been awarded certain works in pursuance of which the work order dated 23.01.2017 came to be issued and an agreement dated 15.02.2017 came to be executed between the parties, wherein the settlement of disputes and arbitration is governed by a rather long dispute resolution clause in terms of Clause 25 thereof which is reproduced hereunder for easy reference:

    Clause 25:

Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawing and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating the contract, designs, drawings, specifications, estimates, instructions, orders conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:

i. If the contractor considers any work demanded of him to be outside the requirements of contract, or disputes any drawings, record or decision given in writing by the Engineer in-Charge on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days request the Superintending Engineer shall give his written instructions or decision within a period of one month from receipt of contractor's letter.

If the Superintending Engineer fails to give his instructions or decision in writing within the aforesaid period or if the contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the contractor may, within 15 days of receipt of Superintending Engineer’s decision, appeal to the Chief Engineer who shall afford an opportunity to the contractor to be heard, if the latter so desire, and to offer evidence in support his appeal. The Chief Engineer shall give his decision within 30 days of receipt contractor's appeal. If the contractor is dissatisfied with the decision of the Chief Engineer, the contractor may within 30 days from the receipt of the Chief Engineer’s decision, appeal before the Dispute Redressal Committee (DRC) along with a list of disputes with amounts claimed in respect of each such dispute and giving reference to the rejection of his disputes by the Chief Engineer. The Dispute Redressal Committee (DRC) shall give his decision within a period of 90 days from the receipt of Contractor’s appeal. The constitution of Di

                  Click Here to Read the rest of this document
                  1
                  2
                  3
                  4
                  5
                  6
                  7
                  8
                  9
                  10
                  11
                  SupremeToday Portrait Ad
                  supreme today icon
                  logo-black

                  An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                  Please visit our Training & Support
                  Center or Contact Us for assistance

                  qr

                  Scan Me!

                  India’s Legal research and Law Firm App, Download now!

                  For Daily Legal Updates, Join us on :

                  whatsapp-icon Back to top