IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
ARAVIND KUMAR, J.
Bhagwati Construction - Petitioner
Versus
Western Railway - Respondent
R/Petn. Under Arbitration Act No. 89 of 2019
Decided On : 25-02-2022
Civil Procedure Code, 1908 – Section 79 – Arbitration and Conciliation Act, 1996 – Sought for extension – Special Leave to Appeal – Petitioner is seeking appointment of a sole arbitrator contending inter alia that it is a registered partnership firm and having got itself registered as a Government approved Contractor, is carrying on business – Held, Court of considered view that statutory bar contained in subsection (5) of Section 12 would be squarely applicable and respondent cannot take a stand that it has a right to appoint an employee either present or past to adjudicate disputes and Railways should not hesitate in taking a stand to appoint an impartial arbitrator though it cannot be gainsaid by contractor like petitioner to contend that panel of arbitrators of respondent would not be impartial – Petition allowed.
ORDER :
1. Heard learned advocate Mr. Sukhwani appearing for the petitioner and learned advocate Ms. Archana Amin appearing for the respondents. Perused the records.
2. Petitioner is seeking appointment of a sole arbitrator contending inter alia that it is a registered partnership firm and having got itself registered as a Government approved Contractor, is carrying on the business. Pursuant to tender called for by the respondents, petitioner was awarded the contract for rebuilding of covering shed over Platform No. 1 & Platform surfacing, construction of foot over bridge with ramps and other miscellaneous work in connection with utility shifting for the proposed DFC parallel alignment on Pansar – Palanpur section and an agreement dated 12.06.2018 came to be entered into between the parties in this regard. As agreed under the agreement, the rate was fixed at Rs.7,67,04,303.87. This was proceeded by the acceptance of tender and submission of performance guarantee as well as irrevocable bank guarantee amounting to Rs.38,35,215/- submitted by the petitioner in favour of the Western Railway. The agreement stipulated the time for completion of work as 12 months. Petitioner has alleged that for completion of work, respondents were required to provide drawings and it was belatedly furnished and the work for platform was awarded only on 30.07.2018 and on account of there being live water line and electric cable line, it was not possible to speed up the work. Petitioner is said to have appraised the Deputy Chief Engineer of the bottlenecks faced in execution of the work by communication dated 01.10.2018 and as such sought for extension, which is said to have been granted upto 31.03.2019. Petitioner is said to have sought for dismantling old shed, as it was not possible to do new work on the ground that it would endanger human life and as such requested the respondent for dismantling old shed and sought for providing drawing for covering shed and finalizing the drawing for foot over bridge. Petitioner is said to have received 48 hours notice from the office of Deputy Chief Engineer dated 02.01.2019 in terms of Clause 62 of the Standard General Conditions of contract, which is said to have been duly replied by the petitioner and assured that the work would be completed on or before 31.03.2019 and requested the respondent to withdraw 48 hours notice issued. Thereafter the respondent is said to have issued 7 days notice on 01.02.2019 resulted in petitioner informing the respondent by communication dated 12.02.2019 that petitioner was not provided with entire scope of work and only 30% was provided. Subsequently, Deputy Chief Engineer by communication dated 15.02.2019 is said to have rescinded the contract on the ground that termination of the contract is in terms of Clause 62. Contending said termination is wrongful and illegal and it was valid till 31.03.2019, as also the fact that time was not the essence of the contract, notice came to be issued to respondent by the petitioner on 26.02.2019 seeking payment of 1,15,05,645/- with interest @ 18% p.a. from the date of termination of the contract and also sought for release of FDRs within a period of 30 days and informing the respondent that failure to comply with the demands made thereunder, petitioner would be constrained to file a petition seeking for referring the disputes for being adjudicated through arbitration. On account of said demand having not been complied nor notice being replied, present petition has been filed.
3. On service of notice, respondents have appeared and filed their reply contending inter alia that Union of India is not a party and Western Railway is owned by the Union of India and the above petition is essentially against the Union of India and as such, proceedings should have been against the Union of India as contemplated under section 79 of Code of Civil Procedure and as such it is contended present petition is not maintainable. Denying the averments made in the p
Central Organisation for Railway Electrification Versus ECI-SPIC-SMO-MCML (JV) A Joint Venture
Jaipur Zila Dugadh Utpadak Sahkari Sangh Limited and Others Versus Ajay Sales and Suppliers
Voestalpine Schine GMBH Versus Delhi Metro Rail Corporation Ltd.
The main legal point established in the judgment is the importance of impartiality and independence of arbitrators, as well as the need for a balanced approach to arbitration, as emphasized by the in....
The appointment of an arbitrator must comply with the Arbitration and Conciliation Act, particularly Section 12(5), which disqualifies certain individuals from serving as arbitrators.
An employee of the respondent or even a retired employee would be ineligible to be appointed as an arbitrator. The panel of arbitrators should be broad-based and should include persons with diverse b....
The main legal principle established in the judgment is the procedure for appointing arbitrators under the amended Act and the modified Clause 64 of the GCC, emphasizing the ineligibility of certain ....
The court affirmed that the claimant must secure the necessary Airport Entry Permits and upheld the arbitration award, ruling no breach by the respondent; consent regarding the arbitrator's appointme....
The court reinforced that impartiality and independence of arbitrators is essential, disqualifying those with vested interests under Section 12(5) of the Arbitration and Conciliation Act, 1996.
2020 Rules which came into force from the date of their publication in the Official Gazette, i.e. 12.02.2020, cannot be given retrospective effect. The intention of Government of India to make the 20....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.