2024 Supreme(Kar) 259
IN THE HIGH COURT OF KARNATAKA
H.P.Sandesh, J.
Executive Engineer – Appellant
Versus
M/S. Theju Construction Co. – Respondent
Miscellaneous first appeal no. 7703 of 2014
Decided On : 02-02-2024
Important Points
Subject
Civil Law
Act Referred
Headnote
ARBITRATION - ARBITRATION AND CONCILIATION ACT, 1996 - Sections 24, 34 - The court discussed the provisions of the Arbitration and Conciliation Act, 1996, particularly Sections 24 and 34. Section 24 mandates that all statements and documents submitted by one party must be communicated to the other party, ensuring fairness in the arbitration process. Section 34 outlines the limited grounds on which a court can set aside an arbitration award, emphasizing that the court's role is not to re-evaluate the merits of the case but to ensure procedural compliance. The court found that the trial court erred in setting aside the arbitration award based on claims of lack of jurisdiction and failure to provide opportunity, as the arbitrator had indeed provided sufficient opportunities for both parties to present their cases.
Fact of the Case:
The appellant challenged the trial court's decision to set aside an arbitration award in a dispute regarding the construction of residential accommodation for an etiological center. The trial court found that the arbitrator had not considered certain applications and had failed to provide adequate opportunity to the plaintiff, leading to a claim of lack of jurisdiction.
Finding of the Court:
The court found that the trial court had erred in its assessment of the arbitrator's conduct. It noted that the arbitrator had provided multiple opportunities for both parties to present their cases and that the claims of lack of jurisdiction were unfounded. The court emphasized the limited scope of review under Section 34 of the Arbitration and Conciliation Act.
Issues: Whether the trial court correctly set aside the arbitration award based on claims of lack of jurisdiction and failure to provide adequate opportunity to the plaintiff.
Ratio Decidendi: The court held that the trial court misapplied the provisions of the Arbitration and Conciliation Act, particularly Sections 24 and 34. It clarified that the arbitrator had indeed provided sufficient opportunities for both parties and that the trial court's findings were not supported by the evidence presented.
Final Decision: The court allowed the appeal, set aside the trial court's order, and restored the arbitration award.
Sri. Kumar M.N.,CGC, for the Appellant; Sri. Bharath Kumar V., Advocate, for the Respondent.
JUDGMENT
H.P. Sandesh, J.
Heard the learned counsel for the appellant and though the respondent represented through the counsel, the counsel did not choose to appear before this Court. This Court made it clear in the previous occasion that if the respondent's counsel does appear in the next date of hearing, the matter will be heard in his absence. Hence, this Court heard the counsel appearing for the appellant in the absence of the respondent's counsel.
2. The main contention of the appellant's counsel that the Trial Court erroneously reversed the arbitration award in A.S.No.26/2007 filed by the respondent. The counsel also brought to notice of this Court paragraph Nos.20 and 21 of the order. In paragraph No.20 an observation is made that on perusal of the award it doesn't not disclose that, any of such applications of the plaintiff have been considered by the Arbitrator while passing the award. It has been urged by the plaintiff in Annexure -'E' viz., letter of the plaintiff to the Executive Engineer defendant No.3 and having sent copy of the same to the then Arbitrator stating that copies of some of the pages of the measurement books supplied by the Executive Engineer are not related to the work in question and measurement book numbers are even not forthcoming on the copies and also sought for complete measurement books duly certified, the said aspect has not been considered by the Arbitrator, it has to be stated that, the plaintiff has not been properly afforded opportunity and as such, the claim of the plaintiff/claimant has been affected by the said award of the Arbitrator which can be termed that, the said aspect having not been considered by the Arbitrator, it is seriously affected the case of the plaintiff. The counsel also brought to notice of this Court observation made in paragraph No.21 having considered all the aspects, when the jurisdiction of the Arbitrator itself is questioned and the very opportunity being not heard is evidence the same and as a result of same, the Arbitrator having not followed section 24 of the Arbitration and Conciliation Act, 1996, the award of the Arbitrator is liable to be set-aside. Therefore, the said materials available before the Court and in the light of the contentions of the parties and also in the light of the said rulings relied by the Advocate for the plaintiff, the circumstances involving in this case, demand for setting aside the award in question. Hence, the Trial Court exercised the power under Section 34(2) of the Arbitration and Conciliation Act, 1996 to set aside the award.
3. The counsel appearing for the appellant would vehemently contend that scope of Section 34 is very limited and also observation made by the Trial Court while setting aside the award is erraneous and inspite of sufficient opportunities is given and the same is noted in the award itself and also the counsel brought to notice of this Court the respondent was absent almost all the days i.e., out of 12 days, 6 times he was absent. Even Arbitrator while proceeding the matter also given an opportunity to submit any written submission by fixing the date and no such written submission is also made and having considered the opportunity proceeded to pass the award. The counsel would submits that the observation made by the Trial Court that there was no any jurisdiction and the same is erraneous. The counsel brought to notice of this Court clause 25 of the agreement between the plaintiff and respondent wherein it is clearly mentioned that if any dispute between the parties, the matter shall be referred to the sole Arbitrator who appointed by the Chief Engineer, Civil Wing, New Delhi in charge of the work at the time of dispute or there will be no Chief Engineer, the Administrative head of the said department at the time of the appointment. It will be no objection to such appointment that the Arbitrator so appointed is a government servant that he had to deal with the matters to which the Contracts relates and that