IN THE HIGH COURT OF KARNATAKA AT BENGALURU
ANU SIVARAMAN, VIJAYKUMAR A.PATIL, JJ.
B. Lakshman Gupta S/o Late B.L. Betaiah Setty – Appellant
Versus
M/s. Sampurna Builders – Respondent
Commercial Appeal No. 451 of 2023
Decided On : 17-12-2025
| Table of Content |
|---|
| 1. challenge to arbitral award under commercial courts act (Para 1 , 4) |
| 2. arguments on limitation and compliance with agreements (Para 5 , 6 , 7) |
| 3. court analysis of arbitral award findings (Para 8 , 9 , 10 , 15) |
| 4. limitations periods for claims and counterclaims (Para 11 , 12 , 13) |
| 5. standard for judicial interference with arbitral awards (Para 14 , 16) |
| 6. outcome of the appeal and order (Para 17 , 18) |
JUDGMENT :
ANU SIVARAMAN, J.
1. This appeal is filed under Section 13 (1-A) of the Commercial Courts Act, 2015 challenging the Judgment dated 21.09.2023 passed by LXXXV Additional City Civil and Sessions Judge, Bengaluru (CCH-86) ('Commercial Court' for short) in Commercial Appeal No.93/2023.
2. We have heard Shri. Nandakumar C.K. learned senior counsel as instructed by Shri. Sridhar Chakravarthi M.V. learned counsel appearing for the appellants.
3. Notice had been ordered by way of substituted service to the respondents on 06.06.2024 and duly served. However, there is no representation on behalf of the respondents.
4. The subject matter of the dispute between the parties was the handing over of built-up area to the appellants, who were the landowners on the basis of Joint Development Agreement dated 11.06.2008 and Supplementary Joint Development Agreement dated 18.03.2010. The matter was referred to arbitration and an arbitral award was passed on 27.06.2022, allowing the claim in part. The respondents herein filed an arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 ('Arbitration Act' for short) challenging an arbitral award dated 27.06.2022. The same was allowed and the award was set aside. The claimants are in appeal under Section 13 (1-A) of the Commercial Courts Act, 2015.
5. The learned senior counsel appearing for the appellants submits that there was no justification on the part of the Commercial Court in having interfered with the arbitral award. It is submitted that the parties had entered into a registered Joint Development Agreement dated 11.06.2008 and a Registered Supplementary Joint Development Agreement dated 18.03.2010. The Supplementary Joint Development Agreement provided for completion of construction within 18 months with a grace period of six months. It was further provided that after completion of the construction, 28% of the built-up area would be handed over by the developer to the appellants. Alleging that the built-up area in floor number 4 and 5 and the corresponding parking space was not handed over, the appellants sought reference of the dispute to arbitration. Thereafter, they filed CMP No.94/2018, which was allowed and the sole arbitrator was appointed to adjudicate the disputes between the parties. The arbitrator allowed the claim of the appellants in part and held that they were entitled to 28% of the build-up area in the fourth and fifth floors of the schedule property along with corresponding extent of parking space and ordered compensation of Rs.2,25,000/- per month, if the respondents fail to honour the award within three months.
6. In the Section 34 application preferred by the respondents herein, the Commercial Court held that the time to complete the construction having ended on 18.03.2012, the claim preferred by the appellants on 21.12.2017, was barred by limitation. The application was allowed and the award was set aside. It was found that the finding in the arbitral award that limitation for raising the main claim starts only when the claimant has notice of refusal to handover 28% of the built-up area in floors 5 and 6, is contrary to the agreement entered into between the parties by way of Ex.P2 - Supplementary Joint Development Agreement. It was found that the claim was barred by limitation and the finding on limitation entered into in the award is a patent illegality that vitiates the award.
7. The learned senior counsel appearing for the appellants submits that the respondents being put on notice by the sole arbitrator filed their st
Bharat Sanchar Nigam Limited and Another v. Nortel Networks India Private Limited
AI
An arbitral award can only be set aside on limited grounds as defined in Section 34 of the Arbitration Act, and claims are not barred by limitation if notice of refusal is not received.
The court upheld the trial court's dismissal of the appeal against the arbitration award, confirming that there was no patent illegality or grounds for interference under the Arbitration and Concilia....
The court affirmed that arbitral awards can only be set aside under Section 34 if grounds of patent illegality are established, emphasizing the sanctity and finality of arbitration decisions.
Point of law: Section 2(1)(c) of Act, 2015 defines what is meant by ‘commercial dispute’ and instances are mentioned in various clauses incorporated therein. ‘Commercial dispute’ means a dispute aris....
Arbitration proceedings validly commenced under Section 21 of the Arbitration Act on notice dated 20.08.1992; findings on completion and cost claims affirmed due to lack of evidence.
The court upheld the arbitral award directing possession and damages, affirming the applicability of limitation provisions to arbitration proceedings.
Limited judicial interference under Sections 34/37 of Arbitration Act; no re-appreciation of arbitral findings absent patent illegality.
The court reiterated that a party's failure to perform contractual obligations negates the other's right to enforce the contract, emphasizing limited interference in arbitral awards.
The jurisdiction of the Appellate Court dealing with an appeal under Section 37 against the judgment in a petition under Section 34 is more constrained than the jurisdiction of the Court dealing with....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.