SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Kar) 1830

IN THE HIGH COURT OF KARNATAKA AT BENGALURU
ANU SIVARAMAN, VIJAYKUMAR A.PATIL, JJ.
B. Lakshman Gupta S/o Late B.L. Betaiah Setty – Appellant
Versus
M/s. Sampurna Builders – Respondent
Commercial Appeal No. 451 of 2023
Decided On : 17-12-2025

Advocates Appeared:
For the Appellants : Nandakumar C.K., Sridhar Chakravarthi M.V.

An arbitral award can only be set aside on limited grounds as defined in Section 34 of the Arbitration Act, and claims are not barred by limitation if notice of refusal is not received.

Headnote:(A) Commercial Courts Act, 2015 - Section 13(1-A) - Arbitration and Conciliation Act, 1996 - Section 34 - Appeal challenging the commercial court's order setting aside an arbitral award. (Paras 1, 4, 6)

(B) Legal principle - An arbitral award can only be interfered with on limited grounds under Section 34; the finding by the Commercial Court that the claim was barred by limitation is contrary to the agreement and findings of the sole arbitrator. (Paras 6, 14)

(C) The court observed that limitation for the main claim starts when the claimant has notice of the refusal to perform. The arbitral tribunal correctly determined that this occurred upon notice received by the claimants. (Paras 11, 15)

Facts of the case:
The appellants and respondents entered into a Joint Development Agreement, leading to arbitration due to non-delivery of built-up area. The arbitral award allowed the claim in part but was overturned by the Commercial Court on limitation grounds.

Findings of Court:
The Commercial Court misdirected itself in its interference, as the claim was not barred by limitation.

Issues: Whether the claim was barred by limitation, and whether the Commercial Court had justifiable grounds to interfere with the arbitral award.

Ratio Decidendi: The court ruled that the limitation period began when performance was refused and the Commercial Court overstepped its authority.

Result: The Commercial Appeal is allowed, the Commercial Court's judgment is set aside, and the arbitral award is upheld.

Table of Content
1. challenge to arbitral award under commercial courts act (Para 1 , 4)
2. arguments on limitation and compliance with agreements (Para 5 , 6 , 7)
3. court analysis of arbitral award findings (Para 8 , 9 , 10 , 15)
4. limitations periods for claims and counterclaims (Para 11 , 12 , 13)
5. standard for judicial interference with arbitral awards (Para 14 , 16)
6. outcome of the appeal and order (Para 17 , 18)

JUDGMENT :

ANU SIVARAMAN, J.

1. This appeal is filed under Section 13 (1-A) of the Commercial Courts Act, 2015 challenging the Judgment dated 21.09.2023 passed by LXXXV Additional City Civil and Sessions Judge, Bengaluru (CCH-86) ('Commercial Court' for short) in Commercial Appeal No.93/2023.

2. We have heard Shri. Nandakumar C.K. learned senior counsel as instructed by Shri. Sridhar Chakravarthi M.V. learned counsel appearing for the appellants.

3. Notice had been ordered by way of substituted service to the respondents on 06.06.2024 and duly served. However, there is no representation on behalf of the respondents.

4. The subject matter of the dispute between the parties was the handing over of built-up area to the appellants, who were the landowners on the basis of Joint Development Agreement dated 11.06.2008 and Supplementary Joint Development Agreement dated 18.03.2010. The matter was referred to arbitration and an arbitral award was passed on 27.06.2022, allowing the claim in part. The respondents herein filed an arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 ('Arbitration Act' for short) challenging an arbitral award dated 27.06.2022. The same was allowed and the award was set aside. The claimants are in appeal under Section 13 (1-A) of the Commercial Courts Act, 2015.

5. The learned senior counsel appearing for the appellants submits that there was no justification on the part of the Commercial Court in having interfered with the arbitral award. It is submitted that the parties had entered into a registered Joint Development Agreement dated 11.06.2008 and a Registered Supplementary Joint Development Agreement dated 18.03.2010. The Supplementary Joint Development Agreement provided for completion of construction within 18 months with a grace period of six months. It was further provided that after completion of the construction, 28% of the built-up area would be handed over by the developer to the appellants. Alleging that the built-up area in floor number 4 and 5 and the corresponding parking space was not handed over, the appellants sought reference of the dispute to arbitration. Thereafter, they filed CMP No.94/2018, which was allowed and the sole arbitrator was appointed to adjudicate the disputes between the parties. The arbitrator allowed the claim of the appellants in part and held that they were entitled to 28% of the build-up area in the fourth and fifth floors of the schedule property along with corresponding extent of parking space and ordered compensation of Rs.2,25,000/- per month, if the respondents fail to honour the award within three months.

6. In the Section 34 application preferred by the respondents herein, the Commercial Court held that the time to complete the construction having ended on 18.03.2012, the claim preferred by the appellants on 21.12.2017, was barred by limitation. The application was allowed and the award was set aside. It was found that the finding in the arbitral award that limitation for raising the main claim starts only when the claimant has notice of refusal to handover 28% of the built-up area in floors 5 and 6, is contrary to the agreement entered into between the parties by way of Ex.P2 - Supplementary Joint Development Agreement. It was found that the claim was barred by limitation and the finding on limitation entered into in the award is a patent illegality that vitiates the award.

7. The learned senior counsel appearing for the appellants submits that the respondents being put on notice by the sole arbitrator filed their st

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top