IN THE HIGH COURT OF KARNATAKA DHARWAD BENCH
M. Nagaprasanna, J.
Torrent Solar Power Private Limited - Petitioner
Versus
Power Grid Koppal Gadag - Respondent
Writ Petition No.104896 OF 2025 (GM - RES)
Decided On : 15-12-2025
| Table of Content |
|---|
| 1. detailed background of power project and approvals. (Para 2) |
| 2. contrasting arguments of parties regarding wtg locations. (Para 4 , 5) |
| 3. court's analysis of public interest in transmission lines. (Para 6 , 7 , 12) |
| 4. supreme court's rationale on transmission lines' legality. (Para 10) |
| 5. final decision rejecting the petition. (Para 13) |
ORDER :
M. Nagaprasanna, J.
The petitioner is at the doors of this Court seeking the following reliefs:
“i. Issue a writ order or direction of mandamus or in the nature of mandamus directing the Respondent to re-route the Extra High Voltage ("EHV") Lines without interrupting any work, erections, etc. within the distance of 227 meters of the Petitioner's land parcels as per Ministry of New and Renewable Energy ("MNRE") Guidelines at WTG Locations as per coordinates morefully detailed in the map/sketch (Annexure-R)
ii. Issue a writ order or direction of certiorari or in the nature of certiorari quashing and setting aside the letters dated 01/04/2025 number reference bearing by SRTS- II/PKGT L/Gadag TLC/2024-25/273 (Annexure- S), the letter dated 07/02/2025 bearing reference number PKGTL-Gadag/TLC/Torrent/255 (Annexure-P) sent Respondent to the Petitioner asking to relocate the WTG Locations along with the connected communication dated 06/02/2025 (Annexure-N);
iii. Issue a writ order or direction of mandamus or in the nature of mandamus restraining the Respondent from issuing any directions to, or otherwise in any manner seeking to compel a change in the WTG Locations and further restrain the Respondent from in any manner interfering with the business and activities/Project of the Petitioner; and iv. Pass such orders as this Hon'ble Court may deem just and proper in the facts and circumstances of the present writ petition.”
2. Facts in brief, germane, are as follows:
2.1. The petitioner - Torrent Solar Power Pvt. Ltd., (hereinafter referred to as the ‘Company’ for short) is a Company established in the year 2020, as an integrated power utility, having its business or interest in power generation, transmission, distribution and supply of power cables and operates wind power generation projects at various places. The respondent is the Power Grid Koppal Gadag Transmission Ltd., (hereinafter referred to as the ‘Power Grid’ for short) a wholly owned subsidiary of the Power Grid Corporation of India. Power Grid is incorporated as a special purpose vehicle of the Government of India for transmission. In the years 2021-2022, the petitioner is said to have conducted a deliberation with the Ministry of New and Renewable Energy (MNRE) for setting of 300.3 MW. Wind power project, which is proposed to be established in the villages of Yalaburga and Koppal Taluk of Koppal District. After the deliberations, it transpires that the petitioner submits an application to the Karnataka Renewable Energy Development Limited (KREDL) as per the MNRE guidelines, requesting for allotment of 300.3 MW. wind power project under the Inter-State Transmission System (ISTS) category at various places.
2.2. Pursuant to the said deliberation, the petitioner is said to have prepared a detailed project report for the project for the purpose of enquiry or investigation into the feasibility of the project and is submitted to KREDL. The particulars of the locations and the project including the latitude and longitude of the land requirement, the tentative survey numbers, the tentative village names, the height of the wind mast for each proposed site and the tentative project schedule are said to have been submitted by the petitioner.
2.3. The Government, in terms of its order dated 23-02-2022, accorded an in-principle approval to the project of the petitioner by issuance of a Government order, pursuant to which, the petitioner enters into an agreement with KREDL, agreeing to complete the project by 22-02-2028. Between 27-04-2023 and 29-11-2023, the petitioner secured conversion of agricultural lands into non-agricultural purposes, a







The court emphasized that electric transmission lines serve a higher public interest, and unilateral alterations by the petitioner to WTG locations are impermissible without approval.
The authority of the respondent to shift transmission towers under the Electricity Act and the entitlement of aggrieved parties to compensation under the Indian Telegraph Act.
The authority under the Indian Telegraph Act has the right to lay transmission lines on private property, prioritizing public interest and following due process, including compensation for any damage....
The statutory framework permits the installation of power transmission lines on private land despite objections, with the authority required primarily to consider compensation rather than block the p....
The main legal point established in the judgment is that once the technical feasibility of an electricity project is approved by the appropriate Government, the landowner has no right to object to th....
The court upheld the statutory authority to lay electricity lines, prioritizing public interest over individual objections.
The court's decision was influenced by the completion and functionality of the electric line, the failure of the villagers to substantiate their claims, and the analysis of the provisions of the Elec....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.