2026 Supreme(Kar) 333
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
SURAJ GOVINDARAJ, J.
P S Adinarayana Prasad S/o Late Sri. P.Satyanarayana - Appellant
Vs.
M/s Hindustan Petroleum Corporation Ltd. - Respondent
Writ Petition No. 19508 Of 2025 (GM-RES)
Decided On : 04-08-2026
Important Points
Subject
Civil Law - Arbitration and Conciliation
Act Referred
LIMITATION ACT : S.5
Headnote
(B) Legal Principles - Maxim "nullus commodum capere potest de injuria sua propria" - No person can take advantage of his own wrong - A party cannot rely on a self-created disability or its own inaction to enlarge the rigid period of limitation fixed by statute (Paras 33, 36).
(C) Arbitral Award - Delivery and Receipt - Duty of the tribunal/institution to deliver a signed copy under Section 31(5) is substantially discharged when the institution informs the parties that the award is ready for collection subject to the statutory lien for unpaid costs under Section 39 (Paras 20, 38).
Facts of the case:
An arbitral award was pronounced and the arbitral institution notified both parties that the signed copy was ready for collection upon payment of dues. One party paid the dues and collected the signed copy promptly. The other party delayed the payment of costs and the subsequent collection of the signed copy. This party then filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the limitation period began only from the date of actual physical receipt of the signed copy, despite the award having been ready for delivery much earlier.
Findings of Court:
The delay in obtaining the signed copy was solely attributable to the applicant's failure to pay dues and collect the award promptly. Since the award was ready and the institution had notified the parties, the applicant's own inaction cannot be used to extend the limitation period.
Issues: Whether, while computing the period of limitation under Section 34(3) of the Arbitration and Conciliation Act, 1996, the Court is required to take into consideration the delay attributable to the applicant in obtaining the signed copy of the arbitral award after the award had admittedly become ready for delivery? (Para 11)
Ratio Decidendi: The court ruled that a party cannot postpone the commencement of limitation by its own delay in complying with steps entirely within its control. Where the arbitral institution has made the signed award available and informed the parties that it may be collected upon payment of prescribed dues, any self-induced delay by the recipient must be excluded. Such inaction cannot enlarge the rigid statutory period provided under Section 34(3) of the Act. (Para 42)
Result: Writ petition allowed; order of the Commercial Court set aside; application under Section 34 held to be barred by limitation and dismissed.
Advocate Appeared:
For the Appellant :Sri. Subhash Srinivasa Rangachar, Advocate
For the Respondent:Sri. Pramod.B., Advocate
ORDER :
SURAJ GOVINDARAJ, J.
1. The Petitioner is before this court seeking for the following reliefs:
a. Call for the records in Com. A.P. NO. 112/2024 pending on the file of LXXXIV ADDL. CITY Civil and Sessions Judge (CCH-85), (Commercial Court) Bengaluru.
b. Hear the petitioner allow the prayer made in IA No. 1 filed in CO. AP. NO. 112/2024 on the file of LXXXIV Addl. City Civil and Sessions Judge (CCH85) Commercial Court, Bengaluru vide Annexure-F;
c. Declare that the COM. AP 112/2024 on the file of LXXXIV Addl. City Civil and Sessions Judge (CCH85), Commercial Court is not maintainable as the same is. barred by limitation.
d. Set aside the orders dt. 08.01.2025 passed on IA No. 1 in COM. AP 112/2024 on the file of LXXXIV Addl.City Civil and Sessions Judge (CCH85) Commercial Court, Bengaluru.
e. Such other relief and reliefs as this Hon’ble Court may deem fit to grant in the facts and circumstances of the case.
2. The petitioner is a dealer operating a retail outlet for petrol and petroleum products under a dealership agreement with the respondent, M/s Hindustan Petroleum Corporation Limited ("HPCL"). The retail outlet has been in operation since the year 1959.
3. On 31.12.2017, HPCL conducted an inspection of the petitioner's retail outlet through its inspection team. Based on the observations recorded during the inspection, a show-cause notice was issued calling upon the petitioner to submit its explanation. Not being satisfied with the explanation offered, HPCL terminated the dealership agreement. Aggrieved by the said termination, the petitioner instituted proceedings under Section 9 of the Arbitration and Conciliation Act, 1996 ("the A&C Act"), seeking an interim injunction against the termination. The competent Court granted an order of injunction.
4. Thereafter, the petitioner invoked the arbitration clause contained in the dealership agreement. Since HPCL did not appoint an Arbitrator, the petitioner approached this Court under Section 11 of the A&C Act. Pursuant to the orders passed by this Court, an Arbitrator was appointed. The arbitral proceedings were conducted under the aegis of the Arbitration and Conciliation Centre, Bengaluru. Upon conclusion of the proceedings, the matter was reserved for award on 14.01.2024.
5. On 15.02.2024, the Arbitration and Conciliation Centre, Bengaluru, addressed a communication to both parties informing them that the arbitral award had been passed on that day and calling upon them to pay the requisite administrative charges payable to the Centre for obtaining the signed copy of the award. HPCL thereafter remitted the requisite charges, obtained the signed copy of the arbitral award on 22.04.2024, and subsequently instituted proceedings under Section 34 of the A&C Act challenging the award.
6. Upon presentation of the petition under Section 34 of the A&C Act, the Registry raised an objection regarding limitation. In response, HPCL contended that the signed copy of the arbitral award had been received only on 22.04.2024 and that the petition presented on 18.07.2024 was within the period of limitation prescribed under Section 34(3) of the A&C Act.
7. The present petitioner thereafter filed I.A. No. I on 08.11.2024 in Com.A.P. No.102 of 2024 contending that the petition under Section 34 was barred by limitation. By order dated 08.01.2025, the LXXXIV Additional City Civil and Sessions Judge (Commercial Court), Bengaluru, rejected the said application.Aggrieved by the rejection of the application, the petitioner has filed the present writ petition.
8. Sri.Subhash Srinivasa Rangachar, learned counsel for the petitioner submits that;
8.1. The communication issued by the Arbitration and Conciliation Centre on 15.02.2024 categorically stated that the arbitral award had been pronounced on 15.02.2024 and called upon the parties to pay the dues payable to the Centre. The said communication dated 15.02.2024 is reproduced hereunder for easy reference;
AC No.227/2021-Award Pronounced