1968 Supreme(Bom) 103
IN THE HIGH COURT OF BOMBAY
Vimadalal, J.
Appellants: K.G. Hiranandani
Vs.
Respondent: Bharat Barrel and Drum Mfg. Co. Pvt. Ltd.
Suit No. 355 of 1963Decided On: 19.09.1968
Counsels:
For Appellant/Petitioner/Plaintiff: A.N. Mody and H.G. Advani, Advs.
For Respondents/Defendant: C.N. Daji and P.R. Kedia, Advs.
Important Points
Subject
Contract Law - WRONGFUL TERMINATION OF SERVICE
Act Referred
CONSTITUTION OF INDIA : Art.141
CONTRACT ACT : S.73
EVIDENCE ACT : S.106, S.103
Headnote
CONTRACT - WRONGFUL TERMINATION OF SERVICE - DAMAGES - MEASURE OF DAMAGES - NORMAL MEASURE OF DAMAGES IS SALARY FOR THE WHOLE OF THE UNEXPIRED PERIOD OF SERVICE - ONUS OF PROVING THAT THERE EXISTED MEANS OF REMEDYING THE INCONVENIENCE CAUSED BY THE BREACH LIES ON THE DEFENDANT - EXTENT OF THE EFFORTS WHICH THE PLAINTIFF MAY BE BOUND TO MAKE IN ORDER TO MITIGATE THE LOSS ARISING FROM THE BREACH IS TO BE REASONABLY CONSTRUED AND CAN ONLY BE IMPOSED ON THE PLAINTIFF WHERE IT CAN PRACTICALLY TAKE EFFECT.
Fact of the Case:
The plaintiff, a retired railway employee, was employed by the defendants as the General Manager of their barrel factory in Bombay for a period of five years. After working for about a year, the plaintiff was asked to work at his own house instead of working at the office, and that the necessary papers would be sent to his house. When the plaintiff reminded the defendants about the increment in salary that had become payable to him on completing a year's service, he received the defendants' letter alleging that he had refused to accept the work which was assigned to him at the company's office at Calcutta and the defendants had, therefore, been constrained to relieve the plaintiff of his service with effect from the 1st April 1963. The plaintiff filed a suit claiming the full salary and allowances payable for the remaining period of his contract of service with the defendants as damages for breach of contract by the defendants.
Finding of the Court:
The court held that the termination of the plaintiff's services by the defendants was wrongful and that the plaintiff was entitled to damages for the full unexpired period of service. The court also held that the onus of proving that there existed means of remedying the inconvenience caused by the breach lay on the defendants and that the defendants had failed to discharge this onus. The court further held that the extent of the efforts which the plaintiff may be bound to make in order to mitigate the loss arising from the breach is to be reasonably construed and can only be imposed on the plaintiff where it can practically take effect.
Issues: 1. To what amount, if any, is the plaintiff entitled as and by way of damages? 2. Whether the plaintiff was at all material times bound and liable to mitigate the said alleged damages and has deliberately not done so as alleged in paragraph 9 of the Written Statement. 3. To what relief, if any, is the plaintiff entitled? 4. And Generally.
Ratio Decidendi: 1. The normal measure of damages for wrongful termination of a contract of employment for a fixed term is the salary for the whole of the unexpired period of service. 2. The onus of proving that there existed means of remedying the inconvenience caused by the breach lies on the defendant. 3. The extent of the efforts which the plaintiff may be bound to make in order to mitigate the loss arising from the breach is to be reasonably construed and can only be imposed on the plaintiff where it can practically take effect.
Final Decision: The court passed a decree in favor of the plaintiff against the defendants for the sum of Rs. 86,374 by way of damages inclusive of interest from 12th February 1967 till judgment, and for further interest on the sum of Rs.78,796 at the rate of 6 percent per annum from the date of this judgment till payments.
2. In view of the fact that it is now conceded that the termination of the plaintiffs services by the defendants was wrongful, it is not really necessary for me to refer to the defences that are to be found in the Written Statement in regard to the merits of the controversy between the parties. In paragraph 9 of the Written Statement, the defendants have denied the plaintiffs right to the damages claimed by him and have pleaded that in any event, the plaintiff was bound and liable to mitigate the alleged damages and was not entitled to claim the full amount Rs. 92,019.54 or any part thereof, or to claim inte