SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2007 Supreme(Bom) 708

HI IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION
R.M.S. KHANDEPARKAR & D.G. KARNIK, JJ.
Pawan Hans Helicopter Ltd., - Appellants
Versus
Messers Associated Construction - Respondents
APPEAL NO.840 OF 1999
IN
ARBITRATION PETITION NO.106 OF 1997
AND
APPEAL NO.1455 OF 1999
IN
ARBITRATION PETITION NO.108 OF 1997
Decided on: JUNE 07, 2007

Advocates:
Advocate Appeared
Shri S.U. Kamdar with Ms Chhaya Shah & Shri Sudeep Dasgupta i/b M/s. Bhasin & & Co. for the Appellants in both the
Appeals.
Sarvasri Pradip Sancheti with Karthik Somasundaram i/b M/s. Paras Kuhad & Associates for the Respondents in
both the Appeals.

Headnote:Arbitration Act, 1940 - Sections 30 and 33 - Arbitral award - Arbitration agreement - Absence of any escalation clause in agreement - Escalation charges can- not be granted by Arbitrator in contravention of arbitration agreement - If granted, he misconducted himself - Arbitral award can be interfered with by Court. - It is apparent that the arbitrator clearly travelled beyond the terms of the contract in relation to the claim made by the respondents for the escalation charges for the period after the expiry of the original period under the contract.

       Once it is clear that the respondents are not entitled to claim escalation charges, and the entire dispute, which is the subject-matter of the appeals being related to the escalation charges, the impugned orders, to the extent they confirm the award in relation to the escalation charges, are liable to be set aside.

       Arbitration Act, 1940 - Sections 30 and 33 - Arbitration agreement - Arbitrator bound by terms of agreement between parties - Arbitrator, a technical expert in field - Yet he cannot travel beyond periphery of contract. - Merely because the arbitrator happens to be a technical expert in the field, that would not permit him to travel beyond the periphery of the contract. An arbitrator is always bound by the terms of the agreement between the parties.

JUDGMENT

(Per R.M.S.Khandeparkar, J.):

1. Since common questions of law and facts arise in both these appeals, they were heard together and are being disposed of by this common judgment.

2. Pursuant to the allotment of work for construction of compound wall and for construction of a bridge over a nullah to the respondents, respective work contracts were entered into between the parties. The work in both the cases was required to be completed within a specified time. However, since it could not be completed within the said period, the time for completion of the work was extended. Consequent to the dispute arising between the parties, same was referred to arbitration in terms of the arbitration clause in the agreements. The learned arbitrator had held that the respondents would be entitled to claim 15% escalation charges as against the 30% escalation charges claimed by the respondents for the period beyond the expiry of the contractual period. As the appellants herein were not satisfied with the awards, they preferred petition under Sections 30 and 33 of the Arbitration Act, 1940, herein after referred to as "the said Act", for setting aside of the award. Consequently, the awards were partially modified to the benefit of the respondents. Being dissatisfied, the appellants have preferred these appeals.

3. The challenge to the impugned judgments and consequently to the awards is three-fold: firstly, that the learned arbitrator could not have granted the claim for escalation of rates made by the respondents and, secondly, that the contract between the parties does not provide for second final bill and therefore no claim based on the second final bill could have been allowed by the learned arbitrator and thirdly that the arbitrator could not have entertained the dispute having been raised beyond the period of limitation. The challenge to the awards regarding grant of the claim for escalation of rates is on two grounds: firstly, that the claim could not have been granted in view of Clauses 18 and 34 of the agreement between the parties and secondly, that the respondents had already issued "No Due Certificate" and, therefore, any claim made after the issuance of such certificate could not have been granted.

4. As regards the first ground of challenge to the grant of escalation charges to the respondents, it is the case of the appellants that the escalation charges granted are for the period subsequent to the contractual period which is contrary to the terms of the contract in view of Clause Nos.18 and 34. The said clauses clearly indicate that the contract price was not subject to rise or fall in prices and therefore the appellants were not liable to pay any escalation charges. Reliance is sought to be placed in the decision in the matter of New India Civil Erectors (P.) Ltd. v. Oil and Natural Gas Corporation, reported in AIR 1997 SC 980, and in the matter of Steel Authority of India Ltd. v. J.C. Budharaja, Government and Mining Contractor, reported in AIR 1999 SC 3275 as well as State of Orissa v. Sri S.C. Roy (dead) by LRs., reported in JT 2001 (5) SC 267. Secondly, it is the contention of the appellants that the terms of the contract between the parties nowhere provide for any second final bill as such and this is also very clear from the Clauses 31 and 32 of the agreement and once the respondents had submitted the final bill, and further had issued the no claim certificate, it was not open for the arbitrator to grant any claim based on the second final bill. It is their case that the contractor was obliged to incorporate all his claims under the final bill which was duly confirmed by him on issuance of the no claim certificate. In that regard, reliance is sought to be placed in the decision in the matter of Bharat Coking Coal Ltd. v. M/s. Annapurna Construction, reported in AIR 2003 SC 3660. In any case, it is the contention on behalf of the appellants that the arbitrator misconducted himself in ignoring the no claim certificate a
































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top