High Court of Judicature at Bombay
ANOOP V. MOHTA, J.
Mahanagar Gas Ltd.
Versus
M/s. Babulal Uttamchand & Co.
ARBITRATION PETITION NO.958 OF 2010
Decided on : 09-03-2012
The facts are totally distinct and distinguishable. The arbitrator and/or the Court needs to consider the terms and conditions of the contract. In that case the respondent themselves expressed inability to complete the project. The situation in the present case is totally reverse. In this case the arbitrator after considering the material on record held that the fundamental breach was committed by the petitioner that resulted into loss of profit. Once the finding is given that the petitioner’s action/inaction results into breach of contract the grant of loss of profit, based upon the Supreme Court’s recognised formula, in the present facts and circumstances, needs to be accepted. The judgments so cited because of its distinct facts and circumstances, are of a little assistance to the petitioner.
In any arbitration case which has to be decided on the contract terms between the parties. Therefore, the loss of profit granted and/or rejected in particular base that itself is not sufficient to decide such issue, without referring to the contract and the facts and circumstances of the case, between the parties. In that case there was a clause entitling the parties to delete any part of the contract at any time. The claim was of sub-contractor. As per the clause he was not entitled for damages for breach of contract. In the present case, the arbitrator has considered the contract terms and conditions and found that there was fundamental breach committed by the petitioner and, therefore, awarded loss of profit on the basis of settled and recognised formula, even noted by the Supreme Court as quoted above. Therefore, this judgment is also of no assistance to set aside the well reasoned award.
There was no question of granting claim of the respondent on both the counts. It is in principle one and the same. Therefore, there is no question of accepting the submission by counsel appearing for the petitioner that having once not granted any claim on account of loss of business opportunity for want of any evidence, and the award of the loss of profit on foundation of a reasonable expectation of profit, without evidence and/or material on record. The submission is also unacceptable.
Arbitration and Conciliation Act, 1996 - Sections 34 and 31(7)(a)(b) - Award of future interest. Since award of future interest at rate of 18% p.a., by arbitrator, during pendency of petition under Section 34 of Act is improper hence interest awarded restricted to 12% p.a.
1. The Petitioner, who is the original respondent has challenged, by petition under Section 34 of the Arbitration and Conciliation Act, 1996 (The arbitration Act) reasoned award dated 5th March, 2010 passed by the learned sole arbitrator.
2. The Petitioner awarded to the Respondent (the claimant) the work of Project Management and Construction of pipeline network for domestic supply of natural gas in the area of Santacruz by work order dated 12th October, 2002. It was for three years from the date of letter of acceptance. The value of the work was Rs.3,87,07,260.00. The Respondent accordingly mobilised requisite resources and invested huge amount. The Petitioner was responsible to provide gas connection to the individuals of area. The Respondent was required to enter into agreement with the customers. The Petitioner failed and neglected to provide gas to the customers though the pipeline work was completed by the Respondent. The delay in supply of gas was for about 18 months, resulted in non-payment by the customers and consequent non-payment for the work done to the Respondent by the Petitioner. The Respondent, therefore, suffered heavy financial losses because of breach of the terms of the contract. For various reasons including default on the part of the Petitioner, the full work could not completed in stipulated period, because of change of specifications from time to time by the Petitioner. Therefore, in view of arbitration clause, the Respondent raised claims. The Petitioner also filed counter claims. The reply and the rejoinders were filed. One witness each was examined. The learned arbitrator heard the matter, accordingly, from time to time and not granted all the respective claims except challenged in the petition.
3. On 7th August, 2008, so far as counter claim No.18 is concerned, both the parties agreed and decided to arrive at agreed figure of the balance amount payable to the claimant on account of work done (Claim No.1) and the amount payable from the claimant to the Respondent on account of Material Reconciliation Recoveries. On 5th January 2009, both the parties, under authorisation of the respective clients filed jointly signed statement informing an agreed figure of Rs.35,37,176/-as the amount payable to the Respondent on account of work done but not paid and a figure of Rs.7,17,445/-as the amount due from the respondent to the petitioner on account of recovery against material reconciliation.
4. The learned arbitrator after considering rival contentions, as well as, the material placed on record gave reasoned finding that there was undue delay in supplying the gas and changed the specifications which were most essential requirements for marketing of gas connection by the Respondent and thereby concluded that the Petitioner committed manifest breach of contract.
5. Though there was clause No.44.1 and 59.2 for extension of time for completion of the work and, accordingly, the request was made to the Petitioner, but refused to grant extension. The Petitioner in view of Andheri fire incident pending execution of the contract changed the specifications which resulted in an extra work to be executed by the Respondents. This was also an additional factor for the Respondent to claim for a revised rate for the changed specifications. The Petitioner enhanced safety norms to adopt ISO certificate which required the Respondent to procure new safety tools which also caused delay in day-to-day execution of the work. There was delay in revision of rates also and the same was done in January 2004. There was delay in the third working session as approval from requisite authority (MMRDA) could not be obtained upto January 2005.
6. The Petitioner in view of clause 10.2 and 10.3, though necessary, failed to prepare joint construction programme. The Petitioner committed many breaches that resulted in delay in execution of the work. Therefore, taking overall view and the cumulative effects of defaults the learned arbitra
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.