IN THE HIGH COURT OF BOMBAY AT NAGPUR
A.S. CHANDURKAR, J.
Central Mine Planning & Design Institute Ltd. & Another - Petitioners
Versus
M/s Anupam Rai - Respondent
First Appeal No.178 of 1998
Decided On : 08-05-2015
Arbitration Act 1940 - Construction Contract - Section 39 - Clause 9, 16, 21 - PawanHans Helicopter Ltd. vs. Messers Associated Construction 2007 (6) Mh.L.J. 255, Municipal Corporation of Greater Bombay vs. Thermal Engineering Corporation and others 1997(1) Mh.L.J. 700, Ramnath International Construction Pvt. Ltd. v. Union of India and Anr. AIR 2007 SC 509, State of Orissa v. Sudhakar Das AIR 2000 SC 1294, New India Civil Erectors (P) Ltd. v. Oil and Natural Gas Corporation AIR 1997 SC 980, Ramchandra Reddy & Co. v. State of Andhra Pradesh and others AIR 2001 SC 1523, Continental Constuction Co. Ltd. v. State of Madhya Pradesh AIR 1988 SC 1166, Associated Engineering Co. v. Government of Andhra Pradesh and another AIR 1992 SC 232, Ch. Ramalinga Reddy vs Superintending Engineer and another (1999) 9 SCC 610 and Hindustan Petroleum Corporation Limited vs. Batliboi Environmental Engineers Ltd. 2008 (1) ARB LR 166
Fact of the Case:
The appellants challenged the judgment making the Arbitrator's award rule of the Court, contesting the award of escalation charges and interest at 18% per annum. The respondent sought appointment of an Arbitrator due to disputes arising from a construction contract. The Civil Court upheld the award and made it rule of the Court, leading to the present appeal.
Finding of the Court:
The Court found that the Arbitrator did not exceed jurisdiction in awarding amounts for completion of work beyond the agreed period and confirmed the award. However, the Court set aside the interest awarded for the period prior to the date specified in the notice issued by the respondent, modifying the decree accordingly.
Issues: (1) Whether the claims awarded by the Arbitrator for completion of work beyond the agreed period are justified? (2) Whether the grant of interest at 18% per annum is liable to be interfered with?
Ratio Decidendi: The Court held that the Arbitrator did not exceed jurisdiction in awarding amounts for completion of work beyond the agreed period, considering the extensions granted by the appellants. However, the Court set aside the interest awarded for the period prior to the date specified in the notice issued by the respondent.
Final Decision: The first appeal is partly allowed, confirming the award except for the interest awarded for the period prior to the date specified in the notice issued by the respondent, which was set aside.
1. The appellants in the present appeal filed under Section 39 of the Arbitration Act 1940 (for short the said Act) have challenged the judgment dated 23-4-1998 in Special Civil Suit No.67/1992 whereby the award made by the Arbitrator was made rule of the Court.
2. The relevant facts are that the appellants had invited tenders for constructing of office, dwelling units, boundary wall etc. Pursuant to said notice, the respondent had submitted its offer and on 24-4-1986, an agreement was entered into between the appellants and the respondent for undertaking said work. Prior thereto, work order came to be issued to the respondent on 31-3-1986. The work in question was to be completed within a period of 12 months from 10-4-1986 to 9-4-1987. The work was to be carried out as per the terms agreed between the parties. Certain conditions had been stipulated in the notices inviting the tenders. On that basis, the respondent undertook the work of construction. Said work could not be completed within the stipulated period and hence, time to complete the same was extended on two occasions vide communication dated 14-5-1987 and 14-12-1987. The work came to be completed on 31-1-1988.
3. Disputes having arisen between the parties, the respondent in terms of the agreement sought appointment of an Arbitrator. By order dated 20-12-1995, the Civil Court directed the present appellants to file the arbitration agreement in Court and appointed a sole Arbitrator to adjudicate the claim of the present respondent. Pursuant thereto, arbitration proceedings took place and on 30-6-1997, the sole Arbitrator made his award and held that the respondent was entitled to a total amount of Rs.16,05,982.95/-. The award was thereafter placed before the Civil Court and the appellants filed their objection vide Exhibit.41. The objections pertained to grant of amount towards escalation and award of interest at 18% per annum. The Civil Court thereafter considered the award and the objections thereto and by judgment dated 23-4-1998 upheld said award and made it rule of the Court. This judgment is under challenge in the present appeal.
4. Shri C. S. Samudra, learned Counsel appearing for the appellants submitted that the amounts as awarded by the Arbitrator in respect of escalation charges and interest @18% per annum were not permissible under the agreement between the parties and hence, by awarding said amounts, the Arbitrator had misconducted himself. He submitted that as per Clause 9 of the tender conditions, time had been made an essence of contract and, therefore, it was necessary for the respondent to have completed the work in question within stipulated time. He submitted that as per Clause 21 thereof, no escalation was permissible on account of fluctuation in market prices of labour and material during the currency of the contract. Similarly, as per Clause 16, it was agreed that the respondent would not be entitled to any compensation for any loss on account of delay in commencing or executing the work. He, therefore, submitted that in the absence of any agreement to provide for escalation, it was beyond the jurisdiction of the Arbitrator to award any amount of claim for said reason. In support of the said submission, the learned Counsel placed reliance on decision of the Division bench in PawanHans Helicopter Ltd. vs. Messers Associated Construction 2007 (6) Mh.L.J. 255, Municipal Corporation of Greater Bombay vs. Thermal Engineering Corporation and others 1997(1) Mh.L.J. 700, Ramnath International Construction Pvt. Ltd. v. Union of India and Anr. AIR 2007 SC 509, State of Orissa v. Sudhakar Das AIR 2000 SC 1294, New India Civil Erectors (P) Ltd. v. Oil and Natural Gas Corporation AIR 1997 SC 980, Ramchandra Reddy & Co. v. State of Andhra Pradesh and others AIR 2001 SC 1523, Continental Constuction Co. Ltd. v. State of Madhya Pradesh AIR 1988 SC 1166, Associated Engineering Co. v. Government of Andhra Pradesh and another AIR 1992 SC 232, Ch. Ramalin
Pawan Hans Helicopter Ltd. vs. Messers Associated Construction 2007 (6) Mh.L.J. 255
Ramnath International Construction Pvt. Ltd. v. Union of India and Anr. AIR 2007 SC 509
State of Orissa v. Sudhakar Das AIR 2000 SC 1294
New India Civil Erectors (P) Ltd. v. Oil and Natural Gas Corporation AIR 1997 SC 980
Ramchandra Reddy & Co. v. State of Andhra Pradesh and others AIR 2001 SC 1523
Continental Constuction Co. Ltd. v. State of Madhya Pradesh AIR 1988 SC 1166
Associated Engineering Co. v. Government of Andhra Pradesh and another AIR 1992 SC 232
Ch. Ramalinga Reddy vs Superintending Engineer and another (1999) 9 SCC 610
Oil and Natural Gas Corporation Ltd. Bombay vs. Essar Steel Ltd. Bombay 2002(1) Mh.L.J. 699
Associated Construction vs Pawanhans Helicopters Limited (2008) 16 SCC 128
Asian Techs Limited vs. Union of India and others (2009) 10 SCC 354
K. N. Sathyapalan vs State of Kerala (2007) 13 SCC 43
Indu Engineering & Textiles Ltd. vs. Delhi Development Authority (2001) 5 SCC 691
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.