2018 Supreme(Bom) 1277
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Naresh H. Patil, G. S. Kulkarni, JJ.
In the matter between : Ahluwalia Contracts (India) Ltd. – Appellant
Versus
Bellamy Constructions & Infrastructure Pvt. Ltd. and anr. – Respondents
Notice of Motion Lodging No. 596 of 2018 In Commercial Appeal Lodging No. 279 of 2018 Along With Commercial Appeal Lodging No. 279 Of 2018 In Commercial Suit No. 65 of 2013 With Notice of Motion Lodging No. 597 Of 2018 (For Stay)
Decided On : 06-09-2018
Subject
Banking Law - BANK GUARANTEE
Act Referred
CONTRACT ACT : S.126, S.28
Headnote
Companies Act, 1956 – Civil Procedure Code, - Order I Rule 10 - Appeal for challenging - Commercial Suit - Seeking a decree for a sum - Respondent No.1 filed Commercial Suit against respondent no. 2 - Plaintiff contends in said Suit that it is a company registered under Companies Act, 1956 and engaged in business of real estate development and construction activities - Plaintiff is the owner of land - Under Letter of Intent addressed by the plaintiff to Ahluwalia Contracts - Appellant herein and confirmed by ACIL, plaintiff confirmed their intention to enter into a contract with ACIL for supply, erection, protection and commissioning of Shell and Core Works at Litolier Hotel project of plaintiff - Under Letter of Intent it was prescribed that 13% of contract value would be paid by plaintiff to ACIL as a mobilization advance against on-demand bank guarantees for an equivalent amount - ACIL was to commence work at site on 22nd July 2011 and complete it by 22nd May, 2012 - Whether encashment of bank guarantee would cause any “irretrievable injury” or “irretrievable injustice” - There is no plea of any “special equities” by appellant in its favour – Held, Court are not inclined to accept submission made by learned counsel appearing for the appellant that in view of order passed by learned Single Judge, respondent no.1 could not have invoked bank guarantees thereafter - Period of nine months lapsed after initial time limit prescribed under bank guarantee - All other terms and conditions remain unchanged - Contractual period of invocation of bank guarantees stood extended by consent of parties and now it would not be permissible and appropriate for appellant to raise an issue of time limit of invocation of bank guarantees – We find sufficient force in submissions of learned Senior Counsel appearing for respondent no.1 – plaintiff that bank guarantee itself is an independent contract and respondent no.1 – plaintiff was entitled to invoke bank guarantees which was unconditional - Court find that invocation of bank guarantees was done in accordance with terms of contract and bank guarantees - Invocation letter is part of compilation, which states that respondent no.1 – plaintiff would like to encash nine bank guarantees which are detailed in communications - Learned Single Judge has properly construed terms of bank guarantees, contractual relationship between appellant and respondent no.1 and reached conclusions which are reasonable and proper - Court do not see any perversity in view adopted by learned Single Judge - View taken by learned Single Judge is a possible one and does not call for any interference at appellate stage - After pronouncement of judgment, learned Senior Counsel appearing for appellant prays for maintaining status quo as on today in respect of encashment of bank guarantees for a period of ten weeks - None present for respondents - Court direct that status quo as on today in respect of encashment of bank guarantees be maintained for a period of four weeks from today – Appeal disposed of.
For the Appellant :Mr. Rajiv Kumar, Senior Advocate a/w Mr. Mayur Khandeparkar, Mr. Satyasrikant Vutha, Ms. Smiti Tewari, Mr. Dhiraj Mhetre, Ms. Nupur Jalan i/by Khaitan Legal Associates,
Ms. Rajani Iyer, Senior Advocate a/w Mr. Vaibhav P. Bajpai I/by Pramod Bajpai for respondent no.1 – Org. Plaintiff.
For the Respondent: Ms. Sandhya Nambidi I/by Law Focus
Naresh H. Patil,
1. The Notice of Motion (L) No. 596 of 2018 is filed seeking leave to appeal for challenging the Judgment and Order dated 14th & 15th February, 2018 delivered by the learned Single Judge in Commercial Suit No. 65 of 2013 and for condoning the delay in filing the appeal.
2. The respondent No.1 - Bellamy Constructions & Infrastructure Pvt. Ltd., Original Plaintiff, filed Commercial Suit No. 65 of 2013 against the respondent no. 2 – Bank of India, Original sole Defendant seeking a decree for a sum of Rs.4.80 crores. The plaintiff contends in the said Suit that it is a company registered under the Companies Act, 1956 and engaged in the business of real estate development and construction activities. The plaintiff stated that plaintiff is the owner of land bearing CTS No.25A of Chakala and CTS No.215/B of Mulgaon Mahakali Caves Road, Andheri-Kurla Road, Andheri (East), Mumbai – 400 093. Under the Letter of Intent dated 8th July, 2011 addressed by the plaintiff to Ahluwalia Contracts (India) Ltd., applicant/appellant herein, (hereinafter referred to as “ACIL”) and confirmed by ACIL, the plaintiff confirmed their intention to enter into a contract with ACIL for supply, erection, protection and commissioning of the Shell and Core Works at the Litolier Hotel project of the plaintiff at Andheri (East), Mumbai for total contract value of Rs.42,00,00,000/-. Under the Letter of Intent dated 8th July, 2011 it was prescribed that 13% of the contract value would be paid by the plaintiff to ACIL as a mobilization advance against on-demand bank guarantees for an equivalent amount. The ACIL was to commence the work at site on 22nd July 2011 and complete it by 22nd May, 2012.
3. Consequent to the contract and Letter of Intent, ACIL submitted 9 (nine) bank guarantees all dated 18th July, 2011 issued by the Defendant – Bank of Inida in favour of the plaintiff for amounts aggregating to Rs.4,46,00,000/-. The details of the bank guarantees i.e. numbers, dates and amounts are mentioned in para 5 of the plaint. Copies of the bank guarantees are also annexed to the plaint.
4. It is the plaintiff's contention that relying on the said nine bank guarantees, all dated 18th July, 2011, the plaintiff paid to ACIL mobilization advances of Rs.4,46,00,000/-. Under four letters all dated 17th January, 2012, addressed by the defendant to the plaintiff, the period of validity of the first four bank guarantees was extended upto 17th April, 2012 from 17th January, 2012. The period of validity of nine bank guarantees was extended upto 17th July, 2012. The communications issued in this behalf indicated that the defendant was liable to pay the guaranteed amount to the plaintiff on the plaintiff serving upon the defendant a written claim or demand on or before 17th July, 2012 and all other terms and conditions of the original bank guarantees remain unchanged.
5. The plaintiff contends that ACIL failed to observe, perform and fulfill the terms of the contract between the plaintiff and ACIL. The subject work was not completed in time and, therefore, by letter dated 17th July, 2012 addressed to defendant, the plaintiff claimed and demanded encashment of the said nine bank guarantees dated 18th July, 2011 for a total sum Rs.4,46,00,000/-. The plaintiff called upon the defendant to remit the full payment of the said amount.
6. The defendant by its communication dated 18th July, 2012 informed the plaintiff that the invocation of the nine bank guarantees, issued by the defendant in favour of the plaintiff, was not in conformity with the terms of the bank guarantees and it would not be possible for the defendant to accede to the request of the plaintiff.
7. On 19th July, 2012, the ACIL filed Arbitration Petition (L) No. 964 of 2012 in this Court against the plaintiff and the defendant. According to the plaintiff, a statement was made before the court that since ACIL has objected to the contents of the letter invoking the bank guarantees, the plaintiff shall i