IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Naresh H Patil, G.S. Kulkarni, JJ.
Ahluwalia Contracts (india) Ltd - Appellant
Versus
Bellamy Constructions And Infrastructure Pvt Ltd And Anr - Respondent
Notice Of Motion Lodging No. 596 of 2018, 597 of 2018; Commercial Appeal Lodging No. 279 of 2018; Commercial Suit No. 65 of 2013
Decided On : 06-09-2018
Code of Civil Procedure, 1908 - Order XXXVII – Indian Contract Act, 1872 - Section 28 - Notice Of Motion - Challenging The Judgment - Impugned Judgment - Seeking Leave - Respondent No-1 - Bellamy Constructions & Infrastructure Pvt- Ltd- Original Plaintiff filed Commercial Suit against respondent no- 2 - Bank of India Original sole Defendant seeking a decree for a sum of - Plaintiff contends in said Suit that it is a company registered under Companies Act 1956 and engaged in business of real estate development and construction activities - It is plaintiffs contention that relying on said nine bank guarantees all plaintiff paid to ACIL mobilization advances - Under four letters all addressed by defendant to plaintiff period of validity of first four bank guarantees was extended upto from period of validity of nine bank guarantees was extended - Communications issued in this behalf indicated that defendant was liable to pay guaranteed amount to plaintiff on plaintiff serving upon defendant a written claim or demand on or before and all or terms and conditions of original bank guarantees remain unchanged – Held, Learned Single Judge framed issues and has referred to relevant clauses of bank guarantee and record- In of judgment while referring to relevant clauses of bank guarantee learned Single Judge observed that guarantee is a continuing guarantee man to continue by its own force until events noted occur- Clause 11 suggests guarantee to be in force until of Virtual Completion Certificate under Contract - It was further observed that re was a specific stipulation in Clause which countenances demand or claim under guarantee within nine months from expiry of guarantee - learned Single Judge observed that one has to construe guarantee and make a sense out of it learned Single Judge has properly construed terms of bank guarantees contractual relationship between appellant and respondent no-1 and reached conclusions which are reasonable and proper - Court do not see any perversity in view adopted by learned Single Judge - appeal dismissed
JUDGMENT
Naresh H. Patil, A.C.J. - The Notice of Motion (L) No. 596 of 2018 is filed seeking leave to appeal for challenging the Judgment and Order dated 14th & 15th February, 2018 delivered by the learned Single Judge in Commercial Suit No. 65 of 2013 and for condoning the delay in filing the appeal.
2. The respondent No.1 - Bellamy Constructions & Infrastructure Pvt. Ltd., Original Plaintiff, filed Commercial Suit No. 65 of 2013 against the respondent no. 2 - Bank of India, Original sole Defendant seeking a decree for a sum of Rs. 4.80 crores. The plaintiff contends in the said Suit that it is a company registered under the Companies Act, 1956 and engaged in the business of real estate development and construction activities. The plaintiff stated that plaintiff is the owner of land bearing CTS No.25A of Chakala and CTS No.215/B of Mulgaon Mahakali Caves Road, AndheriKurla Road, Andheri (East), Mumbai - 400 093. Under the Letter of Intent dated 8th July, 2011 addressed by the plaintiff to Ahluwalia Contracts (India) Ltd., applicant/appellant herein, (hereinafter referred to as "ACIL") and confirmed by ACIL, the plaintiff confirmed their intention to enter into a contract with ACIL for supply, erection, protection and commissioning of the Shell and Core Works at the Litolier Hotel project of the plaintiff at Andheri (East), Mumbai for total contract value of Rs. 42,00,00,000/-. Under the Letter of Intent dated 8th July, 2011 it was prescribed that 13% of the contract value would be paid by the plaintiff to ACIL as a mobilization advance against on-demand bank guarantees for an equivalent amount.
The ACIL was to commence the work at site on 22nd July 2011 and complete it by 22nd May, 2012.
3. Consequent to the contract and Letter of Intent, ACIL submitted 9 (nine) bank guarantees all dated 18th July, 2011 issued by the Defendant - Bank of Inida in favour of the plaintiff for amounts aggregating to Rs. 4,46,00,000/-. The details of the bank guarantees i.e. numbers, dates and amounts are mentioned in para 5 of the plaint. Copies of the bank guarantees are also annexed to the plaint.
4. It is the plaintiff''s contention that relying on the said nine bank guarantees, all dated 18th July, 2011, the plaintiff paid to ACIL mobilization advances of Rs. 4,46,00,000/-. Under four letters all dated 17th January, 2012, addressed by the defendant to the plaintiff, the period of validity of the first four bank guarantees was extended upto 17th April, 2012 from 17th January, 2012. The period of validity of nine bank guarantees was extended upto 17th July, 2012. The communications issued in this behalf indicated that the defendant was liable to pay the guaranteed amount to the plaintiff on the plaintiff serving upon the defendant a written claim or demand on or before 17th July, 2012 and all other terms and conditions of the original bank guarantees remain unchanged.
5. The plaintiff contends that ACIL failed to observe, perform and fulfill the terms of the contract between the plaintiff and ACIL. The subject work was not completed in time and,therefore, by letter dated 17th July, 2012 addressed to defendant, the plaintiff claimed and demanded encashment of the said nine bank guarantees dated 18th July, 2011 for a total sum Rs. 4,46,00,000/-. The plaintiff called upon the defendant to remit the full payment of the said amount.
6. The defendant by its communication dated 18th July, 2012 informed the plaintiff that the invocation of the nine bank guarantees, issued by the defendant in favour of the plaintiff, was not in conformity with the terms of the bank guarantees and it would not be possible for the defendant to accede to the request of the plaintiff.
7. On 19th July, 2012, the ACIL filed Arbitration Petition (L) No. 964 of 2012 in this Court against the plaintiff and the defendant. According to the plaintiff, a statement was made before the court that since ACIL has objected to the contents of the letter invoking the bank guarantees, the pl
Himadri Chemicals Industries Ltd. Vs. Coal Tax Refining Co.
Hindustan Construction Co. Ltd. Vs. State of Bihar
Mahatma Gandhi Sahakari Karkhana Vs. National Heavy Engg. Co.-op. Ltd.
Mula Sahakari Sakhar Karkhana Ltd. Vs. State Bank of India
Mumbai International Airport Vs. Regency Convention Centre
State Bank of India Vs. Mula Sahakari Sakhar Karkhana
State of Maharashtra Vs. National Construction Co.
U. P. Co-op. Federation Ltd. Vs. Singh Consultants and Engineers
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.